MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 001500 – 1

PINE RIDGE JOB CORPS CCC LIST OF DRAWINGS AND SPECIFICATIONS

SECTION 001500

PINE RIDGE JOB CORPS CCC

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS

LIST OF DRAWINGS AND SPECIFICATIONS

PART 1 – GENERAL

1.1 DESCRIPTION

A. List of Contract Drawings:

1. Index of Sheets:

T1.1 G1.1 F1.0

Title Sheet and Drawing Index Legend, General Notes, and Center Map Dining Hall (Bldg 121) Life Safety Plan

F2.0 Maintenance/Painting (Bldg 230) Life Safety Plan F3.0 Dormitory 1 (Bldg 514) Life Safety Plan F4.0 Male Honor Dorm (Bldg 515) Life Safety Plan F5.0 F6.0

Dormitory 4 (Bldg 530) Life Safety Plan Female Honor Dorm (Bldg 516) Life Safety Plan

F7.0 Gymnasium/Education (Bldg 523) Life Safety Plan 9 Total Plan Sheets in this Contract

B. List of Contract Specifications

1. Index of Specifications

DIVISION 1 - GENERAL REQUIREMENTS

Section 001500 List of Drawings and Specifications Section 010150 General Requirements

DIVISION 8 – DOORS AND WINDOWS

Section 081113 Section 081416 Section 087100

Hollow Metal Frames Flush Wood Doors Door Hardware

DIVISION 9 – FINISHES

Section 092900 Gypsum Board and Fire Sealing

DIVISION 21 – FIRE SUPRESSION

Section 210050 Carbon Dioxide Fire Suppression System

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 001500 – 2

PINE RIDGE JOB CORPS CCC LIST OF DRAWINGS AND SPECIFICATIONS

Section 283111 Fire Alarm System

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 1

PINE RIDGE JOB CORPS CCC GENERAL REQUIREMENTS

SECTION 010150

GENERAL REQUIREMENTS

PART 1 – SUMMARY OF WORK

1.1 DESCRIPTION

A. Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, utilities, miscellaneous items, freight and delivery and all necessary valid licenses and permits for the work summarized as follows:

1. Modifications and replacement of fire detectors, alarm panels, and fire detection devices, alarms, and associated equipment.

2. Installation of a low pressure carbon dioxide fire suppression system and detection.

B. This project is located at the Pine Ridge Job Corps Center campus located approximately 13 miles south of Chadron, Nebraska. The address is 15710 South Highway 385, Chadron, Nebraska 69337.

1.2 GENERAL SITE CONDITIONS AND WEATHER

A. The elevation of the site is approximately 3400 feet above mean sea level. The construction site can experience heavy snowfalls and cold temperatures in the winter and shoulder seasons.

1.3 USE OF PREMISES

A. Use of Site: Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Full Government Occupancy: Government will occupy site and buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations.

C. Driveways and Entrances: Keep driveways, parking areas, loading areas and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 2

1.4 WORK RESTRICTIONS

A. Nonsmoking Buildings: Smoking is not permitted within the buildings or within 25 feet (8 m) of entrances, operable windows, or outdoor air intakes.

1.5 CONTRACTOR’S RESPONSIBILITIES

A. Confine storage of materials to areas as approved by the CO.

B. Provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Minimize disturbance of all undisturbed areas.

1.6 FIELD VERIFICATION

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

1.7 PERMITS

A. Obtain permits for work required by County, State, or Federal laws or regulations.

B. State electrical inspection is required for this project. Obtain permits for electrical work if the State Electrical Inspector requires a permit to perform the inspection.

PART 2 – DEFINITION OF ITEMS AND PAYMENT

2.1 DESCRIPTION

A. This section explains what is and what is not included in each pay item; the limits or cut-off points where one item ends and another begins; and basis of payment for work items listed in the Schedule of Items.

