AMEND_0001_06022022_FINAL.pdf
PDF 315 KB Posted
- Attached to
- El Yunque National Forest Trails Federal contract opportunity
- Solicitation number
- 12441922R0002
- Issued by
- Department of Agriculture Forest Service
About this file
This document outlines a proposed federal solicitation for trail maintenance services on the El Yunque National Forest in Puerto Rico. The solicitation will include work on several trail heads to consist of applicable engineering services, construction surveying and staking, erosion control measures, clearing and grubbing, excavation, geotextile placement, concrete work, fill and cut slope designs and repairs, trail resurfacing, installing rock culverts, removal and demolition as specified in drawings, riprap armoring, and hauling off of excessive excavation and accumulated sediment materials. The contract value is estimated between $1 million to $5 million and performance must be completed by May 31, 2023, with an estimated start date of July 18, 2022. The opportunity is set aside for small businesses with average annual receipts of $39.5 million or less. The solicitation will require payment and performance bonds within 15 days of award and will be posted on sam.gov on or around May 16, 2022. A site visit will also be held.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_12441922R0002_Amd_0002.pdf | ||
| 1_Schedule of Items -- Trail ERFO Repairs.xlsx | XLSX spreadsheet | |
| 12441922R0002_FINAL_05272022.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
�����������������������#���"�$��%&'()*+�,%�-,)*�&./0,1(+23+4+05�5,��+�*+.+'6+2�&5�57+�8(&.+�2+9'30&5+2�%,*�57+�*+.+'85�,%�,%%+*9�8*',*�5,�57+�7,)*�&02�2&5+�98+.'%'+2�4&-�*+9)(5�'0�*+:+.5',0�,%�-,)*�,%%+*$��'�����;�"�#����������������������#�����"�����
��� =>?@ABCDEB�FG����H�I���������ABFJKJBFJBGJ�>LJ�?=�M?I��NO?KEG�J>?DP?F>�QE
J?D�?J
LAGJ �HR�SR�������� ���
TUV�WXYZ�YW[\�]̂ _̀�abb_Y[Z�W]�\]cYdYeaWY]̂ �]d�e]̂ WfaeWZg]fc[fZV��YW�\]cYdY[Z�WX[�e]̂ WfaeWg]fc[f�̂]V�aZ�c[ZefYh[c�Ŷ�YW[\�TiVjk$�&..,)05'03�&02�&88*,8*'&5',0�2&5&�lmn�opqrsoptu ���������������$�����������<�'�����v�����jw<�����"��#"���!,���"���#���� ���������"�����������<����������������� ����!��������x�������� ��� ����!5������;���#���"����� � ����������������������������"������'����jy$��5�����#"������������� ��������,���"�TTV�WXYZ�YW[\�]̂ _̀�abb_Y[Z�W]�a\[̂ c\[̂ WZ�]d�Z]_YeYWaWY]̂ Z%&.'('5-�.,2+�.,2+� jz�$�2&5+2�l{||�m}|~���ujz&$�4,2'%'.&5',0�,%�.,05*&.5�,*2+*�0,$��$�2&5+2�l{||�m}|~���u�&$�&4+024+05�,%�9,('.'5&5',0�0,$
.,2+� v$�0&4+�&02�&22*+99�,%�.,05*&.5,*�l�������opp�����r�����{���p���t��m����tpu
�$�&24'0'95+*+2��-�lmn����po������m�p���u.,2+��$�'99)+2��- 8&3+���,%��8&3+9y$�*+�)'9'5',0�8)*.7&9+�*+�$�0,$�$�+%%+.5'6+�2&5+k$�&4+024+05�4,2'%'.&5',0��0,$� w$�8*,:+.5�0,$�lmn�����s����puj$��.,05*&.5�'2�.,2+a\[̂ c\[̂ W�]d�Z]_YeYWaWY]̂ g\]cYdYeaWY]̂ �]d�e]̂ WfaeW
