1294TZ18Q0032_7.31.18.pdf
PDF 1 MB Posted
- Attached to
- Palace Station Improvements
- Solicitation number
- 1294TZ18Q0032
About this file
Update page 8; SITE VISIT: A site visit is scheduled for Thursday August 9, 2018 @1000 AM with Terri Beard/Ann May, Phone: (928) 443-8177/(928) 443-8017.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pre-bid_questions_8-9-18.pdf | ||
| 1294TZ18Q0032_7.26.18.pdf | ||
| Wage_Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1294TZ18Q0032
1. REQUEST NO.
5a. ISSUED BY
NAME
a. NAME
c. STREET ADDRESS
d. CITY
10. PLEASE FURNISH QUOTATIONS TO
THE ISSUING OFFICE IN BLOCK 5a ON
OR BEFORE CLOSE OF BUSINESS (Date)
2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.
UNDER BDSA REG. 2
AND/OR DMS REG.1
RATING
6. DELIVERY BY (Date)
7. DELIVERY
9. DESTINATION
a. NAME OF CONSIGNEE
b. STREET ADDRESS
PAGE OF PAGES
5b. FOR INFORMATION CALL: (No collect calls)
TELEPHONE NUMBER
AREA CODE NUMBER
8. TO:
b. COMPANY
e. STATE f. ZIP CODE
c. CITY
d. STATE e. ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
THIS RFQ
REQUEST FOR QUOTATION
(THIS IS NOT AN ORDER)
IS IS NOT A SMALL BUSINESS SET ASIDEX
07/23/2018 901340
1 6
WESTERN ZONE CP
2324 E MCDOWELL ROAD
PHOENIX AZ 85006-2440
USDA FOREST SERVICE
60 Days After Notice to Proceed
BRADSHAW RANGER DISTRICT
2230 E HIGHWAY 69
PRESCOTT
AZ 86301-5657
602 225.5350DAVID WATSON
08/15/2018 1400 AZT
FOB DESTINATION
OTHER
(See Schedule)X
ITEM NO.
(a)
SUPPLIES/SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
Palace Station Improvements
Palace Station Improvements Delivery: 60
Days After Notice to Proceed
12. DISCOUNT FOR PROMPT PAYMENT
a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS
NUMBER PERCENTAGE
NOTE: Additional provisions and representations
13. NAME AND ADDRESS OF QUOTER
b. STREET ADDRESS
c. COUNTY
d. CITY e. STATE f. ZIP CODE
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
16. SIGNER
a. NAME (Type or print)
c. TITLE (Type or print)
a. NAME OF QUOTER
AREA CODE
NUMBER
15. DATE OF QUOTATION
b. TELEPHONE are are not attached
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition not usable
STANDARD FORM 18 (REV. 6-95)
Prescribed by GSA - FAR (48 CFR) 53.215-1(a)
B - Prices/Costs Schedule of Items Clauses
C - Description/Specifications/Statement of Work Clauses
E - Inspection and Acceptance Clauses
F - Deliveries or Performance Clauses
I - Contract Clauses Clauses
J - List of Documents, Exhibits, and Other Attachments List of Documents, Exhibits, and Other Attachments Clauses
K - Representations, Certifications, and Other Statementsof Offerors or Respondents Clauses
L - Instructions, Conditions, and Notices to Offerors or Respondents Clauses
B - Prices/Costs Schedule of Items
Clauses
C - Description/Specifications/Statement of Work
Clauses
E - Inspection and Acceptance
Clauses
52.246-12 Inspection of Construction. (AUG 1996)
F - Deliveries or Performance
Clauses
52.242-14 Suspension of Work. (APR 1984)
I - Contract Clauses
Clauses
52.204-7 System for Award Management. (OCT 2016)
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015)
52.211-6 Brand Name or Equal (Aug 1999)
52.211-18 Variation in Estimated Quantity. (APR 1984)
52.219-27 Notice of Service-Disabled Veteran-Owned Small Business Set-Aside. (NOV 2011)
52.222-3 Convict Labor. (JUN 2003)
52.222-6 Construction Wage Rate Requirements. (MAY 2014)
52.222-7 Withholding of Funds. (MAY 2014)
52.222-8 Payrolls and Basic Records. (MAY 2014)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance With Copeland Act Requirements. (FEB 1988)
52.222-11 Subcontracts (Labor Standards). (MAY 2014)
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (MAY 2014)
52.222-21 Prohibition of segregated facilities. (APR 2015)
52.222-26 Equal Opportunity. (SEP 2016)
52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)
52.222-35 Equal Opportunity for Veterans. (OCT 2015)
52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014)
52.222-37 Employment Reports on Veterans. (FEB 2016)
52.223-6 Drug-Free Workplace. (MAY 2001)
52.224-1 Privacy Act Notification. (APR 1984)
52.224-2 Privacy Act. (APR 1984)
52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)
52.228-14 Irrevocable Letter of Credit. (NOV 2014)
52.228-15 -- Performance and Payment Bonds -- Construction
52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014)
52.232-27 Prompt Payment for Construction Contracts. (JAN 2017)
52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL 2013)
52.233-1 Disputes. (MAY 2014)
52.233-3 Protest After Award. (AUG 1996)
52.236-2 Differing Site Conditions. (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
52.236-5 Material and Workmanship. (APR 1984)
52.236-6 Superintendence by the Contractor. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.236-8 Other Contracts. (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.