B. Payment: For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications, and as shown on the drawings.

2.2 SCHEDULE OF ITEMS

A. Schedule of Items: The project Schedule of Items includes several sections to organize the work into Base Items and Optional Items.

1. Provide pricing for all items listed in the Schedule of Items.

2. Contract award will be made for all Base Items.

3. Optional Items will be awarded based on available project funding.

B. Base Items (BI):

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 3

1. Base Item No. 1- Dining Hall Fire Detection Repairs

a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to install duct mounted smoke detectors and all necessary wiring.

2. Base Item No. 2 – Maintenance/Paint Shop Life Safety Repairs

a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to install a low pressure automatic carbon dioxide fire protection system and manual pull stations.

3. Base Item No. 3 – Dormitory 1 Fire Detection Repairs

a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, demolition, labor and incidentals to remove existing duct smoke detectors and install new duct smoke detectors.

4. Base Item No. 4- Male Honor Dormitory Life Safety Repairs

a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to install fire detection devices and make life safety repairs.

5. Base Item No. 5 – Dormitory 4 Fire Detection Repairs includes all materials, equipment, labor and incidentals to install a new duct smoke detector and wiring.

6. Base Item No. 6 - Female Honor Dormitory Life Safety Repairs includes all materials, equipment, labor and incidentals to make life safety repairs.

C. Optional Items (OI):

1. Optional Item No. 7 - Gymnasium/Education Fire Alarm System Replacement includes all materials, equipment, labor and incidentals to remove the existing fire detection and alarm system and install a new fire detection and alarm system.

PART 3 – ACCIDENT PREVENTION

3.1 DESCRIPTION

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 4

A. This section consists of establishing an effective accident prevention plan and providing a safe environment for personnel and visitors.

3.2 SUBMITTALS

A. Accident Prevention Plan: Before on-site work begins, submit a company approved accident prevention plan. This plan will be posted in the contract file. Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project. Notice to proceed will not be made until the plan is received. As a minimum the plan shall include:

1. Name, position title and contact information of company executive responsible for approving the Accident Prevention Plan.

2. Name and contact information of supervisor responsible to carry out the plan.

3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.

4. Contingency plans for emergency situations such as medical, fire, hazard material spills and other contract assessed hazard prevention and abatement requirement needs that apply to this project.

B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.

C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.

D. Submit a brief report of safety meetings and of inspections.

E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.

3.3 QUALITY ASSURANCE

A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions: In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

B. Qualifications of Employees: Ensure employees are physically qualified to perform assigned duties in a safe manner.

3.4 ACCIDENT REPORTING

A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 5

$100, and fires. Within 7 calendar days of a reportable accident, fill out and forward to the CO a CA-1 form, which may be obtained from CO.

B. All Other Accidents: Report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.

3.5 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the type of construction at the site.

3.6 PERSONNEL PROTECTIVE EQUIPMENT

A. Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.

3.7 EMERGENCY INSTRUCTIONS

A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

3.8 PROTECTIVE EQUIPMENT

A. Inspect personal protective equipment daily and maintain in a serviceable condition.

Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3.9 SAFETY MEETINGS

A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.

3.10 HARD HATS AND PROTECTIVE EQUIPMENT AREAS

A. The CO will designate a hard hat area. Post the hard hat area in a manner satisfactory to the CO.

B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide two hard hats for use by visitors. Change liners before reissuing hats.

3.11 TRAINING

A. First Aid: Provide adequate training to ensure prompt and efficient first aid.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 6

B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

PART 4 – SUBMITTAL PROCEDURES

4.1 DESCRIPTION

A. This section includes administrative and procedural requirements for submittals.

4.2 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Contracting Officer’s (CO's) responsive action.

B. Informational Submittals: Written information that does not require CO's approval.

Submittals may be rejected for not complying with requirements.

4.3 PROCEDURES

A. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 10 working days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 10 working days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

B. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space approximately 2 by 3 inches on label or beside title block to record

Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 7

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. Other necessary identification.

C. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

D. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

E. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

F. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

G. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

H. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

I. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

4.4 ACTION SUBMITTALS

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit four copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 8

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

4.5 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit two copies of each submittal, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

B. Contractor's Construction Schedule: Provide a construction schedule.

C. Cost Breakdown: Following award provide a cost breakdown schedule listing main types of work with associated costs for each bid item.

PART 5 – TEMPORARY FACILITIES AND CONTROLS

5.1 DESCRIPTION

A. This section consists of requirements for temporary facilities and controls, including utilities, support facilities, and security and protection facilities.

5.2 UTILITIES

A. Water Service: Use of Government existing water service facilities will be permitted without metering and without payment of use charges, as long as facilities are cleaned and maintained in a condition acceptable to CO. At Substantial Completion, restore these facilities to condition existing before initial use.

B. Sanitary Facilities: Use of Government sanitary facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to CO. At Substantial Completion, restore these facilities to condition existing before initial use.

C. Electric Power and Lighting Service: Use of Government's existing electric power and lighting service will be permitted without metering and without payment of use charges, as long as equipment is maintained in a condition acceptable to CO.

D. Telephone Service: The Contractor is responsible for providing telephone service deemed necessary for the duration of the construction.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 9

5.3 STORAGE AREAS

A. Coordinate on-site storage requirements with the Contracting Officer.

5.4 CONSTRUCTION WASTE DISPOSAL FACILITIES

A. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste.

5.5 SUPPORT FACILITIES INSTALLATION

A. Locate temporary construction and support facilities for easy access.

5.6 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects. Restrict use of noisemaking tools and equipment to hours that will minimize complaints from persons or firms near Project site.

B. Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erecting structurally adequate barricades. Paint with appropriate colors, graphics, and warning signs to inform personnel and public of possible hazard. Where appropriate and needed, provide lighting, including flashing red or amber lights.

C. Fire Protection:

1. Store combustible materials in containers in fire-safe locations.

2. Maintain unobstructed access to fire extinguishers, fire hydrants, fire-protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.

3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.

PART 6 – EXECUTION REQUIREMENTS

6.1 DESCRIPTION

A. This section consists of general procedural requirements governing execution of the Work including, but not limited to, the following:

1. General installation of products.

2. Progress cleaning.

3. Protection of installed construction.

4. Correction of the Work.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 10

6.2 EXAMINATION

A. Existing Conditions: Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work.

B. Acceptance of Conditions: Examine areas, and conditions, with Installer. Record observations.

1. Examine roughing-in for electrical systems to verify actual locations of connections before equipment and fixture installation.

2. Proceed with installation only after unsatisfactory conditions have been corrected.

Proceeding with the Work indicates acceptance of surfaces and conditions.

6.3 PREPARATION

A. Field Measurements: Take field measurements as required to fit the Work properly.

B. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO.

Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

6.4 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

B. Comply with manufacturer's written instructions and recommendations for installing products.

C. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.

6.5 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 11

B. Site: Maintain Project site free of waste materials and debris.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

D. Waste Disposal: Burying or burning waste materials on-site will not be permitted.

Washing waste materials down sewers or into waterways will not be permitted.

6.6 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.

6.7 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

PART 7 – OPERATIONS AND MAINTENANCE MANUALS

7.1 DESCRIPTION

A. This Section consists of administrative and procedural requirements for operation and maintenance manuals.

7.2 SUBMITTALS

A. Submit two manuals in final form at least 15 working days before final inspection.

7.3 OPERATION AND MAINTENANCE MANUALS

A. Assemble a complete set of operation and maintenance data indicating the operation and maintenance of each system, subsystem, and piece of equipment not part of a system.

Include operation and maintenance data required in individual Specification Sections and as follows:

1. Operation Data: Include emergency instructions and procedures, system and equipment descriptions, operating procedures, and sequence of operations.

