Sol_1240LT22R0031_Amd_0006.pdf

PDF 214 KB Posted

Attached to
Antelope Flat Campground Waterline Replacement Federal contract opportunity
Solicitation number
1240LT22R0031
Issued by
Department of Agriculture Forest Service

View the file

Other files for this federal contract opportunity

Other files attached to Antelope Flat Campground Waterline Replacement, newest first.
File Type Posted
Sol_1240LT22R0031_Amd_0005.pdf PDF
Sol_1240LT22R0031_Amd_0004.pdf PDF
Amd_03_1240LT22R0031_AntelopeFlatCampground.pdf PDF
Sol_1240LT22R0031_Amd_0002.pdf PDF
Sol_1240LT22R0031_Amd_0001.pdf PDF
Attachment 1 - Special Project Specifications.pdf PDF
RFP 1240LT22R0031 Antelope Flat Campground.pdf PDF
Attachment 2 - Maps and Drawings.pdf PDF
Attachment 3 - Wage Determination Uintah County Utah.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1240LT22R0031

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

40LT

IDAHO FALLS ID 83401

1405 HOLLIPARK DRIVE

USDA-FS CSA INTERMOUNTAIN 8

40LT

IDAHO FALLS ID 83401

1405 HOLLIPARK DRIVE

ATTN KELLIE SHAW

USDA-FS CSA INTERMOUNTAIN 8

GAOA04/05/20220006

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

04/01/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to post a revised B-1 Schedule of Items (SOI). Offerors are required to submit their pricing on the revised SOI

The due date and time for receipt of proposals HAS BEEN EXTENDED. All proposals in response to the solicitation shall be emailed to kellie.shaw@usda.gov no later than 1300 MST, Monday, May 9, 2022. Proposals received after the stated due date and time will not be considered.

PLEASE SEE CONTINUATION SHEET FOR AMENDMENT DETAILS

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

KELLIE SHAW

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

This solicitation and any resulting contract is a firm-fixed price type of contract, which under the definition in FAR 16.202-1, “this type of contract provides for a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract. This contract type places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss.”

Prices on the Schedule shall reflect Contractor’s full cost for labor, supervision, overhead costs, and incidental items.

B-1 SCHEDULE OF ITEMS

ITEM # DESCRIPTION METHOD

OF MEAS

UNIT QTY PRICE TOTAL

011900 Mobilization LSQ LS 1 $ $ 221100-1 Water pipeline 3-inch HDPE, 160 psi with heat fusion joints, including Trench pipe zone and bedding

DQ LF 5500 $ $

221102-1 3-inch Metal Ball Isolation Valve installed in Existing Concrete Boxes

AQ EA 4 $ $

221102-1 2-inch Metal Drain Gate Valve and Box and drain line

AQ EA 1 $ $

221102-3 3-inch Metal Gate Valve and Box AQ EA 1 $ $ 221103 2-inch Air Release Metal Valve and Vent

Pipe

AQ EA 4 $ $

TOTAL PROPOSAL PRICE: $

B-2 SCHEDULE NOTES

a) Payment for Bond Premiums Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.

b) Basis for Payment Payment will be made on actual work performed as described in FP-14 109.01 unless otherwise noted.

B-1 Schedule of Items Revision.pdf
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B-1 SCHEDULE OF ITEMS
B-2 SCHEDULE NOTES