�HR�SR����
.7+./�,0+ &$�57'9�.7&03+�,*2+*�'9�'99)+2�8)*9)&05�5,x�l{�p�sn���r���os��u��57+�.7&03+9�9+5�%,*57�'0�'5+4�jy�&*+�4&2+�'0�57+�.,05*&.5�$�57+�&�,6+�0)4�+*+2�.,05*&.5�,*2+*�'9�4,2'%'+2�5,�*+%(+.5�57+�&24'0'95*&5'6+�.7&03+9�l�r�����������p��s�����s����nns�p��.$�57'9�9)88(+4+05&(�&3*++4+05�'9�+05+*+2�'05,�8)*9)&05�5,�&)57,*'5-�,%x2$�,57+*�l{�p�sn�����p��n���tsns���s�����t��r���os��u����o��os��s���t�����p���u��9+5�%,*57�'0�'5+4�jy<�8)*9)&05�5,�57+�&)57,*'5-�,%�%&*�y�$jz����$ [V�Y\b]fWâ W� .���"� �$�,*2+*�0,$�'0�'5+4�jz&$ jy$�2+9.*'85',0�,%�&4+024+05�4,2'%'.&5',0�l�o���s�pt������ ��p��s����p�ts�����s���rts������s�s���s��¡����o�����r�¢p�������po�£�pop�np��s��p��D¤¥�¦§̈¦©ª¥�©«�¬¤ª�®̄¥°±̄¥°¬�ª�¬©�̄®²¥�¬¤¥�«©³³©́°µ�¶¤®°µ¥ªR¶©̈ ¥̈¶¬©°ª�·?JJ�>DD>G@JF̧¹>º�G©̈ ¥̈¶¬�¬¤¥�±®¬¥�«©̈�¬¤¥�ª¬¥�»ª¬�°�¼³©¶²����©«�¬¤¥������«̈ ©̄�½§³¾�S¿������¬©�½PBJ�S¿�����®ª�ª¬®¬¥±�°�ª¥¶¬©°�À�©«�¬¤¥�ª©³¶¬®¬©°º¼º�G©̈ ¥̈¶¬�¬¤¥�¦¥̈©±�©«�¦¥̈«©̈ ®̄°¶¥º�?¥¥�®¬¬®¶¤¥±ºGº�K̈©»±¥�?¶¤¥±§³¥�©«�A¬¥̄ª�®ª�®°�®¬¬®¶¤̄¥°¬�¬©�¬¤¥�ª©³¶¬®¬©°º�?¥¥�®¬¬®¶¤¥±ºFº�K̈©»±¥�ÁÂ>º�?¥¥�®¬¬®¶¤¥±ºG©°¬°§¥±�ººº j�&$�0&4+��&02�5'5(+�,%�.,05*&.5'03�,%%'.+*�l}��p��o��os��ujw&$�0&4+�&02�5'5(+�,%�9'30+*�l}��p��o��os��u jw.$�2&5+�9'30+2 j��$�)0'5+2�95&5+9�,%�&4+*'.&�jw�$�.,05*&.5,*�,%%+*,* j�.$�2&5+�9'30+2l{s����rop��n��po�����r���os�pt�����s��u l{s����rop��n�����o���s����nns�pouM>
Ã�½º�MAÀÀJ
95&02&*2�%,*4��z��*+6$�jj�kzj��8"�� "��������39&�%&*��yv�.%*��w�$ky�8"�;��#����������#�#��� � ������'�����&��"�jz&<������"�����"��
� ��"� ��#$% #&% #'% #(% #)% #*%+�,,+-��.///�0///+
� ��1234546562758491 ��������������::9�;3589< =>?@>ABC�DE�" �����;38����<�2:�664
Solicitation: 12441922R0002 Date: 2 June 2022
AMENDMENT 0001
CHANGES/CLARIFICATIONS:
1. The date for the site visit in Block 10 of the 1442 is hereby changed from July 7, 2022 to JUNE 7, 2022 as stated in section L of the solicitation.
2. The period of performance for the design portion of the requirement is 232 days after receipt of the notice to proceed. The construction portion of the requirement is 180 days after government provided acceptance of the 100% design and receipt of Section 106 approval.
3. Provide Schedule of Items as an attachment to the solicitation. See attached.
QUESTIONS & ANSWERS (Q&A)
1. QUESTION: To clarify, in the bids documents of the reference project, it indicates that a site visit will be held on July 7, 2022. And the date to present the proposal is June 28, 2022 at 1300 local time. Please indicate the correct dates.
RESPONSE: The correct date and time for the site visit is June 7, 2022 at 09:30AM local time as stated in section L of the solicitation.