(APR 1984)
52.236-10 Operations and Storage Areas. (APR 1984)
52.236-11 Use and Possession Prior to Completion. (APR 1984)
52.236-12 Cleaning Up. (APR 1984)
52.236-13 Accident Prevention. (NOV 1991)
52.236-15 Schedules for Construction Contracts. (APR 1984)
52.236-21 Specifications and Drawings for Construction. (FEB 1997)
52.236-26 Preconstruction Conference. (FEB 1995)
52.243-5 Changes and Changed Conditions. (APR 1984)
52.244-6 Subcontracts for Commercial Items. (NOV 2017)
(a) Definitions. As used in this clause-
Commercial item and commercially available off-the-shelf item have the meanings contained in Federal Acquisition Regulation 2.101, Definitions.
Subcontract includes a transfer of commercial items between divisions, subsidiaries, or affiliates of the Contractor or subcontractor at any tier.
(b) To the maximum extent practicable, the Contractor shall incorporate, and require its subcontractors at all tiers to incorporate, commercial items or nondevelopmental items as components of items to be supplied under this contract.
(c)(1) The Contractor shall insert the following clauses in subcontracts for commercial items:
(i) 52.203-13, Contractor Code of Business Ethics and Conduct (OCT 2015) (41 U.S.C. 3509), if the subcontract exceeds $5.5 million and has a performance period of more than 120 days. In altering this clause to identify the appropriate parties, all disclosures of violation of the civil False Claims Act or of Federal criminal law shall be directed to the agency Office of the Inspector General, with a copy to the Contracting Officer.
(ii) 52.203-15, Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111-5), if the subcontract is funded under the Recovery Act.
(iii) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017).
(iv) 52.219-8, Utilization of Small Business Concerns (NOV 2016) (15 U.S.C.
637(d)(2) and (3)), if the subcontract offers further subcontracting opportunities.
(v) 52.219-8, Utilization of Small Business Concerns (OCT 2014) (15 U.S.C.
637(d)(2) and (3)), if the subcontract offers further subcontracting opportunities.
If the subcontract (except subcontracts to small business concerns) exceeds $700,000 ($1.5 million for construction of any public facility), the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.
(vi) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
(vii) 52.222-26, Equal Opportunity (SEP 2016) (E.O. 11246).
(viii) 52.222-35, Equal Opportunity for Veterans (OCT 2015)(38 U.S.C.
4212(a));
(ix) 52.222-36, Equal Opportunity for Workers with Disabilities (JUL 2014) (29 U.S.C. 793).
(x) 52.222-37, Employment Reports on Veterans (FEB 2016) (38 U.S.C. 4212).
(xi) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) (E.O. 13496), if flow down is required in accordance with paragraph (f) of FAR clause 52.222-40.
(xii)(A) 52.222-50, Combating Trafficking in Persons (MAR 2015) (22 U.S.C.
chapter 78 and E.O. 13627).
(B) Alternate I (MAR 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).
(xiii) 52.222-55, Minimum Wages under Executive Order 13658 (DEC 2015), if flowdown is required in accordance with paragraph (k) of FAR clause 52.222- 55.
(xiv)(A) 52.224-3, Privacy Training (JAN 2017) (5 U.S.C. 552a) if flow down is required in accordance with 52.224-3(f).
(B) Alternate I (JAN 2017) of 52.224-3, if flow down is required in accordance with 52.224-3(f) and the agency specifies that only its agency-provided training is acceptable).
(xv) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017) (E.O. 13706), if flowdown is required in accordance with paragraph (m) of FAR clause 52.222-62.
(xvi) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).
(xvii) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (DEC 2013), if flow down is required in accordance with paragraph (c) of FAR clause 52.232-40.
(xviii) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C. App. 1241 and 10 U.S.C. 2631), if flow down is required in accordance with paragraph (d) of FAR clause 52.247-64.
(2) While not required, the Contractor may flow down to subcontracts for commercial items a minimal number of additional clauses necessary to satisfy its contractual obligations.
(d) The Contractor shall include the terms of this clause, including this paragraph (d), in subcontracts awarded under this contract.
(End of clause)
52.246-21 Warranty of Construction. (APR 1984)
52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form). (APR 1984)
52.249-10 Default (Fixed-Price Construction). (APR 1984)
452.232-70 Reimbursement for Bond Premiums - Fixed-Price Construction Contracts. (NOV 1996)
452.236-70 Additive or Deductive Items. (FEB 1988)
452.236-74 Control of Erosion, Sedimentation, and Pollution. (NOV 1996)
J - List of Documents, Exhibits, and Other Attachments
List of Documents, Exhibits, and Other Attachments
Attachment Number Title Date
Clauses
K - Representations, Certifications, and Other Statementsof Offerors or Respondents
Clauses
L - Instructions, Conditions, and Notices to Offerors or Respondents
Clauses
452.204-70 Inquiries. (FEB 1988)
FAR 52.212-1 Instructions to Offerors -- Commercial Items (Jan 2017)
FAR 52.212-2 Evaluation -- Commercial Items (Oct 2014)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.
