Final_RFQ_Reserve_Ranger_District_Office_Janitorial.pdf
PDF 1 MB Posted
- Solicitation number
- 12837120Q0007
- Issued by
-
Department of Agriculture Forest Service
About this file
RFQ Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF-1449_Form_12837120Q0007.pdf | ||
| Reserve_Ranger_District_Map.pdf | ||
| Wage_Determination.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Service SOL NO: 12837120Q0007
PROJECT: 2020 Reserve Ranger District Office Janitorial Services
UNIT: Gila National Forest
PART I—THE SCHEDULE
SECTION B—SUPPLIES OR SERVICES AND PRICES/COSTS
DUNS NO: ____________________________________
TIN NO: _____________________________________
NOTE: All pricing shall include New Mexico taxes if applicable.
NOTE: No award will be made unless offeror is currently registered in the SAM database. Offerors shall bid on ALL line items.
“I have read and Acknowledge of Tax Delinquency on page 39 - 42.
Signature:______________________________________ Date:________________________________
See Section M for evaluation criteria. Offeror’s must submit Experience Questionnaire in Response to Section M.
Submit your offers to the physical address on Page 1 of SF-1449 block 9 of subject solicitation.
NOTE: E-MAIL OFFERS WILL BE ACCEPTED. Email: geraldine.carrasco@usda.gov. It is the responsibility of the Contractor to confirm that offer was received.
Line Item
Description
Quantity
Unit
Unit Price
TOTAL PRICE
Furnish all necessary materials, labor, supplies, supervision, equipment and incidentals needed to perform the Reserve Ranger District Office Janitorial Services in Reserve, New Mexico per contract specifications. All pricing shall include New Mexico Gross Receipts Tax.
Base Period - Provide Janitorial Services for the Reserve Ranger District Office from 01/01/2020 to September 30, 2020.
MO
OPTION 1 – Provide Janitorial Services for the Reserve Ranger District Office from October 1, 2020 to September 30, 2021.
OPTION 2 – Provide Janitorial Services for the
2021 to September 30, 2022.
OPTION 3 – Provide Janitorial Services for the
2022 to September 30, 2023.
OPTION 4 – Provide Janitorial Services for the
2023 to September 30, 2024.
TOTAL OF
LINE ITEMS
01-05
Service SOL NO: 12837120Q0007
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Scope of Contract
The work involves janitorial services for approximately 9,000 square feet of office space and related area, including entrance ways, corridors, lobbies, restrooms, and closets at the Reserve Ranger District Office, in accordance with the following terms, conditions, and specifications.
Government Furnished Property
The Government will provide the following materials, supplies, and property, as set forth below. The contractor shall be liable for loss or damage to such property until completion and final acceptance of the work.
A. Push
Broom/Brooms
B. Mops
C. Mop Bucket
D. Liquid Hand Soap
E. Toilet Paper
F. Paper Hand Towels
G. Plastic Trash Bags
J. Cleaners
K. Vacuum Cleaner
L. Hard Wood Floor Mop/Cleaners
M. Cleaning Rags
N. Disinfectants
0. Rolling Janitorial Cart & Trash Receptacle
Service SOL NO: 12837120Q0007
Contractor Furnished Property
Contractor is to provide all other necessary personal supplies, equipment to perform work.
Work Performance
The work shall be performed pursuant to the frequency schedules described below in all areas between the hours of 5:00 p.m. and 7:00 a.m. on weekdays. Also, work can be performed on weekends all day Saturday and Sunday and Holidays as needed.
The contractor or the contractor's employees shall:
A. Not open desks or file drawers.
B. Not remove papers on desks, tables, or file cabinets.
C. Not use office equipment, radios, or telephones.
D. Tum in all lost and found articles to the Contracting Officer's Representative
(COR)
E. Notify the COR as to needs to Government-furnished property.
F. Turn off all lights, locks doors, and insure that the building is secure upon completion of work.
G. Not have children under the age of sixteen (16) on the premises.
H. Not have any animals on premises.
I. Not smoke anywhere inside the building.
J. Follow all occupancy rules.
K. Contractor and the contractor's employees will be responsible for arming and disarming the Security System upon entering and leaving the building.
