Questions and Answers.pdf

PDF 152 KB Posted

Attached to
Manure Storage Tank Federal contract opportunity
Solicitation number
12505B23Q0191
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Midwest Area

About this file

This document contains questions and answers regarding a federal solicitation for a manure storage tank project. The project involves removing an existing concrete pad and plastic tank, and installing a new uninsulated 2-inch PVC Schedule 40 plumbing system that can be suspended from inside the facility and routed outside through a contractor-created penetration in the steel building. The electrical disconnect box on site may still be live, so contractors must verify the power status prior to demolition. The solicitation number is 12505B23Q0191 and is being conducted by the Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Midwest Area.

View the file

Other files for this federal contract opportunity

Other files attached to Manure Storage Tank, newest first.
File Type Posted
SF30 12505B23Q0191 Amendment 0001.pdf PDF
Statement of Work.pdf PDF
Past Performance Questionnaire.pdf PDF
Wage Determination.pdf PDF
1442 12505B23Q0191.pdf PDF
ARS-371.pdf PDF
ARS-372.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ANSWERS BELOW IN BLUE

1) Please confirm this is an open top tank. It is not an open top tank. See SOW paragraph 16.

2) Please confirm the exis�ng concrete pad is to be removed. The existing concrete is to be removed. See SOW paragraph 13, and page 9.

3) Is the exis�ng electrical disconnect on a completely dead circuit or is there power running to this box? It was indicated to me by the Location that the existing disconnect may have power, currently. The contractor is responsible for their own safety so it would be prudent for the contractor to field verify prior to demolition. See paragraph 11. The conductors would need to be removed back to the nearest junction box or panel.

4) Will the USDA keep the exis�ng white plas�c tank or will contractor dispose of it? The Contractor will remove the plastic tank.

5) Please confirm the new plumbing will be 2” uninsulated PVC Schedule 40 that can be suspended from inside the facility and routed outside through a contractor created penetra�on in the steel building? Yes, the intent is to match the existing piping inside the building. If insulation is required by code at the exterior then it must be provided.