2. Maintenance Data: Include manufacturer's information, list of spare parts, maintenance procedures, maintenance and service schedules for preventive and routine maintenance, and copies of warranties and bonds.

B. Organization: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 12

part of a system. Each manual shall contain a title page, table of contents, and manual contents.

C. Title Page: Enclose title page in transparent plastic sleeve. Include the following information:

1. Subject matter included in manual.

2. Name and address of Project.

3. Name and address of Job Corps.

4. Date of submittal.

5. Name, address, and telephone number of Contractor.

6. Cross-reference to related systems in other operation and maintenance manuals.

D. Table of Contents: List each product included in manual, identified by product name, indexed to content of volume, and cross-referenced to Specification Section.

E. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.

1. Binders: Heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.

a. Identify each binder on front and spine, with printed title "OPERATION

AND MAINTENANCE MANUAL," Project title or name, and subject matter of contents. Indicate volume number for multiple-volume sets.

2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section. Mark each tab to indicate contents. Include typed list of products and major components of equipment included in the section on each divider, cross-referenced to Specification Section number and title of Project Manual.

3. Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose diagnostic software diskettes for computerized electronic equipment.

4. Drawings: Attach reinforced, punched binder tabs on drawings and bind with text.

a. If oversize drawings are necessary, fold drawings to same size as text pages and use as foldouts.

b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes and bind envelopes in rear of manual. At appropriate locations in manual, insert typewritten pages indicating drawing titles, descriptions of contents, and drawing locations.

F. Content: Include operation and maintenance data required in individual Specification Sections and equipment descriptions, operating standards, operating procedures, operating logs, wiring and control diagrams, and license requirements.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 13

G. Descriptions: Include the following:

1. Product name and model number.

2. Manufacturer's name.

3. Equipment identification with serial number of each component.

4. Equipment function.

5. Operating characteristics.

6. Performance curves.

7. Engineering data and tests.

8. Complete nomenclature and number of replacement parts.

H. Source Information: For each product, list name, address, and telephone number of Installer or supplier.

I. Operating Procedures: Include startup, break-in, and control procedures; stopping and normal shutdown instructions; routine, normal, seasonal, and weekend operating instructions; and required sequences for electric or electronic systems.

J. Systems and Equipment Controls: Describe sequence of operation, and diagram controls as installed.

K. Maintenance Procedures: For each system, subsystem, and piece of equipment not part of a system, include manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, drawings and diagrams for maintenance, nomenclature of parts and components, and recommended spare parts for each component part or piece of equipment.

L. Maintenance and Service Schedules: Include service and lubrication requirements, list of required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment.

M. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual.

1. Provide heavy paper dividers with plastic-covered tabs for each separate warranty.

Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

PART 8 – CLOSEOUT PROCEDURES

8.1 DESCRIPTION

A. This section consists of administrative and procedural requirements for contract closeout, including, but not limited to, the following:

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 14

1. Inspection procedures.

2. Project Record Documents.

3. Final cleaning.

8.2 SUBSTANTIAL COMPLETION

A. Definition of Substantial Completion: The Date certified by the Contracting Officer when construction is sufficiently complete, in accordance with the Contract Documents, so the Government can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.

B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

2. Advise Contracting Officer (CO) of pending insurance changeover requirements.

3. Submit specific warranties, workmanship bonds, final certifications, and similar documents.

4. Obtain and submit releases permitting Government unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.

5. Prepare and submit Project Record Documents, operation and maintenance manuals, Final Completion construction photographs and photographic negatives, and similar final record information.

6. Complete startup testing of systems.

7. Complete final cleaning requirements, including touchup painting.

8. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

C. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by CO, that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for Final Completion.

8.3 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 15

1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

2. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

3. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.

B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

8.4 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

8.5 PROJECT RECORD DOCUMENTS

A. General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for CO's reference during normal working hours.

B. Record Drawings: Maintain and submit one set of blue- or black-line white prints of Contract Drawings and Shop Drawings.

1. Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.

a. Give particular attention to information on concealed elements that cannot be readily identified and recorded later.

b. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.

2. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 010150 – 16

3. Note Construction Change Directive numbers, Change Order numbers, alternate numbers, and similar identification where applicable.

4. Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. Organize into manageable sets;

bind each set with durable paper cover sheets. Include identification on cover sheets.

8.6 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

2. Remove tools, construction equipment, machinery, and surplus material from Project site.

3. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.

Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

D. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on Government property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully.

END OF SECTION 010150

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 081113 - 1

PINE RIDGE JOB CORPS CCC HOLLOW METAL FRAMES

SECTION 081113

HOLLOW METAL FRAMES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes hollow-metal frames.

1.2 DEFINITIONS

A. Minimum Thickness: Minimum thickness of base metal without coatings according to NAAMM-HMMA 803 or SDI A250.8.

1.3 SUBMITTALS

A. As specified in Division 1 Section, “Submittal Procedures.”

1. Submit manufacturer’s literature for each type of product specified.

1.4 QUALITY ASSURANCE

A. Fire-Rated Assemblies: Complying with NFPA 80 and listed and labeled by a quali-fied testing agency for fire-protection ratings indicated, based on testing at positive pressure according to NFPA 252 or UL 10C.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, available manufacturers of-fering products that may be incorporated into the Work include, but are not limited to, the following:

1. Amweld International, LLC.

2. Ceco Door Products; an Assa Abloy Group company.

3. Commercial Door & Hardware Inc.

4. Curries Company; an Assa Abloy Group company.

5. Door Components, Inc.

6. Greensteel Industries, Ltd.

7. Premier Products, Inc.

8. Republic Doors and Frames.

9. Security Metal Products Corp.

10. Steelcraft; an Ingersoll-Rand company.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 081113 - 2

2.2 MATERIALS

A. Recycled Content of Steel Products: Postconsumer recycled content plus one-half of preconsumer recycled content not less than 25 percent.

B. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B;

suitable for exposed applications.

C. Hot-Rolled Steel Sheet: ASTM A 1011/A 1011M, Commercial Steel (CS), Type B;

free of scale, pitting, or surface defects; pickled and oiled.

D. Metallic-Coated Steel Sheet: ASTM A 653/A 653M, Commercial Steel (CS), Type B.

E. Frame Anchors: ASTM A 879/A 879M, Commercial Steel (CS), 04Z (12G) coating designation; mill phosphatized.

1. For anchors built into exterior walls, steel sheet complying with ASTM A 1008/A 1008M or ASTM A 1011/A 1011M, hot-dip galvanized ac-cording to ASTM A 153/A 153M, Class B.

F. Inserts, Bolts, and Fasteners: Hot-dip galvanized according to ASTM A 153/A 153M.

G. Power-Actuated Fasteners in Concrete: From corrosion-resistant materials.

2.3 INTERIOR HOLLOW-METAL FRAMES

A. Fabricated from cold-rolled steel sheet unless metallic-coated sheet is indicated.

1. Fabricate frames with mitered or coped corners.

2. Fabricate frames as full profile welded.

3. Frames for Level 3 Steel Doors (At all interior locations): Metallic-coated

0.053-inch- (1.3-mm-) thick steel sheet.

4. Frames for Wood Doors: 0.053-inch- (1.3-mm-) thick steel sheet.

5. Exposed Finish: Prime.

B. Hardware Reinforcement: ANSI/SDI A250.6.

2.4 FRAME ANCHORS

A. Jamb Anchors:

1. Masonry Type: Adjustable strap-and-stirrup or T-shaped anchors to suit frame size, not less than 0.042 inch (1.0 mm) thick, with corrugated or perforated straps not less than 2 inches (51 mm) wide by 10 inches (254 mm) long; or wire anchors not less than 0.177 inch (4.5 mm) thick.