Contractor shall also inform the Contracting Officer (CO) in writing the names of all his/her employees associated with this contract.
Services to be Performed Daily (Monday - Friday)
1. Entrance and reception area (rooms 103 and 104). Vacuum all carpeted areas and sweep and damp mop tile floors. Remove all scuff marks from tile floors.
Dust furniture and surfaces that are readily available and visibly require dusting.
Clean windows, glass entrance doors, dust metal window casings, glass displays and bookcases.
2. Restrooms. Sweep and damp mop tile floors. Clean, disinfect, and polish all sinks and toilets including metal surfaces with suitable cleansers, disinfectants, Service SOL NO: 12837120Q0007 and scale removers. Wash tiled walls, stalls, and partitions that visibly require cleaning. Disinfect light switch covers and door kick and handle plates.
Replenish soap, toilet tissue, and towels. Clean mirrors. Empty and replenish with plastic bags all trash receptacles.
3. Kitchen Area. Clean, disinfect, and polish kitchen sink, counter, and refrigerator accessible surface. Clean and disinfect conference room tables. Sweep and damp mop Kitchen/Break room tiled area.
4. Sweep and damp mop with disinfectant solution hallways and janitorial room.
Remove all black marks. Remove hand prints and scrape marks on wall surface.
5. Other:
a. Clean and disinfect/descale water fountains.
b. Clean and disinfect all light switch covers, receptacle covers and kick plates on doors.
c. Empty all trash receptacles and replace with new plastic garbage bags.
All trash collected shall be removed from the building and placed in covered refuse containers furnished by the government.
d. Spot sweep/vacuum areas visibly needing cleaning.
e. Sweep and mop hard wood floors with specific hard wood cleaners.
Services to be Performed Three times a Week:
A. Clean and disinfect the two showers in health and fitness room, sweep and damp mop tile floors.
B. Vacuum all carpeted areas.
C. Floor mats at entrances are to be removed from building, swept, and replaced. This should be done daily during wet, muddy periods.
Services to be Performed Once a Week
A. Dust all furniture, office equipment, window sills, and all surfaces within reach while standing on the floor.
B. Dust, clean and vacuum the Conference Room.
D. Sweep both front and rear patios and exterior concrete walkways. Clean or sweep debris from covered surfaces on both front and rear patios. Empty all outside trash receptacles and ashtray and sand urn. Wash and disinfect picnic tables.
Service SOL NO: 12837120Q0007
Services to be Performed Once a Month
A. Clean all light fixtures and perform other high cleaning. such as, dusting exposed pipes, tops of partitions, tops of storage cabinets, etc.
B. Clean and polish door knobs/handles.
C. Clean all blinds in all offices.
D. Spot clean carpet where obvious spills are as needed.
Services to be Performed Every Three Months
A. Wash all windows, inside and out, remove screens to wash outside windows.
B. Clean all ceiling fixtures of bugs, dust, etc.
C. Wash all wastebaskets.
Superintendence by the Contractor
At all times during performance of this contract until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the work site a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.
Protection of Government Buildings, Equipment, and Vegetation
The Contractor shall use reasonable care to avoid damaging buildings, equipment, and vegetation on the Government installation. If the Contractor's failure to use reasonable care causes damage to any of this property, the Contractor shall replace or repair the damage at no expense to the Government as the Contracting Officer directs. If the Contractor fails or refuses to make such repair or replacement, the Contractor shall be liable for the cost, which may be deducted from the contract price.