The following factors shall be used to evaluate offers:
Technical Past Performance
(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer’s specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
FAR 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998) This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/?q=browsefar
SECTION M--EVALUATION FACTORS FOR AWARD
A contract will be awarded to the lowest-priced technically acceptable offeror. Quotes will be evaluated for acceptability but will not be ranked using the non-cost/price factors. In order to be eligible for award, offerors must receive a rating of “acceptable” in every non-price factor. In the interest of economy and efficiency, the Government will start by evaluating the technical quote of the lowest-priced offeror and will award to that offeror if the technical quote is rated “technically acceptable”. If the lowest offeror receives a rating of “unacceptable” in any of the non-cost factors, the Government will then move on to evaluating the technical quote of the next lowest offeror and so on until a quote is rated “technically acceptable”. Therefore, the technical quote of the non-low price offerors may or may not be evaluated. The following factors will be used to determine technical acceptability:
Factor #1 – Technical Capability Technical Capability Offerors are instructed to provide information on key personnel to be used in the performance of this contract and demonstrate capability to perform janitorial services, including hiring practices, subcontracting, and the offerors plan for quality control.
Factor#2 -Past Performance Recency and relevancy of present/past performance in relation to this effort - In order to receive a rating of “acceptable” for this sub-factor, offeror must, at a minimum provide past experience on similar type contract(s). The past experience should indicate successes of the contractor in completing/meeting performance schedules and customer satisfaction. The Government considers “recent” present/past performance to be within the past 3 years. The Government considers “relevant” present/past performance to be present/past performance effort involved in similar scope and magnitude of effort and complexities this solicitation requires. The Government may also use past performance information obtained from other than the sources identified by the offeror. Information obtained from the Past Performance Information Retrieval System (PPIRS) database located at http//www.ppirs.gov is one of the sources that will be utilized. PPIRS functions as the central warehouse for performance assessment reports received from several Federal performance information collection systems and is sponsored by the DOD E-Business Office and administered by the Naval Sea Logistics Center Detachment Portsmouth.
NOTE: In accordance with FAR 15.305 (a)(2)(iv)), in the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror shall be determined to have unknown past performance. In the context of acceptability/ unacceptability, “unknown” will be considered “acceptable.” PRICE: Award will be made to the lowest priced offeror that is evaluated as “acceptable” for all non-price factors.
SITE VISIT: A site visit is scheduled for Thursday August 9, 2018 @ 10:00 AM with Terri Beard/Ann May, Phone: (928) 443-8177/(928) 443-8017. Contractors are strongly encouraged to visit the site prior to submitting quotes.
OFFERS ARE DUE BY: August 15, 2018, at 14:00 PM AZT. Please e-mail your quotation to David Watson davidwatson2@fs.fed.us.
Estimated price range is $25,000.00 to $100,000.00.
The Government intends to award a firm-fixed price task order.
PRESCOTT NATIONAL FOREST
PALACE STATION SITE IMPROVEMENTS
Prescott National Forest, Bradshaw Ranger District Page 2
Table of Contents
1. SECTION 1 - SCHEDULE OF ITEMS
2. SECTION 2 – GENERAL
2.01 PROJECT LOCATION
2.02 PROJECT REQUIREMENTS
2.03 UTILITY REQUIREMENTS
2.04 SUBMITTALS
2.05 SHOP DRAWINGS
2.06 GOVERNMENT FURNISHED PROPERTY
2.07 CONSTRUCTION SCHEDULE
2.08 PROVISIONS FOR SAFETY AND PUBLIC ACCESS
3. SECTION 3 – MOBILIZATION
3.01 SUMMARY
3.02 PROGRESS PAYMENTS:
3.03 BASIS OF PAYMENT
4. SECTION 4 – SPECIFIC PROJECT REQUIREMENTS
4.01 NEW TOILET BUILDING
4.02 NEW SOLAR SYSTEM ............................................................ ERROR! BOOKMARK NOT DEFINED.
4.03 WELL ABANDONMENT
4.04 TOILET DEMOLITION
Prescott National Forest, Bradshaw Ranger District Page 3
1. SECTION 1 - SCHEDULE OF ITEMS
Item No. Item Description Est.
Qty
Method of Measurement Unit Cost/Unit Cost-Total
Base Bid Items:
1 Mobilization 1 LSQ LS
2 Toilet Building & Vault 1 LSQ LS
Propane & Electric conduit install 1 AQ LF
5 Well Abandonment 1 LSQ LS
6 Toilet Demolition 1 LSQ LS Total Base Bid
Additive Bid Items:
1 Solar system 1 LSQ LS
Total Additive Bid
* DQ = Design Quantity, EA= Each, LF= Linear Feet, LS = Lump Sum, LSQ = Lump Sum Quantity, AQ=Actual Quantity Total Bid:
Prescott National Forest, Bradshaw Ranger District Page 4
2. SECTION 2 – GENERAL
2.01 PROJECT LOCATION
A. There are two routes that will take you to Palace Station. The road conditions vary, and it is recommended to drive a higher clearance vehicle. Four-wheel drive is not necessary unless snow is present along the roadway.
1. From Mayer: County Road 177 also known as the Mayer-Goodwin Road is reached from the town of Mayer. Turn south towards the town of Mayer off highway 69 onto
2. Central Street. Keep right on Central and then make a left turn onto Miami Street. In two blocks turn right onto E. Main Street. At the second intersection turn left onto Wicks Ave, and then another left onto Jefferson. Jefferson continues out of town and becomes County Road 177. Once you’ve traveled the length of County Road 177, you come to a junction with the Senator Highway. Take a right or North towards Prescott, and drive for another 3 miles to Palace Station.
3. From Prescott: Mount Vernon Road in downtown Prescott becomes the Senator Highway after city limits. Travel the Senator for several miles on pavement, and then on gravel until you reach Palace Station. Approximately 15 miles.
2.02 PROJECT REQUIREMENTS
A. The following items shall be constructed:
1. New Toilet and Storage Building with vault.
2. Propane and Electric conduit–New propane line connected to existing propane tank and stubbed out near cabin and electric conduit, with pull rope for future wiring, from toilet building to cabin.