2. Stud-Wall Type: Designed to engage stud, welded to back of frames; not less than 0.042 inch (1.0 mm) thick.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 081113 - 3

3. Compression Type for Drywall Slip-on Frames: Adjustable compression an-chors.

4. Postinstalled Expansion Type for In-Place Concrete or Masonry: Minimum 3/8-inch- (9.5-mm-) diameter bolts with expansion shields or inserts. Provide pipe spacer from frame to wall, with throat reinforcement plate, welded to frame at each anchor location.

B. Floor Anchors: Formed from same material as frames, minimum thickness of 0.042 inch (1.0 mm), and as follows:

1. Monolithic Concrete Slabs: Clip-type anchors, with two holes to receive fasten-ers.

2. Separate Topping Concrete Slabs: Adjustable-type anchors with extension clips, allowing not less than 2-inch (51-mm) height adjustment. Terminate bottom of frames at finish floor surface.

2.5 FABRICATION

A. Fabricate hollow-metal work to be rigid and free of defects, warp, or buckle. Accu-rately form metal to required sizes and profiles, with minimum radius for metal thick-ness. Where practical, fit and assemble units in manufacturer's plant. To ensure proper assembly at Project site, clearly identify work that cannot be permanently factory as-sembled before shipment.

B. Hollow-Metal Frames: Where frames are fabricated in sections due to shipping or handling limitations, provide alignment plates or angles at each joint, fabricated of same thickness metal as frames.

1. Frames: Provide closed tubular members with no visible face seams or joints, fabricated from same material as door frame. Fasten members at crossings and to jambs by butt welding.

2. Provide countersunk, flat- or oval-head exposed screws and bolts for exposed fasteners unless otherwise indicated.

3. Floor Anchors: Weld anchors to bottoms of jambs with at least four spot welds per anchor; however, for slip-on drywall frames, provide anchor clips or coun-tersunk holes at bottoms of jambs.

4. Jamb Anchors: Provide number and spacing of anchors as follows:

a. Stud-Wall Type: Locate anchors not more than 18 inches (457 mm) from top and bottom of frame. Space anchors not more than 32 inches (813

mm) o.c. and as follows:

1) Three anchors per jamb up to 60 inches (1524 mm) high.

2) Four anchors per jamb from 60 to 90 inches (1524 to 2286 mm) high.

3) Five anchors per jamb from 90 to 96 inches (2286 to 2438 mm) high.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 081113 - 4

4) Five anchors per jamb plus one additional anchor per jamb for each 24 inches (610 mm) or fraction thereof above 96 inches (2438 mm) high.

b. Compression Type: Not less than two anchors in each frame.

c. Postinstalled Expansion Type: Locate anchors not more than 6 inches (152

mm) from top and bottom of frame. Space anchors not more than 26 inch-es (660 mm) o.c.

5. Door Silencers: Except on weather-stripped frames, drill stops to receive door silencers.

a. Single-Door Frames: Drill stop in strike jamb to receive three door silenc-ers.

C. Hardware Preparation: Factory prepare hollow-metal work to receive templated mor-tised hardware; include cutouts, reinforcement, mortising, drilling, and tapping accord-ing to SDI A250.6, BHMA A156.115 and templates.

2.6 STEEL FINISHES

A. Factory Finish: SDI A250.3.

1. Color and Gloss: As selected from manufacturer’s full range.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Hollow-Metal Frames: Install hollow-metal frames of size and profile indicated. Com-ply with SDI A250.11 or NAAMM-HMMA 840 as required by standards specified.