Government Quality Control and Assurance
The Forest Service relies on the Contractor’s existing quality assurance system for commercial services as a substitute for Government inspection and testing before tender for acceptance unless customary market practices for the commercial service being acquired include in-process inspection. Any in-process inspection by the Forest Service shall be conducted in a manner consistent with commercial practice. The Forest Service may conduct quality assurance for its benefit and has the right to refuse acceptance of nonconforming services. Quality issues with
Service SOL NO: 12837120Q0007 services tendered for acceptance or rejected by the Forest Service shall be resolved under
Contract Clause FAR 52.212-4(a), “Contract Terms and Conditions-Commercial Items”.
1-12.1 PERFORMANCE REQUIREMENT SUMMARY: The below table describes the quality level of performance expected by the Forest Service and the means by which the Forest Service may use to validate acceptable services. Acceptance by the
Government of satisfactory services provided is contingent upon the Contractor performing in accordance with the terms and conditions of the contract. The following inspection and acceptance criteria are to be used to determine acceptance of work under this contract.
Performance Requirement Summary
PWS
Para #
Required
Services
Performance Standards Acceptable Quality
Level
(AQL)
Monitoring
Method
1-5 GFP Supply
Stock
Two week notice is given to the COR to replenish
GFP Stock
Facilities are 100% stocked with supplies.
COR observation
Valid customer complaint
1-9.1
1-10
Facility Cleaning See Para 1-9 No more than 2 valid customer complaints per month
Valid customer complaint
COR observations
1-9, 1-11 Scheduling
Services
Services are coordinated with COR and delivered as scheduled
No more than 1 occurence per month where services are not delivered on schedule.
Services are rescheduled and completed within the week originally scheduled.
COR Observations
Valid customer complaint
1.11 Quality Control
Program
Contractor effectively manages personnel, delivery of services, and quality control and assurance is evident.
Communication and coordination is timely and effective with the COR
Notifications are timely to the COR, no more than 2 late notification per year.
QCP processes are effective with no negative trends noted in delivery of service
COR visual observations and review of
Contractor inspection reports
1.11 Quality Control
Program
Communication and coordination is timely and effective with the COR
No more than 1 missed communications or timely coordination with COR per Month
COR visual observations
Valid FS customer complaint
Service SOL NO: 12837120Q0007
OTHER REQUIREMENTS
Qualifications Of Contractor Or Employees
The Contractor and his/her employees shall be capable and experienced in janitorial work. The on-site supervisor shall have experience and demonstrated ability in both supervision and custodial work. The Contractor shall provide a list of employees authorized to work under this contract, and will also provide copies of full background checks on these employees, as well as any replacement employees to the Contracting Officer prior to work proceeding, and in accordance FAR 52.204-9 Personal Identity Verification of Contractor Employees.
Subcontracting
The Government reserves the right to approve or disapprove any subcontractors selected. The
Contractor shall obtain approval from the CO for all subcontractors prior to entering into any subcontracts. The Contractor's request for approval shall be in writing and include the specific work to be accomplished by the subcontractor.
Standards of Conduct
The Contractor shall be responsible for maintaining satisfactory standards of employee competency, conduct, appearance, and itegrity and shall be responsible for taking such displinary action with respect to its employees as may be necessary.
Removal From Contract Work
The contracting officer or a designated representative may require the Contractor to remove any employee(s) from Forest Service controlled buildings or other real property should it be determined that the individual(s) is either unsuitable for security reasons or otherwise unfit to work on Forest Service controlled property. This shall include, but not limited to, instances where an employee is determined, in the Government’s sole discretion, to be incompetent, careless, insubordinate, unsuitable or otherwise objectionable.
(a) A contractor employee may also be removed where the continued employment of the contractor employee in connection with the Forest Service work is deemed, in the
Government’s sole discretion, contrary to the public interest, inconsistent with the best interests of security, or a potential threat to the health, safety, security, general well being or operational mission of the facility and its population.
