S01 FBO Questions and Answers.pdf
PDF 93 KB Posted
- Attached to
- Administrative Support Services - USDA NRCS - Mississippi Federal contract opportunity
- Solicitation number
- 12FPC120MS0001
About this file
This document contains questions and answers regarding solicitation number 12FPC120MS0001 for Administrative Support Services with the USDA NRCS in Mississippi. The solicitation seeks quotes from 8(a) vendors only to provide administrative support staff to work in USDA-NRCS area and field offices across 74 counties in Mississippi for a one year base period and four one year option periods. The positions will provide support services across multiple counties as determined by NRCS. The incumbent contractor is All-Pro Placement Service, Inc and one position is currently vacant in Forrest County. While experience with NRCS programs is preferred, federal government administrative support experience is required. The 2000 hours per position is equivalent to one full-time person and is intended to cover regular hours plus potential overtime needs.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S01 - FBO Questions and Answers updated 09162020.pdf | ||
| S01 - FBO Questions and Answers updated 09152020.pdf | ||
| S01 - FBO Questions and Answers updated 09142020.pdf | ||
| S01 - Administrative Services - Mississippi - Revised 09142020.pdf | ||
| S01 - Attachment C - Wage Rates for Mississippi Administrative Services.pdf | ||
| S01 - Attachment F - Pricing Charts Mississippi Adminstrative Services.xlsx | XLSX spreadsheet | |
| S01 - Administrative Services - Mississippi - Revised.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
Mississippi Administrative Services
12FPC120MS0001
Question #1:
Is this a new requirement or is there an incumbent contractor?
Answer #1:
This service is currently being provided under contract 121A2318P0184 and the vendor is All- Pro Placement Service, Inc.
Question #2:
Is this intended for 8(a) vendors only?
Answer #2:
Yes, only SBA approved 8(a) vendors can provide quotes.
Question #3:
Is it permissible for Offerors' to price/ bill a Program Manager? If Yes, please confirm it is permissible to add this row to Attachment F.
Answer #3:
Yes. Per C.10.4 we ask that you have a project manager available. So, it is acceptable to price/bill for a project manager.
Question #4:
As this is a SCA contract, I did not see any first right of refusal for example in the solicitation. I would assume since it is an SCA contract, we do have to offer first right of refusal, correct?
Answer #4:
As for the first right of refusal, Executive Order 13495 was revoked in October 2019, which required that a successor in federal service contractors and subcontractors offer their predecessor’s employees who were employed under the previous contract, a right of first refusal to those employment positions for the new contract. In other words, federal service contractors commencing a new government contract are no longer required to offer employment to those working on the expiring contract. Therefore, it is not included in this solicitation.
Question #5:
Section L.5.1.2 states: Provide references for experience per C.6.2 to support past/present performance. Section C.6.2 states: Contractor shall have a minimum of one-year experience in providing this service or similar and provide references. Section M.3.3.1.2 states: The Government will also evaluate the offeror’s knowledge of the work.
Does this imply for the contractor to be technically acceptable the contractor has to have experience in the NRCS Farm Bill programs and related systems (Protracts, ArcGIS, etc.) or experience providing administrative support services to USDA and NRCS?
Answer #5:
No this does not mean they have to have experience in NRCS Farm Bill Programs. Would it be preferred yes, but not required. What the experience means is that you have experience in working with federal government agencies providing administrative support. USDA and NRCS experience are desirable but not required. Federal Government experience is a must.
Question #6:
Please explain basis for 2000 hours. Is the 2000 productive hours working at USDA? Per Service Contract Act, 2000 hours per year is not possible because employees are entitled to 2 weeks leave and 6 days of sick leave. Max productive hours would be 1860 when you add in 10 federal holidays. Please explain basis for 2000 hours per year.
Answer #6:
The max hours would typically be 1860 but we have factored in some extra time incase overtime is needed. So, 2000 is the max hours we would pay in a year but you are right they will most likely only work 1860.
Question #7:
Are all positions filled on current contract?
Answer #7:
All but one is currently filled on the current contract.
Question #8:
Which positions are vacant on current contract?
Answer #8:
One of the positions in Forrest County is currently vacant.
Question #9:
Does the 2000 hours per year reflect one full time person?
Answer #9:
Yes, the 2000 hours is one full-time person.