1. Set frames accurately in position; plumbed, aligned, and braced securely until permanent anchors are set. After wall construction is complete, remove tempo-rary braces, leaving surfaces smooth and undamaged.

a. At fire-protection-rated openings, install frames according to NFPA 80.

b. Where frames are fabricated in sections because of shipping or handling limitations, field splice at approved locations by welding face joint contin-uously; grind, fill, dress, and make splice smooth, flush, and invisible on exposed faces.

c. Install frames with removable stops located on secure side of opening.

d. Remove temporary braces necessary for installation only after frames have been properly set and secured.

e. Check plumb, square, and twist of frames as walls are constructed. Shim as necessary to comply with installation tolerances.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 081113 - 5

2. Floor Anchors: Provide floor anchors for each jamb and mullion that extends to floor, and secure with postinstalled expansion anchors.

3. In-Place Concrete or Masonry Construction: Secure frames in place with postinstalled expansion anchors. Countersink anchors, and fill and make smooth, flush, and invisible on exposed faces.

4. Installation Tolerances: Adjust hollow-metal door frames for squareness, align-ment, twist, and plumb to the following tolerances:

a. Squareness: Plus or minus 1/16 inch (1.6 mm), measured at door rabbet on a line 90 degrees from jamb perpendicular to frame head.

b. Alignment: Plus or minus 1/16 inch (1.6 mm), measured at jambs on a horizontal line parallel to plane of wall.

c. Twist: Plus or minus 1/16 inch (1.6 mm), measured at opposite face cor-ners of jambs on parallel lines, and perpendicular to plane of wall.

d. Plumbness: Plus or minus 1/16 inch (1.6 mm), measured at jambs at floor.

3.2 ADJUSTING AND CLEANING

A. Final Adjustments: Check and readjust operating hardware items immediately before final inspection. Leave work in complete and proper operating condition. Remove and replace defective work, including hollow-metal work that is warped, bowed, or other-wise unacceptable.

B. Metallic-Coated Surface Touchup: Clean abraded areas and repair with galvanizing repair paint according to manufacturer's written instructions.

C. Touchup Painting: Cleaning and touchup painting of abraded areas.

END OF SECTION 081113

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 081113 - 6

This page intentionally left blank.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 081416- 1

PINE RIDGE JOB CORPS CCC FLUSH WOOD DOORS

SECTION 081416

FLUSH WOOD DOORS

PART 1 – GENERAL

1.1 SUMMARY

A. This Section includes solid-core doors as follows:

1. Solid core doors with wood-veneer faces.

2. Factory machining for hardware.

1.2 SUBMITTALS

A. As specified in Division 1, “Submittal Procedures.”

1. Product Data: For each type of door. Include factory-finishing specifications.

2. Samples: For each face material and finish.

1.3 QUALITY ASSURANCE

A. Manufacturer Qualifications: A qualified manufacturer that is certified for chain of custody by an FSC-accredited certification body.

B. Quality Standard: Comply with AWI's "Architectural Woodwork Quality Standards Illustrated."

C. Fire-Rated Wood Doors: Doors that are listed and labeled by a testing and inspecting agency for fire ratings indicated.

PRODUCTS

2.1 MANUFACTURERS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers of-fering products that may be incorporated into the Work include, but are not limited to, the following:

1. Algoma Hardwoods Inc.

2. Ampco Products, Inc.

3. Buell Door Company.

4. Eagle Plywood & Door Manufacturing, Inc.

5. Eggers Industries; Architectural Door Division.

6. Oshkosh Architectural Door Co.

7. VT Industries Inc.

8. Weyerhaeuser Company.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 081416- 2

2.2 DOOR CONSTRUCTION

A. Low-Emitting Materials: Provide doors made with adhesives and composite wood products that do not contain urea formaldehyde.

B. Doors for Transparent Finish:

1. Grade: Custom Grade A faces.

2. Species and Cut: White Oak, plain sliced.

3. Match between Veneer Leaves: Book match.

4. Assembly of Veneer Leaves on Door Faces: Center balance match.

C. Interior Veneer-Faced Solid-Core Doors:

1. Core: Either glued block or structural composite lumber.

2. Construction: Five plies with stiles and rails bonded to core, then entire unit abrasive planed before veneering.

D. Fire-Rated Doors:

1. Construction: Construction and core specified above for type of face indicated or manufacturer's standard mineral-core construction as needed to provide fire rating indicated.