(b) Where a contractor employee is granted a temporary suitability determination, and an unfavorable final suitability determination is later rendered, the Forest Service may insist on the employee’s removal from the work site and from other work in connection with the Contract.
Service SOL NO: 12837120Q0007
(c) The Contractor shall be responsible for providing replacement employees in cases where contract employees are removed at no additional cost to the Government.
Security Of Building
The Contractor shall be responsible for locking outside doors and windows and turning off all lights when night cleaning is finished in all areas, unless otherwise directed by Forest Service personnel then in attendance. During the time the cleaning is being done, lights shall be on only in the portion of the building where the work is being done.
The Contractor shall be responsible for seeing that Contractor’s employees do not disturb papers on desks, tamper with computer terminals, open drawers or cabinets, or use telephones except for emergency calls to the police or fire department. Use of Government photocopiers, fax machines, computers, and other Government office equipment by Contractor’s personnel is strictly prohibited. Government office equipment shall not be unplugged, bumped, or disturbed in any manner unless specifically authorized by Government personnel.
Ensure the premises are locked and secure prior to leaving after cleaning services have been completed.
Safety
In order to help keep the buildings safe and secure, report hazardous and safety conditions and any items in need of repair to the COR.
Keep doors closed/locked when in the buildings.
Do not allow ANYONE other than cleaning person(s) access to the buildings or allow anyone to borrow or use door keys or give anyone the entry code.
Do not open doors to anyone you do not recognize. All Forest Service personnel have entrance codes or keys.
CONTRACT PERIOD AND RENEWAL OPTION AND PAYMENT
Contract Period and Renewal Option
The contract Base Period is from January 1, 2020 to September 30, 2020.
The base year of the contract period shall extend for four fiscal years from
October 1, 2020 to September 30, 2024. However, at the option of the
Government and availability of funds, the contract may be renewed for an additional 1-year period, not to exceed one renewal period provided the
Service SOL NO: 12837120Q0007
Contracting Officer serves preliminary notice of renewal at least 60 calendar days prior to contract expiration. The renewal is at the same terms and conditions except that any renewal is subject to the provisions of Section I, FAIR LABOR
STANDARDS ACT and SERVICE CONTRACT ACT- (FAR 52.222-440)
Payment
Payments will be made in accordance with provisions of Prompt Payment and be made using the IPP (Invoicing Processing Platform).
Service SOL NO: 12837120Q0007
SECTION D--PACKAGING AND MARKING
MSDS (Material Safety Data Sheets) for products being used shall be posted for employees to access.
Service SOL NO: 12837120Q0007
SECTION E--INSPECTION AND ACCEPTANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-1 Contractor Inspection Requirements (APR 1984)
52.246-4 Inspection of Services—Fixed Price (AUG 1996)
E-1 CONTRACTOR QUALITY CONTROL SYSTEM
The Contractor shall identify the quality control inspection system it will use to ensure that contract specifications will be achieved. At no time shall the contractor rely upon
Government inspections to provide notification of unsatisfactory performance. The
Contractor shall produce written inspection records in a format and at times and places satisfactory to the Contracting Officer. Inspection records shall be made available upon request of the Contracting Officer and be maintained until the date of contract closure.
The Contracting Officer may observe the Contractor’s inspection at any time and shall otherwise have unlimited access to the inspection data.
E-2 QUALITY ASSURANCE
The Government may inspect 10% or more of the completed survey units. The
Government will randomly select the time and place of the inspection without the
Contractor’s knowledge. The Government will walk through the surveyed areas evaluating unit conditions and ensuring no sites were overlooked.
The Government may request a selection of completed draft cultural site records at any time for inspection to evaluate site recording procedures.
