RFI Official Responses - 2.pdf
PDF 150 KB Posted
- Attached to
- 127EAW22R0037 - Loop 6 Bridge Replacement Federal contract opportunity
- Solicitation number
- 127EAW22R0037
- Issued by
- Department of Agriculture Forest Service
About this file
This document contains a Request for Information (RFI) related to solicitation 127EAW22R0037 for the Loop 6 Bridge Replacement project. The RFI responses will be provided through amendments posted to beta.SAM.gov by the contracting officer. One question was asked regarding substituting 3/8 inch A588 steel in place of 5/16 inch due to availability and cost issues, to which the response was that the substitution would be acceptable. The solicitation is for the Loop 6 Bridge Replacement project managed by the Tahoe National Forest of the Department of Agriculture Forest Service. The total value of the construction project is between $250,000 and $500,000, and it is set aside for total small business. Responses to the RFI are due by May 18, 2022.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI Official Responses - 3.pdf | ||
| A00004 - RFIs.pdf | ||
| A00003 - RFIs.pdf | ||
| A00002 - RFIs.pdf | ||
| RFI Official Responses - 1.pdf | ||
| A00001 - Time Extension.pdf | ||
| 6. Forest Service Supplemental Specifications.pdf | ||
| 5. Bridge Pictures.pdf | ||
| 2. Fire Plan.pdf | ||
| 127EAW22R0037 - Loop 6 Bridge Replacement.pdf | ||
| 1. Statement of Work.pdf | ||
| 3. Schedule.docx | DOCX document | |
| 4. Map and Drawings.pdf | ||
| 7. Davis-Bacon Act WD # CA20220007.pdf | ||
| 8. RFI Form.docx | DOCX document |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOR OFFICIAL USE ONLY
REQUEST FOR INFORMATION (RFI) OFFICIAL RESPONSES
127EAW22R0037 - Loop 6 Bridge Replacement
RFI responses will be responded to as necessary in amendment format which will be posted to the solicitation via beta.SAM.gov
Telephone requests for information will not be accepted or returned.
RFI #1 – Grade A588 Steel is not readily available in 5/16”, this is not a common thickness in the
A588 Industry, can 3/8” A588 be substituted ILO of 5/16”?
5/16” is available but in such a small quantity it would add significant cost to the project as there are minimums of materials that need to be produced for the mill to be do it.
USFS Response –
Yes, 3/8” A588 can be substituted ILO of 5/16”.
-H. Dodini/Bridge Engineer