This document contains a federal solicitation and related opportunity for fence reconstruction services on National Forest land damaged by wildfire. The solicitation requests bids to remove and replace 33.5 miles of pasture and allotment boundary fencing, repair 6.4 miles, and remove 6.1 miles of additional fencing across 13 grazing allotments within the Minidoka Ranger District of the Sawtooth National Forest in Idaho. The work includes removing all old fencing materials, clearing vegetation as needed, and constructing new four-strand barbed wire fences. The Forest Service will provide barbed wire and t-posts for reconstruction and all materials for repair work, while contractors must provide labor, expertise, and safety and quality control plans. Bids are due by 1:00pm local time on the specified date, with no extensions anticipated. Contractors must acknowledge any amendments prior to the deadline.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1282B123R0002 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

82B1

WASHINGTON DC 20250-0001

1400 INDEPENDENCE AVE SW MS-1138

SPOC INTERMOUNTAIN

USDA FOREST SERVICE

10/07/20220001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

10/07/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to include the requirement for contractors to submit the following documents:

1)Quality Control Plan: Contractor must describe in detail the inspection procedures that will reflect all aspects of work activities/tasks listed in the Schedule and detailed in the plans and specifications.

2)Safety Plan: Describe the equipment and safety procedures that are intended to be used to assure safety of on-site workers as well as the general public.

Upon award, awardee will be requirement to submit a final work plan including crew size, work schedule, and work sequence that will ensure completion of the project in an orderly

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

JESSICA LYN H. RASMUSSEN

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

1282B123R0002/0001 and timely manner.

See questions and answers.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Question 1: Do the stays required need to be treated or bark-on?

Answer 1: Use bark-on stays

Question 2: If braces are drill steel, does it matter if it is 2 7/8 or 2 3/8?

Answer 2: The solicitation states that the USFS prefers 2 7/8 drill steel but 2 3/8 is fine also. Contractors can use either one. (page 4 in SOW)

Question 3: Can you confirm if all or part of the material is provided by the USFS or the contractor?

Answer 3: All material for REPAIR fence is provided by the USFS. (Table 1 in SOW, page 12) All BARBED wire and TPOST/w clips for reconstruction is provided by USFS. (Table 2 in SOW, page 12)