The Contractor shall resurvey any area or portion that does not meet the terms of the contract. If the inspection reveals the need for rework, the Government will notify the
Contractor immediately in writing. All rework shall be completed prior to proceeding with new areas.
http://www.arnet.gov/far/
Service SOL NO: 12837120Q0007
SECTION F--DELIVERIES OR PERFORMANCE
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
52.242-14 Suspension of Work (APR 1984)
52.242-15 Stop Work Order (AUG 1989)
52.242017 Government Delay of Work (APR 1984)
F-1 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within _5_ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than _N/A_ calendar days. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed within 5 calendar days from date of award. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
F-2 SCHEDULES FOR SERVICE CONTRACTS
Contractor shall, within ten (10) days from receipt of a request from the Contracting
Officer, submit a time chart or schedule of proposed progress to ensure completion of the work within the time set forth in this contract. If the Contractor’s progress falls behind the schedule, Contractor shall take such action as necessary to improve progress; in addition the Contracting Officer may require the Contractor to submit a revised schedule and proposed plan of work to ensure completion of the work within the time specified.
Service SOL NO: 12837120Q0007
SECTION G--CONTRACT ADMINISTRATION DATA
AGAR 452.215-73 Post Award Conference (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within __5__ days after the date of contract award. The conference will be held at a time and date to be determined.
GOVERNMENT-FURNISHED PROPERTY
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the
Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.
See Section C page 2, Government furnished supplies and equipment.
DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE.
The Contracting Officer designates the Contracting Officer's Representative(s) (COR). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)
On all matters that pertain to the contract terms, the Contractor must communicate with the
Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
FAR 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011)
(a) The Contractor shall comply with agency personal identity verification procedures identified in the contract that implement Homeland Security Presidential Directive-12 (HSPD-
12), Office of Management and Budget (OMB) guidance M-05-24 and Federal Information
Processing Standards Publication (FIPS PUB) Number 201.
Service SOL NO: 12837120Q0007
(b) The Contractor shall account for all forms of Government-provided identification issued to the Contractor employees in connection with performance under this contract. The Contractor shall return such identification to the issuing agency at the earliest of any of the following, unless otherwise determined by the Government:
(1) When no longer needed for contract performance.
(2) Upon completion of the Contractor employee’s employment.
(3) Upon contract completion or termination.
(c) The Contracting Officer may delay final payment under a contract if the Contractor fails to comply with these requirements.
(d) The Contractor shall insert the substance of this clause, including this paragraph (d), in all subcontracts when the subcontractor’s employees are required to have routine physical access to a Federally-controlled facility and/or routine access to a Federally-controlled information system. It shall be the responsibility of the prime Contractor to return such identification to the issuing agency in accordance with the terms set forth in paragraph (b) of this section, unless otherwise approved in writing by the Contracting Officer.
Service SOL NO: 12837120Q0007
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 FAR 52.236-4 Physical Data (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The
Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys.
(b) Weather conditions _10 year average, National Weather Service_.
Utility Services
No services available.
H.2 Contractor Representative
The contractor shall provide a contract representative for the performance of the work. The name of this person and an alternate(s) who shall act for the contractor when the contractor is absent shall be designated in writing to the contracting officer.
H.3 SAFETY PLAN
1. The Contractor shall provide a copy of their safety plan at the pre-work meeting. This copy of the Safety plan shall be kept in the contract folder for OSHA’s review.
2. The Safety Plan should be available to all employees and subcontractors working on the contract.
3. The Safety Plan should cover at a minimum:
a. Safety briefings covering the work area, equipment being used, and any special consideration for the work under the contract.
b. Personal Protective Equipment for the work under the contract.
c. Identify appropriate OSHA requirements for the type of work under the contract.
d. Weather considerations for the time of year of the contract.
e. Communication issues and locations of the nearest medical facilities.
f. Name of point of contact information of supervisor responsible for enforcing
Safety Plan.
g. Name, position title and point of contact information of company executive responsible for approving the Safety Plan.
h. Specific contingency plans for emergencies such as medical, fire, hazard material spills and any other contract assessed hazard prevention and abatement requirement needs that apply to this project.