3. Solar System for Cabin- additive bid item
B. The following items shall be demolished/abandoned and removed from National Forest Lands:
1. Old Toilet Building shall be removed.
2. The hand dug well shall be abandoned according to ADWR standards. All associated hardware and plumbing shall be disposed of off National Forest Lands.
C. Provide an O&M Manual
1. Compile product data and related information appropriate for Government's maintenance and operation of products furnished under the contract. The Contractor will warranty all parts and labor associated with the project for one year at the minimum per FAR 52.246-21.
2. Format: 8-1/2" x 11" on Manufacturer's original printed data or neatly typewritten - no fax paper or copies thereof.
3. Drawings: Must provide reinforced punched binder tab, bind in with text and fold larger drawings to size of text pages.
4. Cover must identify each volume with typed or printed title "OPERATING AND MAINTENANCE INSTRUCTIONS" and must list:
a. Title of Project, Year
b. Identity of separate structure as applicable.
5. Binder shall be a commercial quality, three-ring binders with durable and cleanable plastic covers with a 1” maximum ring size.
Prescott National Forest, Bradshaw Ranger District Page 5
6. There will be no separate measurement for this section. Payment for this work is incidental to other items in the contract and direct separate payment will not be made.
2.03 UTILITY REQUIREMENTS
A. For all utilities, ensure the following:
1. Electric conduit buried no less than 18” depth and no less than 1’ horizontal and vertical separation between electric and propane. If rock or abnormal digging conditions are encountered, negotiations can be made with the CO to compensate the contractor for additional time and/or equipment and can be added to the contract through a modification.
2. Provide marking Detectape® for all new underground utilities.
3. Provide appropriate backfill material. (See Section 4.01 A. 26.)
B. Propane shall be installed by professional propane installer. (The existing system is serviced by Ferrell Gas.)
C. All electrical systems shall be installed by electricians licensed in the State of Arizona.
Contractor shall submit to the Government proof of licensure at the 100% Design submittal. (permits are not necessary)
D. All well work shall be completed by a certified well driller, licensed in the State of Arizona. Contractor shall submit to the Government proof of licensure at the 100% Design submittal.
2.04 SUBMITTALS
A. Product Submittals:
1. Submittals shall be made for all items proposed to be furnished and installed. All submittals include, but not limited to, product data, samples, shop drawings, catalogs cuts and manufacturer’s literature, schedules and substitution requests.
2. Work shall not commence on any item requiring submittals until submittals are approved in writing by the COR.
3. Submit to the COR product information, as per this SOW, for any additional products incorporated during the course of Construction. Any additions will be the result of product substitution or modification and require written approval from the CO before implementation.
4. Submittals are required for the following: Toilet vault design; Screened vent pipe;
Grab bars; Toilet paper holder; Concrete mix design; Field test results for concrete slump and air entrainment; Concrete floor sealer with non-skid surface for toilet and shower areas; Metal doors and hardware; Louvered wall vents; Wall insulation;
Toilet and interior wall cover material; Exterior siding, fascia, and trim; Light fixtures; Metal roofing; Windows; Paint or Stain.
If additive bid item is included: Photovoltaic system equipment, including inverter, modules and batteries and sizing calculations;
2.05 SHOP DRAWINGS
A. All Drawings shall include proposed/final and existing systems. These drawings shall include, but are not limited to the following:
1. Toilet building
a. Scaled plan views of toilet/storage building.
Prescott National Forest, Bradshaw Ranger District Page 6
b. Provide dimensioned elevations, sections and details to show all elements of the toilet/storage building including vault and floor drains.
c. Section view of walls showing framing, lumber grade, insulation, interior and exterior finish materials and details.
d. Section view of roofing, decking, framing and lumber grade, insulation, and ceiling details.
e. Section view of porch framing and roofing.
f. Section view of concrete floor.
2. Solar System (if awarded)
a. Plan views of grounding grids. Draw all wiring and equipment to actual scale.
Make sure all devices are installed according to needs, such as grounding rods, clamps and connectors.
b. Plan views of additional pull boxes/wiring.
c. Show all mounting details, supports, and accessories needed for complete systems.
d. Provide schematic sheets for transformer/surge arrestor connections.
e. Provide all electrical sheets showing the existing, proposed and final physical layout and control schematics. Also show any connections to existing electrical components.
2.06 GOVERNMENT FURNISHED PROPERTY
A. The government shall provide and deliver the following property:
1. Toilet riser.
2.07 FACILITIES FOR CONTRACTOR USE
A. No water or electric available on site.
B. Contractor shall provide temporary sanitary facilities.
2.08 CONSTRUCTION SCHEDULE
A. Work shall not begin until September 1, 2018 or after.
2.09 PROVISIONS FOR SAFETY AND PUBLIC ACCESS
A. The cabin site and area of outbuildings across the road will be closed to the public.
Contractor is responsible for signage and barriers to keep the site closed. Forest Roads 52 and 82 shall remain open. Care shall be taken to not to disturb the historic grounds around the cabin except as needed to trench. A staging area will be designated by the COR at the start of the contract, across FR 82 in the area of the toilet to be removed.
B. The Contractor shall take all precautions deemed necessary to secure the worksites, improvements and equipment against vandalism or acts of nature and to ensure public safety. It is recommended that the Contractor make every attempt to secure the project area and to secure all equipment and tools during construction inactivity such as nights and weekends. The Government will not assume any responsibility until final acceptance of the contract.
