SOW - 2020 Valve Vault 108 Removal.docx

DOCX document 31 KB Posted

Attached to
Valve Vault 108 Federal contract opportunity
Solicitation number
12619720B0004
Issued by
Department of Agriculture Animal and Plant Health Inspection Service Veterinary Services

View the file

Other files for this federal contract opportunity

Other files attached to Valve Vault 108, newest first.
File Type Posted
A00003.pdf PDF
A00002.pdf PDF
A0002 Supplemental Drawing9.2.20.pdf PDF
A00002Questions received from Contractor.docx DOCX document
A00001.pdf PDF
SF 1442 (3).pdf PDF
12619720b0004.docx DOCX document
2020 Valve Vault 108 Removal Drawing.pdf PDF
wages.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work 2020 Valve Vault 108 Removal Project USDA, Ames, IA 7-9-2020

1.0Project Requirements:
A.Background:

Valve Vault 108 was used to supply steam and condensate to Building 400. Building 400 has been removed and the piping to Building 400 was isolated in Valve Vault 107 with the piping between vaults 107 and 108 abandoned in place. Valve Vault 108 was also left in place. This has allowed water to collect in vault 108 and to run along the abandoned piping into vault 107, causing corrosion and damage to pipe insulation, and could lead to component failure resulting in a loss of steam to Building 21.

B. Scope of Work:

The general scope of this project is to remove the abandoned piping between Valve Vaults 107 and 108, remove the pipe penetration into vault 107, patch the opening of Vault 107 with reinforced concrete, and remove valve vault 108. Contractor shall perform the following duties as part of this removal:

· Saw cut and remove approximately 7,200 square feet of parking lot and 300 square feet of sidewalk. Note: work shall be phased to only one parking lot at a time to maintain a pathway to the east parking lots of Building 21.

· Excavate and remove approximately 400’ of 3” and 6” steel steam and condensate piping along with the 28” diameter steel conduit.

· Excavate and remove Valve Vault 108, which is approximately 10’ wide X 18’ long X 10’ high.

· Remove conduit penetration into Valve Vault 107 along with all associated insulation and link seal, complete to bare concrete vault wall. Note: work inside Valve Vault 107 will need to be coordinated with owner. Steam must be shutdown prior to vault entry and work will need to be performed on a Saturday. Average ambient Temperatures must be above 40°F to shutdown steam.

· Remove complete all piping and conduit in Valve Vault 107 that was previously abandoned.

· Contractor shall patch the penetration hole into Valve Vault 107 wall with concrete to match existing the existing construction of walls, and create a water proof seal on the wall. Dowel a minimum of three (3) #5 rebar into existing hole, evenly spaced both horizontally and vertically to provide structural reinforcement for concrete to be poured into hole in vault wall. Seal exterior face of vault wall with water proofing to prevent any ground moisture infiltration into vault 107. See detail four (4) on sheet 7 of 7 for existing vault penetration detail.

· Backfill and restore all disturbed ground.

· Replace removed concrete parking lot. New concrete shall be at a minimum, the same thickness of slab as existing concrete paving. Contractor shall install new #5 rebar reinforcing 16” on center (2” from bottom of pour) in each direction in all areas receiving new concrete and dowel rebar into any existing adjacent concrete of area receiving new concrete a minimum of 8” into existing paving. All new concrete in this area shall be sloped to match existing slope towards existing area drains.

· Replace removed concrete sidewalk.

· All ground shall be repaired to match existing surrounding construction and finish (including the grassy areas). Contractor shall match all USDA rules and regulations as well as IADOT specifications 2601 for application for seeding areas.

· Grass seed shall consist of following mix (minimum pounds of pure live seed)

· Annual Rye Grass – 9 lbs per acre.

· Perennial Rye Grass – 40 lbs per acre

· Creeping red fescue – 18 lbs per acre

· Kentucky blue grass – 126 lbs per acre

· Total = 184 lbs per acre.

· Starter fertilizer with minimum guaranteed analysis of 6-24-24 or approved alternate fertilizer shall be applied to all areas to be seeded.

· Remove all rocks and foreign debris from ground prior to seeding grassy areas.

· Prior to seeding, spread a minimum of 6” of clean, black topsoil on disturbed area and disc or harrow until surface has been thoroughly loosened to a depth of 3-4 inches.

Contractors are encouraged to schedule a Site Visit with the COR, Leo Mincks, Work Cell Phone: (515) 231-1574 or other COR as assigned prior to submitting their proposal.

C. Project Timeline:

Contractor shall be given 180 days from the “Notice to Proceed” to complete the project.