(END OF AMENDMENT 0001)
Item No. Pay Unit Unit Price Unit Total
15101 Lump Sum $ - $
Item No. Pay Unit Unit Price Unit Total
25702(1) Foot $ - $
30104(1) Ton $ - $
60306(1) Foot $ - $
64801(1) Cubic Yard $ - $
15713(1) Lump Sum $ - $
20302(1) Each $ - $
20701(1) Square Yard $ - $
25105(1) Ton $ - $
25702(2) Lump Sum $ - $
30104(2) Ton $ - $
62506(1) Square Yard $ - $
62606(1) Square Yard $ - $
Solicitation No: 12441922R0002
SCHEDULE OF ITEMS
Description Estimated Quantity
ANGELITO TRAIL ERFO REPAIR
Mobilization / Demobilization 1
MOBILIZATION
(1) ANGELITO TRAIL ERFO REPAIR
(2) MT. BRITTON TRAIL ERFO REPAIR
(3) CAIMITILLO TRAIL ERFO REPAIR
(4) CAIMITILLO SPUR ERFO REPAIR
(5) EL YUNQUE TRAIL ERFO REPAIR
(6) BANO DE ORO TRAIL ERFO REPAIR
SUB-TOTAL PRICE
Description Estimated Quantity
SUB-TOTAL PRICE
Aggregate base, grading A (FP-14 Table 703-2) compaction method FP-14 Section 204.11(a)(1)
Placed Streambed simulation rock, bed class submittal required, method machine place 6
ANGELITO TRAIL ERFO REPAIR -- OPTIONAL PAY ITEM(S)
Plantings, cohitre (Commelina diffusa) and wedelia (Sphagneticola trilobata) [Refer to FSSS Section 626 for Planting Requirements] 1467
Earthwork geosynthetics, type Class I, nonwoven, Type A 130
Aggregate base, grading 6" surge stone compaction method FP-14 Section 204.11(a)(1) 23
Contractor designed, 60 inch span x 72 inch rise, precast or reinforced cast-in-place concrete three (3) sided box culvert with Footings and Reinforced Concrete Wingwalls w/ weep holes (All Sides) 12
Contractor construction, 60 inch span x 72 inch rise, precast or reinforced cast-in-place concrete three (3) sided box culvert with Footings and Reinforced Concrete Wingwalls w/ weep holes (All Sides) and all Dewatering
OPTIONAL PAY ITEM SUB-TOTAL PRICE
Removal of 36" dia x 4' Length Round Concrete Culvert, disposal method, Legally off National Forest 1
Soil Erosion & Pollution Control 1
Keyed riprap, class 5 50
Contractor designed, 41' (plus or minus 4') span x 66" wide, precast and/or concrete reinforced trail bridge 1
Mulching, Dry method (Dry mulching shall be sterile. Contractor shall use in all areas of disturbance)
15713(2) Lump Sum $ - $
20307(1) Square Feet $ - $
20307(2) Square Feet $ - $
25702(3) Lump Sum $ - $
30104(3) Ton $ - $
60101(1) Cubic Yard $ - $
60306(2) Lump Sum $ - $
25702(5) Lump Sum $ - $
60306(4) Lump Sum $ - $
60413(1) Lump Sum $ - $
62506(2) Square Yard $ - $
62606(2) Square Yard $ - $
Contractor designed, Trail Section, Trail Stabilization at Dam, and Stairway Repair/Reconstruction 1
Contractor construction, Trail Section, Trail Stabilization at Dam, and Stairway Repair/Reconstruction 1
SUB-TOTAL PRICE
Removal of 608' length x 3' wide existing asphalt trail section, disposal method, Legally off National Forest 1824
MT. BRITTON TRAIL ERFO REPAIR
Description
Soil Erosion & Pollution Control 1
Estimated Quantity
OPTIONAL PAY ITEM SUB-TOTAL PRICE
MT. BRITTON TRAIL ERFO REPAIR -- OPTIONAL PAY ITEM(S)
Mulching, Dry method (Dry mulching shall be sterile. Contractor shall use in all areas of disturbance) 2787
Plantings, cohitre (Commelina diffusa) and wedelia (Sphagneticola trilobata) [Refer to FSSS Section 626 for Planting Requirements] 2787
Aggregate base, grading C (FP-14 Table 703-2) compaction method FP-14 Section 204.11(a)(1)
27Concrete, 4" depth concrete with 1/2" Min. to 3" Max. Angular Stone Embeded Brushed Surface Finished Trail Surface (concrete color shall match existing)
Contractor construction, 41-ft long x 7' (plus/minus 1') depth gabion wall fill slope repair 1
Remove and reset, historic rocks/stones along asphalt trail that shall be removed
