About this file
This solicitation is for the replacement of Loop 6 Bridge #1 on the Loop 6 motorcycle trail in the Tahoe National Forest. The project includes removing the existing damaged bridge and furnishing and constructing a new 61 foot long, 2 inch wide trail bridge with a 413 square foot deck. The contractor will be responsible for all labor, equipment, materials, permits, and testing to complete the project. Optional work includes dismantling the existing bridge superstructure.
The performance period is 59 calendar days with a completion date of December 1, 2022. The solicitation is a total small business set aside between $250,000-$500,000 issued by the Department of Agriculture Forest Service. The statement of work specifies construction requirements and references standard specifications. Requests for information are due by May 18, 2022. No pre-proposal site visit will be held but the project site is open to the public.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A00004 - RFIs.pdf | ||
| RFI Official Responses - 3.pdf | ||
| A00003 - RFIs.pdf | ||
| RFI Official Responses - 2.pdf | ||
| RFI Official Responses - 1.pdf | ||
| A00002 - RFIs.pdf | ||
| A00001 - Time Extension.pdf | ||
| 5. Bridge Pictures.pdf | ||
| 127EAW22R0037 - Loop 6 Bridge Replacement.pdf | ||
| 3. Schedule.docx | DOCX document | |
| 4. Map and Drawings.pdf | ||
| 7. Davis-Bacon Act WD # CA20220007.pdf | ||
| 8. RFI Form.docx | DOCX document | |
| 2. Fire Plan.pdf | ||
| 6. Forest Service Supplemental Specifications.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Loop 6 Trail Bridge #1 Replacement Project
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
SCOPE OF CONTRACT
This project is to replace the damaged 61 foot 2-inch-long trail bridge #1 on the Loop 6 motorcycle trail (413 sq. ft. deck). This project is to furnish and construct the new trail bridge and includes the removal of the existing damaged bridge structure. Access to site is by helicopter, motorcycle or on foot. There is no vehicular access, 4WD of otherwise, within 1.5 miles of the site. Please see attached access map. Contractor is responsible for furnishing aerial lift capable of transporting required loads, as well as all labor, equipment, supervision, materials, permits and required testing necessary to complete the project as shown in the specifications and drawings.
OPTIONS:
Optional Item 1) dismantle the existing bridge’s wooden superstructure.
Best Management Practices have been effective in protecting beneficial uses within the affected watersheds. Most are BMPs from the Forest Service publication "Water Quality Management for National Forest System Lands in California" (USDA Forest Service, 201, R5 FSH
2509.22 Chapter 10). All applicable water quality BMPs shall be implemented. The implementation phase of the BMPs occur after a project is completed, but before the winter season. BMP monitoring of the project is done one year later after the project experiences one rainy season. A list of BMPs used within this project: BMP 2.13, BMP 2.3, BMP 2.4, BMP 2.5, BMP 2.8, BMP 2.11, BMP 4.5, BMP 7.1, BMP 7.4, BMP 7.6, BMP 7.8.
PROJECT LOCATION
The project is located in Placer County, CA at Site # 1 of the El Dorado Creek crossing, on the Loop 6 motorcycle trail of the Tahoe National Forest 7.4 miles Northeast of Foresthill, CA. The primary helicopter staging area for this project is the Forest Service Seed Orchard (Lat. 39.0875, Lon. -120.7338 - 1.8 air miles from bridge site)
PROJECT PERIOD OF PERFORMANCE
59 Calendar Days
PROJECT COMPLETION DATE
December 1, 2022
RESTRICTIONS ON WORK
Work shall be performed during daylight hours between 0700 hrs and 1900 hrs local time.
Exceptions to these times are:
1. In accordance with the fire plan, if included in Section J.
2. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
SUBMITTALS
SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications.
INSURANCE & CERTIFICATIONS
The Contractor shall provide evidence of Worker's Compensation Insurance or a written explanation as to why the Contractor is exempt from the requirement. NOTE: The Contractor working alone is not required to carry the insurance.
DRAWINGS AND SPECIFICATIONS
Specifications:
[ ] Construction Standard Institute (CSI) specifications These specifications are physically incorporated in the solicitation.
[ ] Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-03 (US Customary Units) This document is incorporated by reference and is available on the web in electronic PDF https://flh.fhwa.dot.gov/resources/specs/fp-03/fp-03usc.pdf
[X] Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-14 (US Customary Units) This document is incorporated by reference and is available on the web in electronic PDF
(https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf)
[ ]1996 road and bridge specifications-- Standard Specifications applicable to this project can be found in Forest Service Specifications for Construction of Roads & Bridges, August 1996 (EM-7720-100), which is incorporated by reference. The publication is available for purchase from the Superintendent of Documents, US Government Printing Office (GPO), Washington, DC 20402 (202-512-1800). The GPO stock number is 001-001-00660-2. It may also be accessed electronically at the following website address: http://www.fs.fed.us/.ftproot/pub/acad https://flh.fhwa.dot.gov/resources/specs/fp-03/fp-03usc.pdf https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf http://www.fs.fed.us/.ftproot/pub/acad
[ ] 1985 road and bridge specifications-- Standard Specifications applicable to this project can be found in Forest Service Specifications for Construction of Roads & Bridges, April 1985, which is incorporated by reference. The publication is out of print. Contact the issuing office for copies of relevant specifications.
[ ] Trail specifications-- Standard Specifications applicable to this project can be found in Standard Specifications for Construction and Maintenance of Trails, September 1996 (EM-7720-103), which is incorporated by reference. The publication is available for purchase from the Superintendent of Documents, US Government Printing Office (GPO), Washington, DC 20402 (202-512-1800). The GPO stock number is 001-001-00661-1. It may also be accessed electronically at the following website address: http://www.fs.fed.us/.ftproot/pub/acad
Special Project Specifications are physically incorporated within this solicitation, beginning on the next page.
The following specifications are used to do the described work:
101 – Terms, Format, Definitions 108 – Prosecution and Progress 102 – Bid, award & Execution 109 – Measurement and Payment 103 – Scope of Contract 150 – Mobilization 104 – Control of Contract 105 – Control of Material 106 – Acceptance of Work 107 – Legal Relations, Responsibility http://www.fs.fed.us/.ftproot/pub/acad
File details come from the government source that posted it. Updated .