2.0 General Requirements

2.01 Work Restrictions & Conditions

A. Site Security Access

1. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/subcontractor employees shall sign-in and out at the main site entrance gate and wear a contractor/visitor identification badge at all times while on the site. The ID badges will be turned in at the end of the work day. A current government-issued identification with a picture ID is required for entry.

2. Access to each individual site shall be arranged by the Contracting Officer's Representative according to the schedule submitted by the contractor and approved by the Contracting Officer’s Representative. The contractor shall coordinate and schedule his/her work under this contract to cause the least interference with the normal flow of visitor and employee traffic.

3. Construction vehicles will be allowed access adjacent to the work; contractor employee’s personal vehicles shall be parked in the facility parking lots.

4. The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative.

5. Work shall be confined to the areas identified on the Drawings. Unless accompanied by a NCAH/USDA employee, the Contractor, subcontractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.

6. Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs.

7. Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/subcontractor employees from the site and barring further site access to individuals.

B. Work Hours: Regular work hours for the site are 6:30 AM to 5:30PM, Monday through Friday, excluding Government holidays. Requests for exceptions to this schedule shall be made in writing forty-eight (48) hours in advance and approved by the Contracting Officer's Representative.

C. Work Outside Regular Work Hours: Work scheduled outside regular work hours including late hours, Saturdays, Sundays, and Government holidays requires Contracting Officer’s Representative (COR) approval in advance. Make application to the COR at least 5 calendar days prior to such work to allow arrangements to be made by the Government for access to the work area and inspection & monitoring arrangements. Requests shall include the exact dates, hours, location, and purpose of the exception. If approved, the COR will coordinate access with the site security office.

D. Construct Work in stages to accommodate Owner’s use of premises during construction period. Coordinate construction schedule and operations with Contracting Office’s Representative (COR).

1. Access Schedule Work to minimize use of street barricades and detours.

2. Access Phases of construction are those indicated in Drawings.

E. Coordinate use of premises under direction of the COR. Contractor shall confine construction equipment, storage of materials and equipment and operations of workers to areas permitted by law, ordinances, permits, or requirements of Contract Documents, and shall not unreasonably encumber premises with construction equipment or other material or equipment.

1. Assume full responsibility for protection and safekeeping of items under this Agreement, stored on site.

2. Move any stored items, under Contractor’s control, which interfere with operations of Owner or separate contractor.

3. Obtain and pay for use of additional storage or Work areas needed for operations.

F. Owner will occupy premises during entire period of construction for conduct of its normal operations. Coordinate with Owner’s Representative/COR in all construction operations to minimize conflict, and to facilitate Owner usage. Contractor shall at all times conduct its operations as to ensure least inconvenience to Owner.

2.2 Special Agreement Checks (SAC)

A. Use of Premises

1. Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the work is approved.

2. Keep driveways and entrances serving premises clear and available to the Government, employees, visitors and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

3. Limited parking may be available on the site away from each facility.

4. All contractor staff shall pass an appropriate APHIS designated background investigation before performing any work. The contractor personnel who will perform work at the USDA, NCAH facilities will be required to complete and have a favorable determination of suitability for OFI Form 86C, Special Agreement Checks (SAC) prior to starting work under this contract.

a. The contractor shall provide a list of intended employees to the Contracting Officer’s Representative within three (3) calendar days of task order award.

b. The contractor shall keep the list of employees up to date throughout the project in the event of employee separation and transfer.

B. Adherence to Security Policies and Procedures

1. The Contractor shall adhere to all Site, APHIS and USDA security policies and procedures including Code of Federal Regulations Requirements, Standard Operating Procedures, Security Directives, Security Procedures, General Orders, Post Orders and any applicable Government Policies and Procedures.

a. Failure to adhere to or violation of any above listed requirements, procedures, directives, orders and/or policies may result in criminal prosecution or contractor representative or contractor employee (violator) removal.

2.3 Intent of Contract Drawings

A. Government provided drawings, henceforth referred to as “Contract Drawings”, do not attempt to show complete details of building construction that may affect installation. Government provided diagrams of proposed systems are for reference only and do not necessarily show physical arrangement of all equipment and/or maximum number of devices. Minimum system requirements are shown.

B. Devices are shown diagrammatically only. System layout does not necessarily show maximum number of system components and should not be used for obtaining quantities for linear runs of conduits and wires.

C. Locations of existing and Government concept devices are approximate and may be distorted for clarity in representation.