3.
Prescott National Forest, Bradshaw Ranger District Page 7
SECTION 3 – MOBILIZATION
3.01 SUMMARY
A. This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to and from the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.
3.02 PROGRESS PAYMENTS:
A. Progress Payments will be made as follows:
1. When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.
2. When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.
3. Upon completion of all work on the project, any unpaid amount for mobilization will be paid.
4. The total of all payments shall not exceed the original contract amount for this item.
3.03 BASIS OF PAYMENT
A. Payment will be made under:
PAY ITEM DESCRIPTION PAY UNIT
Base Bid Item 1 Mobilization Lump Sum
Prescott National Forest, Bradshaw Ranger District Page 8
4. SECTION 4 – SPECIFIC PROJECT REQUIREMENTS
4.01 NEW TOILET BUILDING & VAULT
A. Construct a new stick built toilet building according to the drawings and specifications below.
1. Design building for snow load of 30 psf.
2. Install the toilet building over a 1000-1250 gallon concrete vault with holes provided for vent stack, access manway, toilet riser and floor drains with p-traps. Concrete slab to sit directly on top of vault.
3. Excavation & backfill:
a. Over excavate 2’ each side of vault to allow for compaction and minor adjustments in orientation. Compact natural ground with 3 passes of tamper-type mechanical equipment.
b. Vault shall have a 4” compacted depth bedding or foundation. Bedding material shall be ¾” minus crushed aggregate or ABC. Washed sand may be used as a leveling and finishing course on top of the bedding material. Compact with 2 passes of tamper-type mechanical equipment.
c. Backfill with site material free from organic material or stone larger than 6”.
d. Within 6” of the vault backfill shall not contain any stone larger than 2”.
e. Compaction shall be in loose lifts of 8” and shall not exceed 6” compacted depth. Compaction shall be with 3 passes of tamper-type mechanical equipment, add water as necessary to ensure compaction.
4. Doors – 3’-0” x 6’-7” x 1 ¾” Flush Hollow Metal doors by Meskerdoor.com, LS series, A60 Galvannealed steel with polystyrene core or approved equal. Frames 16 gauge and door steel 18 gauge, 3 total. Primed and painted with 2 coats of paint.
Color dark brown to match siding, to be approved by COR.
5. Door Closers on toilet and shower doors: Norton 7500 or approved equal.
6. 12” dia. x 12’ long black plastic vent pipe.
7. Sealant for vent pipe and Government Furnished toilet riser: 100% silicone caulk.
8. Provide floor drains with p-traps in toilet and shower rooms, located in center of each room. Connect lines under building and plumb to drain into vault. Slope concrete to floor drains.
9. Hooks: 2 that are suitable to hold a solar shower bag full of water. One mounted in center of west wall of toilet between 38” and 48” above floor. The other to be mounted in middle of south wall of shower room at standard shower head height.
Additionally each room shall have a clothes hook mounted at the same heights as shower hooks on the northern part of the west walls.
10. Concrete pad – See also concrete spec. below, Section 4.01 A. 28.
a. Place 4” depth compacted Aggregate Base, compacted with water and vibratory plate compactor.
b. 6” depth concrete pad under building and 4” depth under the porch. Reinforcing to be #4 rebar, 18” o.c. both ways min. at mid depth in slab, 2” min clear all sides.
Prescott National Forest, Bradshaw Ranger District Page 9
c. Finished Floor Elevation of building pad (FFE) to be 9” -12” above existing grade on west, south and east sides of slab. Pad to slope as shown on drawings.
11. Ceiling and interior walls within the toilet room and shower room shall be covered with Fiberglass Reinforced Panels (FRP). Sequentia-laminated FRP by Crane Composites available at Lowes or approved equal. Color to be light and surface textured, provide color and texture samples to COR. See attached manufacturer’s installation instructions. Attach with glue and mechanical fasteners to substrate.
Substrate to be ½”dry wall and to be suitable for wet conditions or exterior.
12. Interior walls and ceiling of storage room – All interior walls shall extend from the floor to the celling. Walls and ceiling of room shall be covered by dry wall ½” and to be suitable for wet conditions or exterior, seams to be taped and sealed.
13. Insulation- Insulate the battery storage room only with R-22 or better.
14. Exterior walls–Ground contact pressure treated sill plate.
15. Exterior Siding – HardiePanel Vertical Siding, Select Cedarmill with Hardie battens
(to create board and batten style) or equal approved by COR and shall be on all exterior walls. Fascia and trim boards to be of same material and color. Color – through color-Chestnut Brown.
16. Where siding abuts the concrete slab (north walls), an aluminum strip such as SB- FCP: Starter Base for Fiber Cement Panel or approved equal, shall be used to protect the bottom of the panel from weather.
17. Ceiling- of storage room to be insulated with R-22 or better.
18. Porch posts – 6” x 6” wooden posts shall be pressure treated, brown, and unpainted.
19. Metal roofing –24 gage or better standard metal rib roofing. Color shall be approved by the COR.
20. One 12”x12” screened louvered vent in west toilet room wall.
21. One 2010 fixed window in west toilet room wall.
22. Door Hardware – Finish color silver.
a. Toilet and shower doors shall receive two locks, a deadbolt (with no interior locking mechanism and key to a master key) and lever lock, must meet accessibility requirements. Height of handle shall meet ADA specifications.
b. Storage room to receive deadbolt only.
c. Toilet door and shower lever locks and all other locks door must be keyed as to the master key (opens all locks) but the other key only opens the toilet and shower door levers.