2. Edge Construction: Manufacturer's standard laminated-edge construction with improved screw-holding capability and split resistance.

3. Edge Construction for fire rated doors: Intumescent seals concealed by outer stile matching face veneer, and laminated backing for improved screw-holding capability and split resistance.

E. Provide doors with structural composite lumber cores instead of particleboard cores at locations where exit devices are indicated.

2.3 GLAZING AND LIGHT FRAMES

A. Factory Glazing: Transparent, laminated glass with fire-protection rating for assembly in which glazing material is installed, and permanently labeled by a testing and in-specting agency.

B. Metal Frames for Light Openings in Fire-Rated Doors: Manufacturer's standard frame formed of 0.048-inch- (1.2-mm-) thick, cold-rolled steel sheet; with baked-enamel- or powder-coated finish; and approved for use in doors of fire-protection rating indicated.

2.4 FABRICATION

A. Factory fit doors to suit frame-opening sizes indicated. Comply with clearance re-quirements of referenced quality standard for fitting. Comply with requirements in NFPA 80 for fire-rated doors.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 081416- 3

B. Factory machine doors for hardware that is not surface applied. Factory install glass.

C. Openings: Cut and trim openings through doors to comply with applicable require-ments of referenced standards for kind(s) of door(s) required.

1. Light Openings: Trim openings with moldings of material and profile indicated.

2.5 FACTORY FINISHING

A. General: Comply with referenced quality standard for factory finishing. Complete fabrication, including fitting doors for openings and machining for hardware that is not surface applied, before finishing.

1. Finish faces, all four edges, edges of cutouts, and mortises. Stains and fillers may be omitted on top and bottom edges, edges of cutouts, and mortises.

B. Finish doors at factory with transparent finish.

1. Grade: Custom.

2. Finish: AWI System TR-4 conversion varnish.

3. Finish: Manufacturer's standard finish with performance comparable to AWI

System TR-6 catalyzed polyurethane.

4. Staining: As selected by CO from manufacturer's full range.

5. Effect: Semifilled finish.

6. Sheen: Semigloss.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install doors to comply with manufacturer's written instructions, referenced quality standard, and as indicated.

1. Install fire-rated doors in corresponding fire-rated frames according to

NFPA 80.

B. Factory-Fitted Doors: Align in frames for uniform clearance at each edge.

C. Factory-Finished Doors: Restore finish before installation if fitting or machining is required at Project site.

END OF SECTION 081416

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 081416- 4

This page intentionally left blank.

MISCELLANEOUS BUILDING LIFE SAFETY REPAIRS 087100 - 1

PINE RIDGE JOB CORPS CCC DOOR HARDWARE

SECTION 087100

DOOR HARDWARE

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes mechanical door hardware for swinging doors.

1.2 SUBMITTALS

A. As specified in Division 1 Section, “Submittal Procedures.”

1. Submit manufacturer’s literature for each type of product specified.

2. Sample warranties.

3. Door Hardware Schedule: Prepared by or under the supervision of Installer, de-tailing fabrication and assembly of door hardware, as well as installation proce-dures and diagrams. Coordinate final door hardware schedule with doors, frames, and related work to ensure proper size, thickness, hand, function, and finish of door hardware.

a. Content: Include the following information:

1) Building name and number, location, hand, fire rating, size, and ma-terial of each door and frame.

2) Complete designations, including name and manufacturer, type, style, function, size, quantity, function, and finish of each door hardware product.

1.3 CLOSEOUT SUBMITTALS

A. As specified in Division 1 Section, “Submittal Procedures.”

1. Operation and Maintenance Manuals: Provide for each type of door hardware.

2. Warranties.

1.4…