2.4 Regulatory Requirements

A. The equipment materials, installation, workmanship, and operation shall conform to the most stringent applicable requirements of the most recent editions of the associated publications, in the below section and in the attached specifications unless otherwise noted:

1. National Fire Protection Association (NFPA)

a. NFPA 101 – Safety to Life from Fire in Buildings and Structures.

b. NFPA 1 – Uniform Fire Code

c. NFPA 5000 – Building Construction and Safety Code

2. Underwriters Laboratories, Inc. (UL)

a. Appropriate UL Standards

3. State and Local Building Codes as adopted by the Authority Having Jurisdiction (AHJ).

4. The Uniform Federal Accessibility Standards (UFAS)

5. Occupational Safety and Health Administration (OSHA)

B. All work shall be completed in accordance with the Iowa Statewide Urban Design and Specifications (SUDAS) most recent edition. The SUDAS Standard Specifications are modified by the following additions. These are supplemental specifications and they shall prevail over those published in the SUDAS Standard Specifications Manual.

1. Underground Facilities:

a. Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the Site is based on information and data furnished to Owner by the Owners of such underground facilities, including Owner, or by others. Unless it is otherwise expressly provided in the Supplementary Conditions:

i. Owner shall not be responsible for the accuracy or completeness of any such information or data provided by others; and

ii. The cost of all of the following will be included in the Contract Price, and Contractor shall have full responsibility for:

1. Reviewing and checking all such information and data.

2. Locating all Underground Facilities shown or indicated in the Contract Documents.

3. Coordination of the Work with the Owners of such Underground Facilities, including Owner, during construction.

4. The safety and protection of all such underground facilities and repairing any damage thereto resulting from the Work.

a) Not Shown or Indicated: If an Underground Facility is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency), identify the owner of such Underground Facility and give written notice to that owner and to the COR. COR will promptly review the Underground Facility and determine the extent, if any, to which a change is required in the Contract Documents to reflect and document the consequences of the existence or location of the Underground Facility. During such time, Contractor shall be responsible for the safety and protection of such Underground Facility. If Contractor concludes that a change in the Contract Documents is required, a Work Change Directive or a Change Order will be issued to the Contracting Officer to reflect and document such consequences. An equitable adjustment shall be made in the Contract Price or Contract Times, or both, to the extent that they are attributable to the existence or location of any Underground Facility that was not shown or indicated or not shown or indicated with reasonable accuracy in the Contract Documents and that Contractor did not know of and could not reasonably have been expected to be aware of or to have anticipated. If Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment in Contract Price or Contract Times, Owner or Contractor may make a Claim.

2.5 Coordination

A. The contractor shall coordinate all work with the Contracting Officer's Representative.

C. The contractor shall submit an installation schedule for review and approval by the Contracting Officer's Representative within ten (10) days of task order award.

D. The contractor shall be solely responsible for coordinating work with all subcontractors and ensuring that all items of joint use in conjunction with installations are completed.

2.6 Special Provisions

A. There are buildings on campus that are bio-security facilities and contains biohazard materials; therefore, the contractor must complete any area specific training before entry and follow bio-security procedures for entering and exiting any such facility. In addition, any tools or equipment carried into the facility must be decontaminated before they can be removed from the facility.

B. The Contractor shall confine all operations to within the work limits of the project and exercise special care to maintain natural surroundings undamaged. All surfaces that have been altered for the installation of the concrete shall be refinished to match original condition by skilled personnel of the trades involved at no additional expense to the Government.

C. Finished surfaces of existing facilities that are affected, marred, scratched, or damaged by the contractor shall be refinished to match original condition.

1. Patching material shall be of the same type, style, and thickness, and shall be finished to match existing adjacent surface construction in color and texture.

2. Patching material, paint color, paint material and paint application methods shall be approved in advance by the Contracting Officer’s Representative.

D. No building structural members shall be cut or altered without prior approval of the Contracting Officer's Representative.

E. Any damage resulting from contractor's operation shall be brought to the attention of the Contracting Officer's Representative immediately.

F. The contractor shall take all necessary and reasonable measures to keep the work site clean of trash and debris. Work areas shall be cleaned immediately as work in that area is completed, and before moving to a new work site. Place all trash and debris in OSHA approved containers, remove, and dispose of trash off site daily.

G. The contractor shall move all materials and equipment, including ladders and scaffolding from the site at the completion of each day's operation unless otherwise approved by the Contracting Officer's Representative.

H. The contractor shall provide proper safety equipment to workmen and ensure a safe environment for employees and the general public at all times. The contractor shall work to ensure free, unobstructed, and safe access to and about the work area.

