Updated SoW - Renovate B14 - Byron GA - EW.pdf

PDF 2 MB Posted

Attached to
Renovation of Building 14
Solicitation number
12405B22Q0235
Issued by

View the file

Other files

File Type Posted
Google Earth PIC 7.pdf PDF
Google Earth PIC 6.pdf PDF
12405B22Q0235.pdf PDF
LONGTERM STORAGE DRAWING Spray Foam FRP Placement.pdf PDF
Trench Drain.pdf PDF
Building Drawing 2.docx DOCX document
LONGTERM STORAGE Trench Drain.pdf PDF
Water Connection - Two Options.pdf PDF
Roof Dimension.pdf PDF
Vent Pipe.jpg JPG image
Electrical Box.pdf PDF
Leach Field.pdf PDF
Wage Determination.pdf PDF
SoW - Renovate B14 - Byron GA - EW (002).pdf PDF
Clauses and Provisions.docx DOCX document
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Renovate B14

Southeastern Fruit and Tree Nut Research Laboratory

21 Dunbar Rd., Byron, GA 31008

Byron, GA

Prepared by:

Everett Wilson

26JUN22

Statement of Work:

Contractor shall furnish all labor, materials, and supplies to perform the following work for U. S.

Department of Agriculture, Agricultural Research Service, Southeastern Fruit and Tree Nut Research Laboratory, 21 Dunbar Road, Byron, Georgia 31008

This will be a phased project starting with the contractor replacing the R panel roofing, then the alteration of a 60’ by 40’ open space to create a 20’ by 40’ clean room and finally pour a concrete pad. The contractor shall furnish all labor and materials for the described projects in strict conformity with safety, standards, laws, statutes and ordinances for a federal facility.

All work shall be completed in accordance with all local, state, and federal codes and regulations. All work shall also meet the requirements of the ARS Facilities and Design Standards (P&P 242.1). The P&P 242.1 document can be found at: http://www.afm.ars.usda.gov/ppweb/PDF/242‐01M.pdf.

All work shall be accomplished in a professional manner and in accordance with good workmanship and acceptable practice.

Contractor is responsible for inspecting the site and for determining the exact requirements of the project.

Contractor’s working hours shall be scheduled to coincide with the normal working hours (7am‐4pm) at the site. Should it be necessary to schedule working hours other than normal working hours, contractor shall arrange for access to the work area with the Contracting Officer’s Representative (COR) at the site at least three days prior to the need.

Project:

The proposed project is for the renovation/alteration of the open storage warehouse for the construction of a 20’ x 40’ clean room to include install of A/C unit for temperature control. The R‐Panel roof covering this building must be replaced prior to construction of the clean room (overhang not included). A 6” thick by 20’ x 30’ concrete pad is required at the south end of the building adjacent to the main sliding doors for the off‐loading of pecan nut trailers & dump carts.

1.1. Contractor to demolition and remove approximately 7,920 sq ft R‐Panel roofing and install new

26ga R‐Panel roof system

1.2. Construct a floor to ceiling wood wall. Constructed of 2x4’s (ground level 2x4’s pretreated) and

½” CDX plywood on the inside of new wall.

1.3. Install door, trim and hardware in newly constructed wall and finish painting

1.4. Install electrical circuits and receptacles at various locations. There are 4 components of the

Pecan Nut Harvesting system that will require hard wiring to 110v, 4 components require 110v receptacles and 1 component requires a 220v receptacle.

1.5. Install 3ton A/C Unit – Condenser placed outside on west side of building & north of side entry door, air handler and evaporator coils will be suspended from ceiling I‐beams.

1.6. Install plumbing from water source to clean room and install faucet in clean room.

1.7. Spray foam insulation on walls and ceiling

William.Rengstorf Highlight

1.8. Install FRP wall board 10’ high on newly constructed wood wall

1.9. Grade and install forms for concrete pad, Pour Concrete and finish

1.10. Seed and straw around slab and any trenching for plumbing

Site Visit:

Bidders are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for observing firsthand any conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.

Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid.

Registration can be obtained through: https://www.sam.gov/portal/public/SAM/

Safety: The contractor is responsible for complying with all local, state and federal safety codes and laws.

Detailed Bid: Provide all materials, labor, and equipment in order to fully and successfully complete the

Statement of Work described in this document. The detailed bid shall be presented in a MS Excel spreadsheet that is fully functional with formulas intact for ARS analysis of the bid. The proposal shall be submitted in MS Word. Neither type of documents will be password projected. Contractor has option of additionally submitting their proposal in .pdf format for fidelity purposes should they desire to do so but any Bid Proposal will not be accepted for review until it’s presented in MS Excel and MS Word format.

Contractor Responsibility:

The project has a base bid to be performed per the following specifications:

1. Contractor will verify all equipment, dimensions and existing site conditions covered in their report.

2. Contractor is required to manage the project and consult with the Government prior to beginning all work phases. And, to work in a manner that minimizes the impact of the work on Government operations, research, and functions.

3. All work must be performed in such a manner as to not adversely affect daily operations of the facility, its workers, and the onsite facility operations.

Material / Submittals:

The AE firm shall submit a draft of their report for review and comment to the Lab personnel, the EPM and the Contracting officer for a period of 10 business days. Upon review, incorporation of ARS comments, and approval by ARS personnel, the final version of the report shall be issued.

Installation Procedure:

Contractor will verify all dimensions and site conditions prior to beginning work. Contractor will schedule the work between working hours as listed below. Contractor is required to provide labor, specified material, equipment, and other tools required to perform the job fully and completely. No Government equipment will be available for use by the contractor. The contractor shall be responsible for protecting his work at all times and ensuring the safety of his crew and ARS employees. Upon completion of the project, the contractor shall remove from the premises all accumulated materials and rubbish caused by the project. Premises shall be left in a clean, orderly, and acceptable condition.

Project Schedule:

The completion of this project shall not exceed 45 days from date of notice to proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.

Work Hours:

Contractor work hours shall be Monday through Friday, seven (7) A.M. to four (4) P.M. except for Government holidays or as otherwise arranged with the site personnel in advance.

PROJECT CONTACTS:

RESEARCH LEADER:

Dr. David I. Shapiro-Ilan, Ph.D, Tel. No.: 478‐956‐6444

Fruit and Nut Research 21 Dunbar Road Byron, GA 31008 E‐mail: Clive.Bock@ars.usda.gov

ADMINISTRATIVE OFFICER (AO):

Tracy George Tel. No.: 478‐956‐6416 Fruit and Nut Research 21 Dunbar Road Byron, GA 31008 E‐mail: Tracy.George@ars.usda.gov

SITE WORK COORDINATOR:

William Rengstorf Tel. No.: 478‐956‐6466 Fruit and Nut Research 21 Dunbar Road

Byron, GA 31008 E‐mail: William.Rengstorf@ars.usda.gov

CONTRACTING OFFICER (CO):

Unassigned

ENGINEERING PROJECT MANAGER (EPM):

Everett Wilson, PE Tel. No.: 720‐618‐0703 USDA, ARS, SEA Facilities

3550 Main Street #5121 Houston, TX 77002 Email: Everett.Wilson@ars.usda.gov

Photographs

Building 14

Building Drawing

Ariel View

Similar Wall

South Wall

West Wall

File details come from the government source that posted it. Updated .