23. Hinges shall be stainless steel with steel pin equal to Hager Hinge Model BB1279 41/2” x 4-1/2”.
24. Shelves: In the storage room a set of shelves shall be built on the west wall, to store all solar batteries. Provide 4 shelves with 15” separation and each shelf to support approximately 150 pounds. A set of shelves will be built on the east wall to store cleaning supplies and toilet paper. This set of shelves shall comprise of three shelves that are to be 2’ x 1’ each, sturdy enough to support approximately 40 pounds per shelf with a height separation of 18” and the top shelf being at a maximum height of 5’. Shelf corners protruding into room shall be rounded for safety reasons. All shelves shall be built from wood.
25. Grab bars in toilet: Shall comply with section 609 Architectural Barriers Act Accessibility Standards (ABAAS) and be located as per Sections 604.5 and 608.3
Prescott National Forest, Bradshaw Ranger District Page 10
(https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-aba-standards/aba-standards). 2 additional grab bars shall be located on north and west walls for the space to also serve as an accessible shower space.
26. Trenching, Backfill and Bedding – Trenching shall be as shown on detail. Bedding shall be compacted and shall be ¼” minus granular material granular material such as gravel, decomposed granite, or sand; 100% passing a #4 sieve and a maximum plasticity index 10. Backfill shall be composed of native soil that is free from trash, debris, roots over 1” diameter, rocks over 3” in diameter, topsoil, highly plastic soil or other deleterious mater. Backfilling shall be done in horizontal lifts of 6” with each lift being compacted with a minimum of three passes over the entire surface with a motorized mechanical means designed for compacting.
27. Electrical Conduit – A pull rope shall be placed in the electrical conduit in accordance to National Electrical Code Standards for future electrical line installation. If the solar system is a part of this contract, all electrical lines shall be run through appropriate conduit according to National Electrical Code standards.
28. Concrete – 3000 psi
a. Type II Portland cement ASTM C-150 will be used.
b. Aggregate size shall be Size Number 467.
c. Slump shall be a minimum of 2” and a maximum of 4 ½”.
d. Air Entrainment shall be 3 to 6 percent.
e. Concrete must be placed with in a maximum of 90 minutes unless hydration stabilizer are used. If hydration stabilizing admixture is used, determining the slump before placement. Do not use concrete with a slump loss of more than 2 inches (50 mm) as compared to the slump recorded at the batch plant.
f. COR must be notified a minimum of 24 hours prior to placement.
g. Formwork and concrete reinforcement must be approved by COR prior to ordering or mixing concrete.
h. Place concrete in maximum 18” horizontal layers, immediately after placing, thoroughly compact concrete with mechanical vibrators. Provide minimum of two power sources unless commercial power is available at site. Hand tamping or “spudding” for small volumes (under ½ CY) and areas (under 100 sf) may be used if approved by the COR. Do not drop concrete freely more than 6’.
i. Footing may be placed separate from foundation walls; if so provide minimum 2 x 3 x 18” key at 3’ intervals in top of footing.
j. Concrete slabs will be finished with a medium broom. And vertical exposed surfaces will be rubbed finished.
k. Concrete shall be protected from rainfall and rising water until the concrete is set. Do not drag tarpaulins or other covering across unset concrete.
l. Protection from loading and vibration for a minimum of 7 days from time of placement.
m. Curing of concrete will commence immediately after placing and finishing the concrete and will be continuous for 7 day. Curing can be either Water Curing (keeping all surfaces of concrete and forms wet and shading concrete from sun) or by Membrane Curing but do not place membrane cure on slabs receiving resilient flooring.
https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-aba-standards/aba-standards https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-aba-standards/aba-standards
Prescott National Forest, Bradshaw Ranger District Page 11
n. Remove and replace any concrete damaged by frost or freezing as directed by the COR.
4.02 ELECTRIC CONDUIT & PROPANE LINE
A. Install new propane line with connection from tank (to be moved by Government to location shown on plan) to cabin. Stub out for future connection near the center of the southwest cabin wall. Locate in trench with electrical conduit, see plans for approximate location. Final alignment shall be approved by COR prior to excavation.
B. The solar system electrical line (or conduit for future electric) shall be run underground with the propane. (See detail sheet 2)
4.03 WELL ABANDONMENT
A. The existing well must be abandoned according to all state and local regulations. The wellhead shall be removed and disposed of off government property.
B. Old drawings show the well as 36 feet deep. It is unknown if this is an accurate depiction of the well.
4.04 TOILET DEMOLITION
A. Toilet/tool shed combination building located near helipad. Wood walls, concrete floor, approximate size: 8’ x 7’. Demolition includes filling in the old pit with soil, compacting and grading to match existing ground. All wood and concrete shall be disposed of off Forest Land.
4.05 NEW SOLAR SYSTEM (ADDITIVE BID ITEM)
A. Design and build an adequate solar system to include enough power to run the indoor appliance and lights in the cabin. The installation shall also include an underground feeder circuit between the two buildings, interior surface conduit and wiring in the cabin, load center(s), wall switches, LED interior light fixtures, motion-detector operated LED exterior light fixtures, and one 110 volt outlet in each building.
B. Contractor shall size the PV system to power the loads described herein with 15% spare capacity for future lighting connections and a future 100 watt refrigerator, approximately 1000 watts minimum from the inverter. The photovoltaic modules shall be mounted on the south side of the toilet building roof where they will not be in plain view to site users. The available roof area is approximately 13’-6” by 10’; roof slope is approximately 6/12. Roofing material is metal ribbed. Expected use of the lighting is for early morning and evening use by the occupants, frequent operation of all light fixtures simultaneously is expected. Contractor is responsible for securing all materials and equipment at the site during construction.