2.7 Temporary Facilities

A. Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any utility connections.

B. Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service to the project.

C. Toilet Facilities: The Contractor shall provide and maintain portable toilet facilities for the project workmen. Contractor shall coordinate location of portable toilet facilities with Owner prior to construction beginning.

2.8 Confined Space Program

A. The Contractor and/or subcontractor employees who will be entering Confined Spaces shall be adequately trained and equipped for access and extraction. The Contractor shall provide all ventilation equipment, air quality monitoring, harnesses, and other safety equipment as appropriate for OSHA compliance. The Contractor’s Confined Space program shall substantially conform to the NCAH plan.

B. The Contractor shall submit a written copy of their plan(s) for acceptance by the COR prior to entry into any confined spaces.

C. The Contractor shall provide copies of entry logs and monitoring to the Owner’s Representative at any time requested during the project effort.

2.9 Lock-out/Tag-out Program

A. The Contractor and/or subcontractor employees who will be working on the job will apply a lockout/tagout (LOTO) process to control dangerous energy sources. The Contractor/subcontractor shall have a LOTO program established and use Contractor LOTO locks, tags, and procedures.

B. The Contractor/subcontractor shall review their LOTO program with NCAH FEU personnel to coordinate LOTO programs before implementing LOTO.

2.10 Hot Work Plan

A. The Contractor/subcontractor shall have a written plan in place to manage the safety and fire hazards associated with hot work. The Plan shall include fire watch and all other requirements in accordance with OSHA. The Contractor/subcontractor shall maintain written records of hot work until final acceptance of the project and shall provide copies to the Owner’s Representatives at any time requested.

2.11 Submittal & Shop Drawings Procedures

A. Submittal Register: At the beginning of the project, the Contractor will provide a Submittal Register identifying all the items called out in the Specifications for submittal to the COR for approval (in consultation with the project AE). The Contractor will update and maintain the Submittal Register to show the current status of all required submittals.

B. Submittal Requirements

1. Format: There is no formal submittal transmittal or format for this project other than the documents shall be submitted as PDF files, scanned or created in documents that can be easily read when printed on 11x17 sheets. Exceptions for larger sheet sizes will be considered by the COR. Failure of the Contractor to provide legible submittals will be adequate grounds for rejection.

2. Identification: Submittals shall be labeled and marked for this project. The identification shall include: Contractor/subcontractor’s name, date of submittal, description of item, specification section, and details on product data that are marked clearly for this project.

C. Submittal Procedures: All submittals will be posted in PDF by the Contractor to the USDA ARS Sharepoint website that has been established for this project. The submittal reviewing authority/AE will download the submittals for review and post approvals to the Sharepoint site. This same submittal process will be used for RFIs, Change Bulletins, etc.

D. Approved Submittals: The approval/acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist.

E. Submittal items for this project :

1. Granular Sub base

2. Compaction Testing reports

3. Concrete Mix Design

4. Reinforcing Bar

2.12 Close-out Submittals

A. Warranty Documentation

1. Warranty List: Provide a warranty summary sheet in spreadsheet format with all the warranties listed by section, description, supplier, warranty contact, start date, end date. Provide electronic copy to the COR and place printed copy in the front of the Warranty Binder.

2. Warranty Copies in Binder: Provide one signed & dated copy of all warranties for products and equipment installed on the project. The Warranty binder shall be divided by Specification Section and shall be provided to the COR. An electronic (scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-out documentation.

B. Operation & Maintenance Manuals: Contractor shall provide a printed copy of all Operation & Maintenance documentation provided with equipment and systems installed in the project and place the manuals in an organized binder. The O&M Manuals shall be organized by specification section and shall have an index at the front of the binder. The Contractor shall also provide a PDF version of the Manuals to be submitted with the close-out documentation.

C. Record Drawings

1. Redline Specifications: During the construction period the Contractor shall keep an updated & marked-up or “redline” copy of the project specifications on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes. At the end of the project the Contractor shall electronically scan the redline specifications and provide an electronic copy in PDF to the Owner along with the close-out documentation.

2. Redline Drawings: During the construction period the Contractor shall keep an updated “redline” or “conformed” copy of the project drawings on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes. At the end of the project the Contractor shall electronically scan the redline drawings at full-size and in color, and provide an electronic copy in PDF to the Owner along with the close-out documentation.

3. AE Review: The Owner’s AE representative will review the redline specifications & drawings and advise the COR if the documentation appears to be full and complete. If the documentation is not complete, the Contractor will be required to provide complete redline documents before final payment is recommended.

END OF SECTION