Attachment_2_-_Supplemental_Specifications.pdf
PDF 109 KB Posted
- Attached to
- GLEES Powerline Relocation
- Solicitation number
- 1282FT18R0012
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1282FT18R0012AME0001.pdf | ||
| Pre_Bid_Information.pdf | ||
| Attachment_3_-_Drawings_Revised.pdf | ||
| 1282FT18R0012.doc.pdf | ||
| Attachment_1_-_Specifications.pdf | ||
| Attachment_4_-_Wage_Determination.pdf | ||
| Attachment_3_-_Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Forest Service Supplemental Specifications – GLEES Powerline Relocation
201 - Clearing and Grubbing 201.04_National_11_8_2016
Delete and replace Subsection 201.04(d) with the following:
201.04(d) Clearing.
(d) Trim tree branches that extend over the road surface and shoulders to attain a clear height of <number> feet. Trim tree limbs as near flush with the trunk as practicable.
201.04_National_11_2_2016
Add the following paragraph to Subsection 201.04:
201.04 Clearing.
(e) Do not cut vegetation less than 3 feet in height and less than 3 inches in diameter that is within the clearing limits but beyond the roadway and not in a decking area and that does not interfere with sight distance along the road unless otherwise designated.
201.06_National_11_2_2016
Delete the first sentence of this Subsection 201.06 and replace the following:
201.06 Disposal.
Dispose of merchantable timber designated for removal according to the provisions of the timber sale contract.
203 - Removal of Structures and Obstructions 203.04_National_11_2_2016
Make the following changes to Subsection 203.04(b):
203.04 (b) General.
Delete the fifth paragraph of Subsection 203.04(b) and replace with the following:
Remove structures and obstructions in the roadbed to 12 inches (300 millimeters) below subgrade elevation. Remove structures and obstructions outside the roadbed to 12 inches (300 millimeters) below finished ground or to the natural stream bottom.
Delete the seventh paragraph of Subsection 203.04(b) and replace with the following:
When abandoning an existing culvert pipe, remove the upstream and downstream portion of the culvert to within 12 inches (300 millimeters) of the subgrade or embankment slope. Ensure the abandoned pipe is at least 48 inches (1200 millimeters) from a new culvert or structure. Seal the abandoned culvert ends with a tight-fitting plug of concrete at least 6 inches (150 millimeters) thick. Ensure the structure does not entrap water.
203.05_National_11_8_2016
Add the following to Subsection 203.05:
203.05 Disposing of Material.
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toe line of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees.
(f) Scattering. Scatter construction slash in designated areas without damaging trees. Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another.
Limb and scatter other construction slash to reduce slash concentrations. When scattering for erosion control, place construction slash as flat as practicable on the completed slope.
(g) Chipping. Use an approved chipping machine to chip slash longer than 3 feet. Deposit chips on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking. Remove brush from designated log deck areas. Limb and top logs.
Logs not meeting the Utilization Standards described in Subsection 201.04(c) shall be cut to lengths less than <number> feet and decked in designated log deck location.
Merchantable timber not associated with an existing timber sale shall be cut to length meeting the Utilization Standards described in Subsection 201.04(c).
Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps.
| 201 - Clearing and Grubbing |
| 201.04(d) Clearing. |
| 201.04 Clearing. |
| 201.06 Disposal. |
| 203 - Removal of Structures and Obstructions |
| 203.04 (b) General. |
| 203.05 Disposing of Material. |
File details come from the government source that posted it.