About this file

This document is a Statement of Work (SOW) for the procurement of a dry pump compatible with an Exploris 480 mass spectrometer for the USDA-ARS Cereal Disease Laboratory in St. Paul, Minnesota. The key requirements include maximum dimensions, single phase power, air cooling, quiet operation, ability to handle chambers up to 100 liters, and maintenance-free extended operation. The associated federal contract opportunity is a Request for Quote (RFQ) solicitation, number 12505B24Q0163, issued by the USDA Agricultural Research Service. This is a Total Small Business set-aside with a NAICS code of 333914, Measuring, Dispensing, and Other Pumping Equipment Manufacturing. Quotes are due by 5:00 PM Eastern on May 10, 2024, and the period of performance is 90 days after award. The basis for award is Lowest Price Technically Acceptable, and the Government anticipates awarding a Firm Fixed Price contract.

View the file

Other files for this federal contract opportunity

Other files attached to Dry Pump for Exploris 480, newest first.
File Type Posted
Full and Open Provisions and Clauses.pdf PDF
Questions and Answers.pdf PDF
Provisions and Clauses.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) Project: Dry Pump for Exploris 480

GENERAL INFORMATION

1.0 Scope of Work: The USDA-ARS St. Paul, Minnesota location Cereal Disease

Laboratory is requesting a dry pump compatible with an Exploris 480 mass spectrometer.

2.0 Background: The St. Paul USDA-ARS Cereal Disease Laboratory conducts research on diseases of small-grain cereal crops, including rusts and Fusarium Head Blight.

The research unit has acquired an liquid chromatography-mass spectrometry system to study these diseases. Due to temperature issues with the existing vacuum pumps on the Exploris 480 LC-MS system, a dry pump is needed to keep temperatures in the laboratory space within operating specifications.

CONTRACTOR REQUIREMENTS

3.0 Technical Requirements/Tasks: Required specifications for the dry pump:

• Maximum dimensions not to exceed: Height: 14”; Width: 12.5”; Length: 26”.

• Single phase, air cooled and quiet

• Can be used on chambers up to 100 litres, at continuous inlet pressures up to

15 mbar with occasional pump down

• Manual, remote contact closure and RS485 serial communication

• Maintenance free for extended operation

• Built-in exhaust valve for anti-suck-back protection

• Pumping speed: 110 m3h-1

• Ultimate vacuum (total pressure): <2 x 10-2 mbar

• Inlet flange: NW40

• Outlet flange: NW40 / NW50

• Maximum permitted outlet pressure: 0.5 bar gauge / 7.0 psig

• Operating temperature range: 10 – 40 °C

• Nominal rotational speed: 9000 rpm

• Power connector 1-ph: IEC EN60320 C19

• Mains voltage: 200 – 240 V

• Power at typical application condition (2 - 10 mbar): 0.7 - 0.9 kW

• Flow at typical application condition: 3-15 slm

• Leak tightness: 1.0 x 10-5 mbar ls-1

• Noise: 56.7 dB

• Vibration at inlet flange: <2.5 mms-1 (rms)

• Must be installed and configured for an Exploris 480 mass spectrometer by a certified Thermo Scientific Field Service Engineer

4.0 Government Furnished: Not applicable.

5.0 Deliverables / Schedule: Equipment should be delivered to: USDA-ARS Cereal

Disease Laboratory, 1551 Lindig St., St. Paul, MN 55108; Delivery: 30-90 days after receipt of order.

6.0 Travel: Not applicable.

7.0 Contractor’s Key Personnel: Not applicable.

8.0 Security Requirements: Not applicable.

9.0 Data Rights: Not applicable.

10.0 Section 508 – Electronic and Information Technology Standards: Not applicable.

CONTRACTOR REQUIREMENTS
3.0 Technical Requirements/Tasks: Required specifications for the dry pump: