1240LT22R0002 Questions and Answers.docx

DOCX document 14 KB Posted

Attached to
Nebraska Roadbed Reconditioning -Pine Ridge Ranger District
Solicitation number
1240LT22R0002-0001
Issued by

View the file

Other files

File Type Posted
1240LT22R0002 Amendment 0001.pdf PDF
Pre-Bid Sign in sheet NEB road repairs 032122.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GAOA NEBRASKA ROADBED RECONDITIONING

QUESTIONS AND ANSWERS

1. Q: What is the fluff 31%?

A: 31% fluff factor requirement is being removed from the contract.

2. Q: Is a Bid Bond Required?

A: If you are sending in a quote over $150,000 a 20% bid bond will be required.

3. Q: Is there a pre-bid meeting?

A: Yes, there will be a pre-bid as listed in the solicitation.

4. Q: Does the woven geotextile need to be laid in the roadway or in the roadway and the ditches?

A: The requirement calls for woven geotextile to be laid on the roadway surface only.

5. Q: Does this requirement include dam repairs or just the roadbed recondition leading to the dams?

A: This requirement is for roadbed reconditioning leading to the dam only.

6. Q: What is the required compacted cubic yard or depth of aggregate?

A: We want 4” compacted aggregate. You will need to do your own calculations to determine what is needed to get to a 4” compacted aggregate as required in the Statement of Work (SOW).