Service SOL NO: 12837120Q0007
H-4 SAFETY
Known hazards may consist of, but not all inclusive of the following:
Prevention of Slips and Falls:
1. To help prevent accidents, the Contractor shall post wet floor areas with signs or barricade areas to restrict access.
2. The contractor shall post signs whenever mopping, stripping, or finishing floors.
3. Pay particular attention on rainy days to building entrances, stairways hallways, and restrooms.
4. The Contractor shall ensure adequate safety precautions are being exercised while cleaning windows.
Safe Use of Cleaning Materials and Other Chemicals:
Maintenance and custodial work requires the use of several cleaning materials. Some of these can be dangerous if used improperly. The Contractor shall implement the following procedures at a minimum as well as follow information provided on MSDS (Material Safety Data Sheets):
1. Keep materials labeled.
2. Follow the directions for use. Be sure the chemical is properly diluted if needed.
3. Wear protective garments such as rubber gloves or goggles if necessary or required.
4. Provide adequate ventilation to prevent the buildup of fumes or gases.
5. If an individual is exposed to a chemical, get prompt attention, and if necessary, seek medical help. Check the MSDA for the material data sheet and/or the label on the container.
6. Do not use unknown chemicals. Find out what it is or dispose of safely.
Electrical Hazards:
Electrically-powered equipment can be dangerous if used improperly. Use of electrical equipment on a wet floor or under wet conditions can be very dangerous. The Contractor shall follow these procedures at a minimum:
1. Do not use equipment with a spliced cord or with cut or exposed wires, broken wires, a sort, or a damaged ground.
2. Report damaged equipment, any equipment that gives a shock, or a grounds that have been tampered with to the COR (Contracting Officers Representative).
3. Ground all equipment before use.
Fire Safety and Prevention:
Always be alert to recognize potential fire hazards. If smoke or fire is discovered:
1. Immediately evacuate the area of the fire.
2. Evacuate the building.
3. Sound the alarm if possible.
4. Call the local Fire Department then your supervisor and the COR.
Service SOL NO: 12837120Q0007
SECTION I--CONTRACT CLAUSES
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.usda.gov/procurement/policy/agar.html
52.202-1 Definitions. (NOV 2013)
52.203-3 Gratuities. (APR 1984)
52.203-7 Anti-Kickback Procedures. (MAY 2014)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity.
(MAY 2014)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions (Oct 2010)
52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform
Employee of
Whistleblower Rights (April 2014)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (MAY
2011)
52.204-13 System for Award Management Maintenance. (OCT 2018)
52.211-11 Liquidated Damages - Supplies, Services, or Research and Development. (SEP
2000)
52.212-4 Contract Terms and Conditions-Commercial Items (Oct 2018)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights-
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
http://www.usda.gov/procurement/policy/agar.html
Service SOL NO: 12837120Q0007
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act
(31 U.S.C. 3727). However, when a third party makes payment (e.g.,use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the
Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting
Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include-
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/content/52233-1-disputes#i1048610 https://www.acquisition.gov/content/52202-1-definitions#i1063244
Service SOL NO: 12837120Q0007
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice;
and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer-System for Award Management, or 52.232-
34, Payment by Electronic Funds Transfer-Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C.3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR Part1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.-
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt
Payment Act (31 U.S.C.3903) and prompt payment regulations at 5 CFR Part1315.
