Pre_bid_meeting_notes.pdf

PDF 78 KB Posted

Attached to
Forest Lodge Wastewater Treatment Federal contract opportunity
Solicitation number
12569R18B0003
Issued by
Department of Agriculture Forest Service R9-Eastern Region

About this file

Pre-bid meeting notes

View the file

Other files for this federal contract opportunity

Other files attached to Forest Lodge Wastewater Treatment, newest first.
File Type Posted
Forest_Lodge_100__ww_design_amended_7-17-2018_CAD_RJS_4-6-2018.pdf PDF
Amenment_002_Questions.pdf PDF
SF_30_Amend_002.pdf PDF
Forest_Lodge_ww_Section_B-RJS_4-6-2018_REVISED_7-16-2018.doc.pdf PDF
SF_30_Amend_001.pdf PDF
Signed_Drawings.pdf PDF
Wage_Determination.pdf PDF
Specifications.pdf PDF
Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-bid Site Visit Notes

12569R18B0003

Forest Lodge Wastewater Treatment Facility

Attendees:

Karie Linn, CO Forest Service 715-362-1321 klinn@fs.fed.us Kate Roskosky, Inspector

Forest Service 715-367-1355

Michelle Bernard, COR Forest Service 715-401-0653 Greg Howard Howard Bros.

Construction 715-356-3670 ext. 6 greg@howardbrosinc.net

Questions:

Are there any soil borings for the property?

The only soil borings for the property were done for the boathouse. Directional boring was completed for a new well last year, with no problems.

How deep is the crawl space in the cow palace?

It varies, but approximately 3-4 ft.

When connecting the newer sewer lines at the cow palace, is it possible to only go through the utility room and have the junction inside the cow palace?

No. Combining would include having to go under interior walls and would connect the main sewer from the bathroom with a little used condensation line drain

Where do the floor drains in the guesthouse basement go to, and what will be done with them if they drain into the septic tank that is being abandoned?

Floor drains appear to go into the ground. Drains not being used for a condensation line will be filled with grout. The remaining drain will be cut out with a sump pump installed to pump water int the new sewer line.

Where do the down spouts on the guesthouse drain to?

There are clay tiles feeding the water gardens on the backside of the guesthouse.

There will be a future amendment to address changes in locations to septic tank and pull through junction box at the cow palace. This amendment is anticipated on or about July 12th