C. The PV system shall have a 120 volt output full sine wave inverter, charger, charge controller with temperature compensation, disconnects, battery capacity meter, sealed AGM (absorbed propane mat) battery bank with minimum 3 day autonomy, and all related load centers, fixtures, wiring, and conduit. All equipment and batteries shall be located in a 3’ x 4’ storage closet at the toilet/storage building.
D. All interior light fixtures shall be equipped with 120 volt, 10-12 watt LED bulbs, minimum 675 lumens and 2700K warm white color rendition, surface or box mount, acrylic diffuser; Halo LED Disk Light model Model # SLD606927WH as available from Home Depot, or equal. Wiring for all light fixtures, switches, and outlets in the Cabin building shall be installed in plastic surface conduit and boxes such as Wiremold
Prescott National Forest, Bradshaw Ranger District Page 12 or Panduit. All work shall conform to the National Electric Code. The Contractor shall provide submittals of all equipment and light fixtures, along with PV system design calculations, for review prior to installation.
E. The enclosed floor plan for each building shows the light fixture, switches, receptacle, and load center locations. Specific requirements for certain locations are as follows:
1. Cabin SE Entry Door, Toilet Room Entry Door - a wall mounted, motion detector operated, LED porch light with photocell shall be installed adjacent to the lockset side of the door. The NW cabin entry door does not require a light fixture.
2. Toilet Room and shower room, the LED light fixtures shall be controlled by a 15 minute mechanical timer switch.
3. Refrigerator – install a receptacle box with wiring and a blank cover for a future 15 amp receptacle behind or adjacent to the existing propane refrigerator. Mount same height as switches.
F. Inverter/Battery Storage Room- Install one 15 amp receptacle for building maintenance needs.
G. The battery capacity meter shall be mounted in the cabin interior adjacent to the interior load center so that cabin occupants can monitor the battery state of charge. Wiring between the batteries and meter location shall be sized sufficient to permit proper operation of the meter.
H. Solar panels shall be affixed to the roof of the new toilet building.
| Palace-Station-SOW Drawings-REV7.3.18.pdf |
| 1. Section 1 - Schedule of items |
| 2. Section 2 – General |
| 2.01 Project Location |
| A. There are two routes that will take you to Palace Station. The road conditions vary, and it is recommended to drive a higher clearance vehicle. Four-wheel drive is not necessary unless snow is present along the roadway. |
| 1. From Mayer: County Road 177 also known as the Mayer-Goodwin Road is reached from the town of Mayer. Turn south towards the town of Mayer off highway 69 onto |
| 2. Central Street. Keep right on Central and then make a left turn onto Miami Street. In two blocks turn right onto E. Main Street. At the second intersection turn left onto Wicks Ave, and then another left onto Jefferson. Jefferson continues out of t... |
| 3. From Prescott: Mount Vernon Road in downtown Prescott becomes the Senator Highway after city limits. Travel the Senator for several miles on pavement, and then on gravel until you reach Palace Station. Approximately 15 miles. |
| 2.02 Project Requirements |
| A. The following items shall be constructed: |
| 1. New Toilet and Storage Building with vault. |
| 2. Propane and Electric conduit–New propane line connected to existing propane tank and stubbed out near cabin and electric conduit, with pull rope for future wiring, from toilet building to cabin. |
| 3. Solar System for Cabin- additive bid item |
| B. The following items shall be demolished/abandoned and removed from National Forest Lands: |
| 1. Old Toilet Building shall be removed. |
| 2. The hand dug well shall be abandoned according to ADWR standards. All associated hardware and plumbing shall be disposed of off National Forest Lands. |
C. Provide an O&M Manual
| 2.03 Utility requirements |
| A. For all utilities, ensure the following: |
| 1. Electric conduit buried no less than 18” depth and no less than 1’ horizontal and vertical separation between electric and propane. If rock or abnormal digging conditions are encountered, negotiations can be made with the CO to compensate the contr... |
| 2. Provide marking Detectape® for all new underground utilities. |
| 3. Provide appropriate backfill material. (See Section 4.01 A. 26.) |
| B. Propane shall be installed by professional propane installer. (The existing system is serviced by Ferrell Gas.) |
| C. All electrical systems shall be installed by electricians licensed in the State of Arizona. Contractor shall submit to the Government proof of licensure at the 100% Design submittal. (permits are not necessary) |
| D. All well work shall be completed by a certified well driller, licensed in the State of Arizona. Contractor shall submit to the Government proof of licensure at the 100% Design submittal. |
| 2.04 submittals |
| A. Product Submittals: |
| 1. Submittals shall be made for all items proposed to be furnished and installed. All submittals include, but not limited to, product data, samples, shop drawings, catalogs cuts and manufacturer’s literature, schedules and substitution requests. |
| 2. Work shall not commence on any item requiring submittals until submittals are approved in writing by the COR. |
| 3. Submit to the COR product information, as per this SOW, for any additional products incorporated during the course of Construction. Any additions will be the result of product substitution or modification and require written approval from the CO b... |
| 4. Submittals are required for the following: Toilet vault design; Screened vent pipe; Grab bars; Toilet paper holder; Concrete mix design; Field test results for concrete slump and air entrainment; Concrete floor sealer with non-skid surface for toil... |
| If additive bid item is included: Photovoltaic system equipment, including inverter, modules and batteries and sizing calculations; |
