SF30 AMENDMENT 0005 SOLICITATION 12405B23R0033.pdf
PDF 139 KB Posted
- Attached to
- Equipment Storage Building Federal contract opportunity
- Solicitation number
- 12405B23R0033
About this file
This amendment modifies a solicitation for the construction of an equipment storage building. The amendment provides answers to additional questions from interested contractors, clarifying that no termite treatment or vapor barrier will be required, and that the factory primed steel must be painted as noted in the scope of work to fully inhibit corrosion. The solicitation is for the construction of a 90-foot long by 30-foot wide pre-engineered steel equipment storage building in accordance with state and local building authorities. The period of performance is from September 11, 2023 to December 11, 2023. The Construction Wage Rate Requirements Statute and FAR clauses for construction services apply.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30 AMENDMENT 0004 SOLICITATION 12405B23R0033.pdf | ||
| SF30 AMENDMENT 0003 SOLICITATION 12405B23R0033.pdf | ||
| Statement of Work SOW REVISION 1 Raleigh Equipment Shed.docx | DOCX document | |
| SF30 AMENDMENT 0002 SOLICITATION 12405B23R0033.pdf | ||
| SF30 AMENDMENT 0001 SOLICITATION 12405B23R0033.pdf | ||
| Standard Form 24 Bid Bond.pdf | ||
| Past Performance Questionnaire Solicitation 12405B23R0033.docx | DOCX document | |
| Statement of Work SOW Equipment Storage Building .docx | DOCX document | |
| SF1442 SOLICITATION 12405B23R0033.pdf | ||
| Wage Grade Determination DBA NC20230035 Johnston County NC Solicitation 12405B23R0033.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12405B23R0033 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ARS-12405B
STONEVILLE MS 38776
141 EXPERIMENT STATION ROAD
USDA ARS SEA AAO ACQ/PER PROP
110532808/28/20230005
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/04/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 0005 issued to provide answers to additional questions submitted by interested contractor.
1) Can the Government provide a copy of the sign-in sheet for the site visit?
Copy of site-visit sign in sheet cannot be provided.
2) Please confirm no termiticide treatment will be required for this facility (all concrete
& steel).
Confirmed. No Termite treatment needed.
3) Please confirm if a vapor barrier is needed beneath the slab on grade.
No vapor barrier required.
4) Since the primary and secondary framing members come "factory-primed" to inhibit corrosion, please clarify/confirm if the columns, girts, and purlins must be painted as
Continued ...
15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12405B23R0033/0005 noted in the Scope of Work or if the factory primer coat will be sufficient without additional painting. Per discussions at the site visit it was our understanding the intent of the painting was to simply inhibit corrosion.
It must be painted as noted in the scope of work.
Normally factory primed steel is part of a multicoat system. We expect the complementary topcoat to be applied as part of the overall paint system chosen.
Construction of a 90' long x 30' wide pre-engineered steel equipment storage building as defined in attached Statement of Work (SOW) in accordance with State and Local building authorities.
Period of Performance: 09/11/2023 to 12/11/2023 Construction Wage Rate Requirements Statute is hereby incorporated into this contract.
FAR clauses for construction services apply to this contract.
Reference FAR clause 52.204-27. Prohibition on a ByteDance Covered Application (Jun 2023).
Information concerning the REE policies and procedures regarding the definitization of equitable adjustments for change orders under construction contracts and the time required for definitization of those actions per 15 U.S.C. 644 is available at https://www.ars.usda.gov/afm/apd/acquisitions/.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .