Attachment 3 - Questions and Answers.pdf
PDF 112 KB Posted
- Attached to
- Boiler and Water Heater Replacement Federal contract opportunity
- Solicitation number
- 1232SA26Q0393
About this file
This is a Questions and Answers document for federal contract 1232SA26Q0393 addressing clarifications on a USDA boiler and hot water system replacement project.
The document clarifies that all equipment and materials, including boilers, hot water heaters, pumps, and variable frequency drives (VFDs), must comply with the Buy American Act and that the government estimate was based on BAA-compliant equipment. High-efficiency boilers must meet a minimum 10:1 turndown ratio or greater. Piping, valves, and insulation should be installed to match current specifications or fitted to accommodate new equipment, requiring a mandatory site visit by April 15, 2026 at 4:00 PM. The existing boilers are EVAM2000 non-condensing copper fin tube models to be replaced with Thermal Solutions AMP2000 condensing boilers, which may require modifications to concrete footprint, piping, and venting configurations. The current Building Automation System (BAS) platform is through Inteliglas Corporation (contact: Scott Martin at scott@inteliglas.com), and the contractor must disconnect existing BAS controls and establish BACnet communication to new boilers. The contractor should notify the facility's maintenance mechanic when hot work will occur to disable fire alarm systems. System pumps include boiler leg hot water pumps (Pumps 1, 2, 3) controlled by boilers and circulation hot water pumps with independent VFDs (Pumps 4, 5), with detailed specifications available in Taco Inc. PDFs. The expansion tank is manufactured by Taco Inc. (Model CA300-3, Mfr serial no. HO6879). The water heater to be removed was manufactured by PVI Industries LLC (Mfg serial no. 123135) and differs from the SOW specification. Domestic hot water is not fed by indirect tanks heated by the boilers.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_1232SA26Q0393_Amd_0001.pdf | ||
| Sol_1232SA26Q0393_Amd_0001.pdf | ||
| Attachment 4 - Pump Information.pdf | ||
| Sol_1232SA26Q0393.pdf | ||
| Attachment 1 - Scope of Work (SOW).pdf | ||
| Attachment 2 - Wage Determination WI20260011dated 2 Jan 2026.pdf | ||
| Site Visit Information.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 3 – Questions and Answers 1232SA26Q0393
1. The contract requires equipment and materials to meet the Buy American Act (BAA). Was the internal government estimate based BAA-compliant equipment and materials, in particular the boilers, hot water heater, pumps, and VFDs?
Yes
2. What is the minimum turndown requirement for the high efficiency boilers? Is a 10:1 turndown or greater acceptable?
Yes
3. What are the specifications for piping, valves, and insulation? None were called out in the
SOW.
Piping, valves, and insulation to be installed to same specifications as currently installed, or to specifications to fit new equipment. Site visit needed to verify current installation.
4. According to the SOW, the contractor is responsible for disconnecting existing BAS controls and connecting BACnet communication to the new boilers. What is the existing controls platform used at the facility? Who is the facility’s BAS controls contractor? Please provide a POC for the BAS contractor.
The current BAS platform is through Inteliglas Corporation. Contact for Inteliglas Corp. is Scott Martin (scott@inteliglas.com).
5. Will the facility or the contractor be responsible for disabling fire alarm devices during hot work activities inside the mechanical room? If the latter, please provide POC for the building’s FA system?
The contractor can notify the maintenance mechanic when hot work will be completed to disable the fire alarm system.
6. What is USDA’s cutoff date for site visits?
4/15/2026 at 4pm
7. From the photos we have the EVAM2000 non-condensing copper fin tube boilers. The Thermal Solutions AMP2000 condensing boilers have a different footprint, piping, and venting configuration. How will these differences be accommodated?
The SOW text did not include the specific model number. The photos included should be used as what is on-site, along with a required site visit to verify the actual footprint, piping, and venting configuration. The concrete footprint, piping, and venting may need to be modified to fit the new boilers and connect to the current piping and venting.
8. What is the flow and head of the system pumps? What is the model number of the existing system pumps?
See information PDFs from Taco Inc. Pumps 1,2,3 are the boiler leg HW pumps controlled by the boilers. Pumps 4,5 are the circulation HW pumps with independent VFDs.
9. Do you have additional information on the expansion tank model number?
Manufacturer: Taco Inc.; Model number: CA300-3; Mfr serial no. HO6879
10. What is the model number and manufacture of the water heater?
The water heater to be replaced is different from what is called for in the SOW. The water heater to be removed was manufactured by PVI Industries LLC with a Mfg serial no. 123135
11. Is the DHW fed by indirect tanks heated by the boilers?
No