GAOA NEBRASKA ROADBED RECONDITIONING
QUESTIONS AND ANSWERS
1. Q: What is the fluff 31%?
A: 31% fluff factor requirement is being removed from the contract.
2. Q: Is a Bid Bond Required?
A: If you are sending in a quote over $150,000 a 20% bid bond will be required.
3. Q: Is there a pre-bid meeting?
A: Yes, there will be a pre-bid as listed in the solicitation.
4. Q: Does the woven geotextile need to be laid in the roadway or in the roadway and the ditches?
A: The requirement calls for woven geotextile to be laid on the roadway surface only.
5. Q: Does this requirement include dam repairs or just the roadbed recondition leading to the dams?
A: This requirement is for roadbed reconditioning leading to the dam only.
6. Q: What is the required compacted cubic yard or depth of aggregate?
A: We want 4” compacted aggregate. You will need to do your own calculations to determine what is needed to get to a 4” compacted aggregate as required in the Statement of Work (SOW).