Contractor designed, 41-ft long x 7' (plus/minus 1') depth gabion wall fill slope repair 1
Removal of 41' length x 2' wide existing concrete trail section, disposal method, Legally off National Forest
15713(3) Lump Sum $ - $
20307(3) Square Feet $ - $
30104(4) Ton $ - $
60101(2) Cubic Yard $ - $
20302(3) Each $ - $
20307(4) Square Feet $ - $
25702(6) Lump Sum -$ $
60306(5) Lump Sum $ - $
60413(2) Lump Sum $ - $
62506(3) Square Yard $ - $
62606(3) Square Yard $ - $
CAIMITILLO TRAIL ERFO REPAIR
Description Estimated Quantity
Soil Erosion & Pollution Control 1
SUB-TOTAL PRICE
Aggregate base, grading C (FP-14 Table 703-2) compaction method FP-14 Section 204.11(a)(1) 205
Concrete, 4" depth concrete with 1/2" Min. to 3" Max. Angular Stone Embeded Brushed Surface Finished Trail Surface (concrete color shall match existing) 26
Removal of 637' length x 3' wide existing asphalt trail section, disposal method, Legally off National Forest 1911
CAIMITILLO TRAIL ERFO REPAIR -- OPTIONAL PAY ITEM(S)
Mulching, Dry method (Dry mulching shall be sterile. Contractor shall use in all areas of disturbance) 1509
Plantings, cohitre (Commelina diffusa) and wedelia (Sphagneticola trilobata) [Refer to FSSS Section 626 for Planting Requirements] 1509
OPTIONAL PAY ITEM SUB-TOTAL PRICE
Removal of 1,060' length x 3' wide existing asphalt trail section, disposal method, Legally off National Forest 3180
Remove and reset, rocks/stones along asphalt trail that shall be removed 1
Contractor designed, 7 Individual concrete rock culvert w/ top 1
Contractor construction, 7 Individual concrete rock culvert w/ top 1
Removal of 12" dia. x 5' Length Culverts, disposal method, Legally off National Forest 7
15713(4) Lump Sum $ - $
20302(4) Each $ - $
25702(7) Lump Sum $ - $
60201(1) Foot $ - $
60306(6) Lump Sum $ - $
62506(4) Square Yard $ - $
62606(4) Square Yard $ - $
$ OPTIONAL PAY ITEM SUB-TOTAL PRICE
Soil Erosion & Pollution Control 1
Removal of 12" dia. x 5' Length Concrete Culvert, disposal method, Legally off National Forest 1
CAIMITILLO SPUR ERFO REPAIR
Description Estimated Quantity
Contractor designed, 121-ft long x 10' (plus/minus 1') depth gabion wall fill slope repair (Gabion Basket Designed to Grow Vegetation) 1
12 inch dia. pipe culvert, concrete w/ Class 2 riprap energy dissipator 24
SUB-TOTAL PRICE
Contractor construction, 121-ft long x 10' (plus/minus 1') depth gabion wall fill slope repair (Gabion Basket Designed to Grow Vegetation) 1
CAIMITILLO SPUR ERFO REPAIR -- OPTIONAL PAY ITEM(S)
Mulching, Dry method (Dry mulching shall be sterile. Contractor shall use in all areas of disturbance) 900
Plantings, cohitre (Commelina diffusa) and wedelia (Sphagneticola trilobata) [Refer to FSSS Section 626 for Planting Requirements] 900
15713(5) Lump Sum $ - $
20104(1) Square Feet $ - $
20301(2) Lump Sum -$ $
25702(8) Lump Sum -$ $
25702(9) Lump Sum -$ $
25702(10) Lump Sum -$ $
25702(12) Lump Sum -$ $
25702(13) Lump Sum -$ $
60306(7) Lump Sum -$ $
60306(8) Lump Sum -$ $
60306(9) Lump Sum -$ $
60306(11) Lump Sum -$ $
60306(12) Lump Sum -$ $
20307(5) Square Feet -$ $
20701(2) Square Yard $ - $
25702(11) Lump Sum -$ $
30104(5) Ton -$ $
30104(6) Ton -$ $
60306(10) Lump Sum -$ $
62506(5) Square Yard $ - $
62606(5) Square Yard $ - $
Contractor designed, 13-ft long x 9' (plus/minus 1') depth gabion wall fill slope repair (Gabion Basket Designed to Grow Vegetation) 1
Contractor designed, 40-ft long x 36" to 48" wide trail switchback failure redesign w/ landing and smooth transition 1
Contractor designed, 40-ft long x 18' (plus/minus 1') depth gabion wall fill slope repair (Gabion Basket Designed to Grow Vegetation) 1