| 2.05 shop drawings |
| A. All Drawings shall include proposed/final and existing systems. These drawings shall include, but are not limited to the following: |
| 1. Toilet building |
| a. Scaled plan views of toilet/storage building. |
| b. Provide dimensioned elevations, sections and details to show all elements of the toilet/storage building including vault and floor drains. |
| c. Section view of walls showing framing, lumber grade, insulation, interior and exterior finish materials and details. |
| d. Section view of roofing, decking, framing and lumber grade, insulation, and ceiling details. |
| e. Section view of porch framing and roofing. |
| f. Section view of concrete floor. |
| 2. Solar System (if awarded) |
| a. Plan views of grounding grids. Draw all wiring and equipment to actual scale. Make sure all devices are installed according to needs, such as grounding rods, clamps and connectors. |
| b. Plan views of additional pull boxes/wiring. |
| c. Show all mounting details, supports, and accessories needed for complete systems. |
| d. Provide schematic sheets for transformer/surge arrestor connections. |
| e. Provide all electrical sheets showing the existing, proposed and final physical layout and control schematics. Also show any connections to existing electrical components. |
| 2.06 Government furnished property |
| A. The government shall provide and deliver the following property: |
| 1. Toilet riser. |
| 2.07 Facilities for contractor use |
| A. No water or electric available on site. |
| B. Contractor shall provide temporary sanitary facilities. |
| 2.08 Construction schedule |
| A. Work shall not begin until September 1, 2018 or after. |
| 2.09 provisions for safety and public access |
| A. The cabin site and area of outbuildings across the road will be closed to the public. Contractor is responsible for signage and barriers to keep the site closed. Forest Roads 52 and 82 shall remain open. Care shall be taken to not to disturb the hi... |
| B. The Contractor shall take all precautions deemed necessary to secure the worksites, improvements and equipment against vandalism or acts of nature and to ensure public safety. It is recommended that the Contractor make every attempt to secure the p... |
| 3. section 3 – Mobilization |
| 3. section 3 – Mobilization |
| 3.01 summary |
| A. This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to and from the project site, and for all other work and operations that must be performed or that cause costs ... |
| 3.02 Progress payments: |
| A. Progress Payments will be made as follows: |
| 1. When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid. |
| 2. When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid. |
| 3. Upon completion of all work on the project, any unpaid amount for mobilization will be paid. |
| 4. The total of all payments shall not exceed the original contract amount for this item. |
| 3.03 basis of payment |
| A. Payment will be made under: |
| 4. section 4 – specific project requirements |
| 4.01 New Toilet Building & vault |
| A. Construct a new stick built toilet building according to the drawings and specifications below. |
| 1. Design building for snow load of 30 psf. |
| 2. Install the toilet building over a 1000-1250 gallon concrete vault with holes provided for vent stack, access manway, toilet riser and floor drains with p-traps. Concrete slab to sit directly on top of vault. |
| 3. Excavation & backfill: |
| a. Over excavate 2’ each side of vault to allow for compaction and minor adjustments in orientation. Compact natural ground with 3 passes of tamper-type mechanical equipment. |
| b. Vault shall have a 4” compacted depth bedding or foundation. Bedding material shall be ¾” minus crushed aggregate or ABC. Washed sand may be used as a leveling and finishing course on top of the bedding material. Compact with 2 passes of tamper-ty... |
| c. Backfill with site material free from organic material or stone larger than 6”. |
| d. Within 6” of the vault backfill shall not contain any stone larger than 2”. |
| e. Compaction shall be in loose lifts of 8” and shall not exceed 6” compacted depth. Compaction shall be with 3 passes of tamper-type mechanical equipment, add water as necessary to ensure compaction. |
| 4. Doors – 3’-0” x 6’-7” x 1 ¾” Flush Hollow Metal doors by Meskerdoor.com, LS series, A60 Galvannealed steel with polystyrene core or approved equal. Frames 16 gauge and door steel 18 gauge, 3 total. Primed and painted with 2 coats of paint. Color d... |
| 5. Door Closers on toilet and shower doors: Norton 7500 or approved equal. |
| 6. 12” dia. x 12’ long black plastic vent pipe. |
| 7. Sealant for vent pipe and Government Furnished toilet riser: 100% silicone caulk. |
| 8. Provide floor drains with p-traps in toilet and shower rooms, located in center of each room. Connect lines under building and plumb to drain into vault. Slope concrete to floor drains. |
| 9. Hooks: 2 that are suitable to hold a solar shower bag full of water. One mounted in center of west wall of toilet between 38” and 48” above floor. The other to be mounted in middle of south wall of shower room at standard shower head height. Addit... |
| 10. Concrete pad – See also concrete spec. below, Section 4.01 A. 28. |
| a. Place 4” depth compacted Aggregate Base, compacted with water and vibratory plate compactor. |
| b. 6” depth concrete pad under building and 4” depth under the porch. Reinforcing to be #4 rebar, 18” o.c. both ways min. at mid depth in slab, 2” min clear all sides. |
| c. Finished Floor Elevation of building pad (FFE) to be 9” -12” above existing grade on west, south and east sides of slab. Pad to slope as shown on drawings. |
| 11. Ceiling and interior walls within the toilet room and shower room shall be covered with Fiberglass Reinforced Panels (FRP). Sequentia-laminated FRP by Crane Composites available at Lowes or approved equal. Color to be light and surface textured, ... |