https://www.acquisition.gov/content/52232-33-payment-electronic-funds-transfer-system-award-management#i1050674 https://www.acquisition.gov/content/52232-34-payment-electronic-funds-transfer-other-system-award-management#i1050705 https://www.acquisition.gov/content/52232-34-payment-electronic-funds-transfer-other-system-award-management#i1050705 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3
Service SOL NO: 12837120Q0007
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see
52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall-
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the-
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting
Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by
33.211 if–
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
https://www.acquisition.gov/content/52212-5-contract-terms-and-conditions-required-implement-statutes-or-executive-orders-commercial-items#i52_212_5 https://www.acquisition.gov/content/33211-contracting-officer’s-decision#i1080268
Service SOL NO: 12837120Q0007
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting
Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
https://www.acquisition.gov/content/32607-2-deferment-collection#i1081898 https://www.acquisition.gov/content/32608-2-interest-credits#i1081962
Service SOL NO: 12837120Q0007
(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the
Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the
Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the
Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain
Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and
41 U.S.C. chapter 21 relating to procurement integrity.
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3
Service SOL NO: 12837120Q0007
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with
Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments.
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.
https://www.acquisition.gov/content/52212-5-contract-terms-and-conditions-required-implement-statutes-or-executive-orders-commercial-items#i52_212_5 https://www.gsa.gov/forms-library/solicitationcontractorder-commercial-items
Service SOL NO: 12837120Q0007
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of clause)
Alternate I (Jan 2017). When a time-and-materials or labor-hour contract is contemplated, substitute the following paragraphs (a), (e), (i), (l), and (m) for those in the basic clause.
(a) Inspection/Acceptance. (1) The Government has the right to inspect and test all materials furnished and services performed under this contract, to the extent practicable at all places and times, including the period of performance, and in any event before acceptance. The Government may also inspect the plant or plants of the Contractor or any subcontractor engaged in contract performance. The Government will perform inspections and tests in a manner that will not unduly delay the work.
(2) If the Government performs inspection or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties.
(3) Unless otherwise specified in the contract, the Government will accept or reject services and materials at the place of delivery as promptly as practicable after delivery, and they will be presumed accepted 60 days after the date of delivery, unless accepted earlier.
(4) At any time during contract performance, but not later than 6 months (or such other time as may be specified in the contract) after acceptance of the services or materials last delivered under this contract, the Government may require the Contractor to replace or correct services or materials that at time of delivery failed to meet contract requirements. Except as otherwise specified in paragraph (a)(6) of this clause, the cost of replacement or correction shall be determined under paragraph (i) of this clause, but the “hourly rate” for labor hours incurred in the replacement or correction shall be reduced to exclude that portion of the rate attributable to profit. Unless otherwise specified below, the portion of the “hourly rate” attributable to profit shall be 10 percent. The Contractor shall not tender for acceptance materials and services required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken. [Insert portion of labor rate attributable to profit.]
Service SOL NO: 12837120Q0007
(5)(i) If the Contractor fails to proceed with reasonable promptness to perform required replacement or correction, and if the replacement or correction can be performed within the ceiling price (or the ceiling price as increased by the Government), the Government may-
(A) By contract or otherwise, perform the replacement or correction, charge to the Contractor any increased cost, or deduct such increased cost from any amounts paid or due under this contract; or
(B) Terminate this contract for cause.
(ii) Failure to agree to the amount of increased cost to be charged to the Contractor shall be a dispute under the Disputes clause of the contract.
(6) Notwithstanding paragraphs (a)(4) and (5) above, the Government may at any time require the Contractor to remedy by correction or replacement, without cost to the Government, any failure by the Contractor to comply with the requirements of this contract, if the failure is due to-
(i) Fraud, lack of good faith, or willful misconduct on the part of the Contractor's managerial personnel; or
(ii) The conduct of one or more of the Contractor’s employees selected or retained by the
Contractor after any of the Contractor’s managerial personnel has reasonable grounds to believe that the employee is habitually careless or unqualified.
(7) This clause applies in the same manner and to the same extent to corrected or replacement materials or services as to materials and services originally delivered under this contract.
(8) The Contractor has no obligation or liability under this contract to correct or replace materials and services that at time of delivery do not meet contract requirements, except as provided in this clause or as may be otherwise specified in the contract.
(9) Unless otherwise specified in the contract, the Contractor's obligation to correct or replace
Government-furnished…