Contractor construction, 40-ft long x 36' depth gabion wall cut slope repair (Gabion Basket Designed to Grow Vegetation) or Wire Face / Block/ and/or Panel MSE Wall, Soil Nailing or equal
Contractor designed, 40-ft long x 36' depth gabion wall cut slope repair (Gabion Basket Designed to Grow Vegetation) or Wire Face / Block/ and/or Panel MSE Wall, Soil Nailing or equal 1
Contractor designed, 16-ft long x 9' (plus/minus 1') depth gabion wall fill slope repair (Gabion Basket Designed to Grow Vegetation) 1
Contractor construction, 16-ft long x 9' (plus/minus 1') depth gabion wall fill slope repair (Gabion Basket Designed to Grow Vegetation)
Soil Erosion & Pollution Control 1
Removal of 40-ft long x 36" to 48" wide trail switchback failure and failure material, disposal method Legally off National Forest 1
Description Estimated Quantity
Clearing and grubbing, disposal method, Legally off Government Lands 264
EL YUNQUE TRAIL ERFO REPAIR
Contractor construction, 13-ft long x 9' (plus/minus 1') depth gabion wall fill slope repair (Gabion Basket Designed to Grow Vegetation) 1
Contractor construction, 40-ft long x 36" to 48" wide trail switchback failure redesign w/ landing and smooth transition 1
Contractor construction, 40-ft long x 18' (plus/minus 1') depth gabion wall fill slope repair (Gabion Basket Designed to Grow Vegetation) 1
SUB-TOTAL PRICE
Earthwork geosynthetics, type Class I, nonwoven, Type A 615
Plantings, cohitre (Commelina diffusa) and wedelia (Sphagneticola trilobata) [Refer to FSSS Section 626 for Planting Requirements] 12933
OPTIONAL PAY ITEM SUB-TOTAL PRICE
EL YUNQUE TRAIL ERFO REPAIR -- OPTIONAL PAY ITEM(S)
Mulching, Dry method (Dry mulching shall be sterile. Contractor shall use in all areas of disturbance) 12933
Removal of 1030' length x 3' wide existing asphalt trail section, disposal method, Legally off National Forest 3090
Aggregate base, grading A (FP-14 Table 703-2) compaction method FP-14 Section 204.11(a)(1) 257
Aggregate base, grading AASHTO #57 Stone (no fines) compaction method FP-14 Section 204.11(a)(1) 247
Contractor designed, 45-ft trail horizontal alignment x 36" wide trail width w/ proposed 18" depth rock culvert and removing existing trail segment at location 1
Contractor construction, 45-ft trail horizontal alignment x 36" wide trail width w/ proposed 18" depth rock culvert and removing existing trail segment at location 1
15713(6) Lump Sum $ - $
25702(15) Lump Sum $ - $
60306(14) Lump Sum -$ $
25702(14) Lump Sum -$ $
30104(7) Ton -$ $
60306(13) Lump Sum -$ $
62506(6) Square Yard $ - $
62606(6) Square Yard $ - $
-$ GRAND TOTAL
Soil Erosion & Pollution Control 1
OPTIONAL PAY ITEM SUB-TOTAL PRICE
Contractor designed, 56-ft long x 11' (plus/minus 1') depth gabion wall fill slope repair (Gabion Basket Designed to Grow Vegetation) 1
Aggregate base, grading A (FP-14 Table 703-2) compaction method FP-14 Section 204.11(a)(1) 25
Contractor construction, 56-ft long x 11' (plus/minus 1') depth gabion wall fill slope repair (Gabion Basket Designed to Grow Vegetation) 1
SUB-TOTAL PRICE
Contractor construction, 37' (plus or minus 3') span x 60" wide, reinforced concrete low water crossing trail bridge 1
BANO DE ORO TRAIL ERFO REPAIR
Description Estimated Quantity
Contractor designed, 37' (plus or minus 3') span x 60" wide, reinforced concrete low water crossing trail bridge 1
BANO DE ORO TRAIL ERFO REPAIR -- OPTIONAL PAY ITEM(S)
Mulching, Dry method (Dry mulching shall be sterile. Contractor shall use in all areas of disturbance) 1340
Plantings, cohitre (Commelina diffusa) and wedelia (Sphagneticola trilobata) [Refer to FSSS Section 626 for Planting Requirements] 1340
| ADPCDA8.tmp |
| Schedule of Items |
File details come from the government source that posted it. Updated .