Zeloski_Site_Showing_Notes_May_10.pdf

PDF 72 KB Posted

Attached to
Zeloski Marsh WRE Restoration Project Federal contract opportunity
Solicitation number
123C7818Q0014
Issued by
Department of Agriculture National Resources Conservation Service Headquarters

View the file

Other files for this federal contract opportunity

Other files attached to Zeloski Marsh WRE Restoration Project, newest first.
File Type Posted
123C7818Q0014_Zeloski_Marsh_WI_RFQ_Pacakge.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site Showing Notes

Zeloski Marsh WRE Restoration Project Site Showing Held May 10, 2018

1. Contractors were informed access to site was changed from the west end of Alley Road to the

Wisconsin DNR Parking Lot on London Road.

2. Contractors were informed to avoid equipment traffic on the bike trail and to repair and restore any disturbance to the bike trail.

3. Contractors were informed that a change to the construction plans will be made to include Class I, non-woven geotextile placed underneath any crushed stone surfacing. This adds 552 sq. yds.

to the original quantity (~414 linear feet by ~12 feet wide = 552 sq. yds.).

4. Contractors were informed that helical corrugated metal pipe for water control structure was acceptable and must meet Wisconsin NRCS Construction Specification #6, Corrugated Metal Pipe Conduits.

5. Contractors were informed that it was acceptable to waste any stripped vegetation from the work areas in the borrow area.