HRIT: QUESTIONS AND ANSWERS
QUESTION
We have reviewed Solicitation 1332KP18QNEEB0004. Section C4 requires 30 day delivery.
Due to current manufacturing backlog, expected delivery is actually 90 days. Please indicate if this is acceptable.
ANSWER
The 90 day delivery date is acceptable.