The contractor shall provide all professional services necessary to monitor the existing and future critical lab equipment in the 10-story Richard B. Russell Building via the Siemens Desigo CC LEM server. The project consists of installing a new PXCM controller, MSTP communication riser, and TXM1.8x modules to provide 275 points for monitoring or control. The contractor must provide BAS design drawings, Desigo CC licensing for 300 points, 25 sets of address keys, and as-built drawings. The project must be completed within 45 days of the notice to proceed. Certified Siemens equipment and parts are required, and the contractor is encouraged to conduct a site visit prior to submitting a quote. Quotations are due by July 19, 2024, and the contract will be awarded based on a best value tradeoff analysis considering technical acceptance, price, and past performance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work USDA, Agricultural Research Service
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
USDA B1 LEM Monitoring Project
USNPRC SEPRL
934 College Station Road Athens GA, 30605
Prepared by:
Melissa Scott
| Version 2.8, Page - |
| Page 10 of 10 |
Scope of Work The contractor shall provide all professional services necessary to provide monitoring for the existing and future critical lab equipment in the 10 story Richard B Russell Building via the Siemens Desigo CC LEM server. The equipment is located at 950 College Station Road Athens, GA 30605. The contractor shall provide a detailed proposal with a cost breakdown for the project.
The contractor shall include all services and field labor, equipment, materials, testing and personal protective equipment necessary to perform the work. No Government equipment will be available for use by the contractor.
Base Bid The contractor shall provide a detailed proposal and cost breakdown for the entire project as specified in this statement of work. Certified Siemens equipment and parts are required for this project.
Site Visit Contractors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing firsthand any conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.
Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid. Registration can be completed at www.sam.gov/portal/public/SAM
Codes and Standards Applicable Codes and Standards apply and are not limited to the following
| ANSI - | American National Standards Institute. |
| ASME - | American Society of Mechanical Engineers. |
| NEC - | National Electrical Code, NFPA 72. |
| OSHA - | Occupational Safety and Health Administration |
| ADA – | Americans with Disabilities Act |
All work must meet ARS 242.1M “ARS Facilities Design Standards” for the defined scope of this project in addition to meeting all Local, State and Federal codes, and latest International Building Code (IBC).
Project Summary The project consists of the following elements:
Installation of critical lab equipment monitoring at B1.
1. Installation of a new PXCM controller in a new enclosure with hinged door in the IT closet on the South and East corridors of the 2nd floor. A small 600VA UPS will be provided to bridge short power interruptions (5 to 10 minutes).
2. Installation of a MSTP communication riser and 24VAC power trunk to the remaining floors (9 floors on the East Wing and 4 floors on the South Wing)
3. Install (2) TXM1.8x modules within new enclosures in the IT closets of each of the floor. This will provide (275) points for monitoring or control points.
4. Contractor shall provide the following in support of this work:
a. BAS design drawings
b. Desigo CC licensing for 300 points
c. (25) sets of 24-count address keys for current and future monitoring modules.
d. As-built drawings
The facility will be occupied during construction activities. All work shall be scheduled in advance and coordinated with the facility representative to minimize the disruption to daily operations and research programs.
Utilization of Bio-Based Products
The contractor shall utilize products and material based from bio- based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use of detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to the applicable Federal Specifications and Standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at: www.biopreferred.gov
Safety The contractor will submit a Site Safety Specific Plan (SSSP)/Accident Prevention Plan in industry recognizable format to the Contracting Officer within 14 days of contract award. The Government shall review the SSSP prior to the start any construction activities.
Safety and health matters, as they relate to the work, are the exclusive responsibility of the contractor. The contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions that may be required by law or local authorities for the protection and security of the grounds, facilities, and personnel. Contractor shall coordinate with Lab Personnel and strictly always follow all Covid related precautions and procedures.
Contractor Requirements The contractor shall provide a complete and functional installation, including all labor, supervision, tools, materials, equipment, apparatus, transportation, rigging and other equipment and services necessary to accomplish the work in accordance with the intent and meaning of this statement of work.
The project work shall be performed per the following guidelines:
1) Contractor will verify all dimensions and existing site conditions prior to beginning work.
2) The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees.
3) Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site on a weekly basis.
4) Contractor is required to manage the project and consult with the Government prior to beginning all work phases.
5) Contractor shall perform work in a manner that minimizes the impact to daily operations of the facility and its workers. The building will be occupied during construction work.
6) Contractor will provide daily reports of work performed to the COR and weekly status updates to the TPOC.
7) Contractor must have a superintendent on the jobsite when crews are performing the installation work.
8) Contactor will provide their own restroom facility.
9) All Contractor personnel will be required to show a valid Federal or State ID to enter the property.
10) Contractor will abide by all USDA Biosecurity protocols relevant to this project.
All work is to be performed according with building codes, ordinances and laws of the Authority having jurisdiction on the project. When the requirements of the building codes, ordinances, and laws conflict with any other part of the building codes, ordinances and laws, the most restrictive requirement shall prevail. The Contractor is responsible for obtaining all permits and construction approvals necessary to successfully complete the project.
Documentation Requirements
Material Submittals The contractor shall submit for approval all documents/samples necessary to ensure requirements of project will be satisfied. Electronic submittals on all equipment and materials used on this project shall be submitted to the TPOC noted in this document.
Pre-Construction Submittals Prior to construction activities beginning the following submittals must be provided to the CO and TPOC for approval.
1. Project Schedule (including daily work start/stop time)
2. Project Design
3. Site Specific Safety Plan (SSSP) / Accident Prevention Plan
4. List of contract personnel of the general and subcontractors General Requirements
Damage to Property:
The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired to pre-damaged condition to the satisfaction of the TPOC.
Inspection and Acceptance A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 2 days in advance with the TPOC.
Period of Performance The completion of this project shall not exceed 45 days from date of notice to proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.
Work Hours:
Contractor work hours shall be Monday through Friday, 8:00 A.M. to 4:30 P.M. except on Government holidays. Any changes to work schedule shall be submitted to Contacting Officer for written approval prior to schedule change.
Guaranty The contractor shall provide and submit a single guarantee stating that all portions of the work are in accordance with Contract requirements. Guarantee all work against faulty and improper material and workmanship for a period not less than ten (10) years from date of final acceptance by the USDA, except where manufacturer guarantees or warranties are for longer terms. The contractor shall correct any deficiencies which occur during the guarantee period within 24 hours after notification.
Project Contacts
Contract Specialist (CS):
Monte Jordan
| 141 Experiment Station Rd | monte.jordan@usda.gov |
| Stoneville, MS 38776 | Phone: (662)686-5361 |
Administrative Officer (AO):
Charlotte Gilman 934 College Station Road Charlotte.Gilman@usda.gov Athens GA, 30605 Phone: 706-546-3029
Support Services Manager (COR):
Melissa A Scott
| 934 College Station Rd | Melissa.Scott@usda.gov |
| Athens GA, 30605 | Phone: 706-546-3456 |
Facilities Operation Manager (TPOC):
| Teddy Laguins | Teddy.Laguins@usda.gov |
| 934 College Station Rd | Phone: 706-546-3722 |
Athens, GA 30605 image1.jpg