ARS_Prosser_BentonPUD_DevLtr.pdf

PDF 5 MB Posted

Attached to
Electrical Installation for Modular Building Federal contract opportunity
Solicitation number
1232SA26Q0125
Issued by
Department of Agriculture Agricultural Research Service

About this file

This is a Developer's Agreement from Public Utility District No. 1 of Benton County for electrical utility facilities installation at the US Department of Agriculture's Mod Lab facility located at 24106 N Bunn Road, Prosser, Washington (BPUD Work Request #741308). The District will install a three-phase, 120/240 volt overhead transformer bank and related electrical distribution system. The developer is responsible for arranging easements (10 feet in width), providing a notarized easement form, coordinating trench opening and backfilling per District specifications, scheduling a pre-construction meeting with all utilities and contractors, and verifying subcontractor compliance with District requirements and WAC 296-155-428.

The total overhead electric facilities fee is $10,005.76, consisting of $303.00 for easement charges and $9,702.76 for construction assembly units and labor. Fees must be paid within three months of the invoice date or will require recalculation. If fees are paid within three months, electric facilities must be scheduled for installation within one month of payment. Work will be voided if not completed within one year. The developer must complete and return an Application for Service with the firm's Unified Business Identification number, arrange to pick up a pre-wired 13-terminal meter base from the District's Meter Shop with two days' advance notice, install a 1-inch conduit from the Current Transformer compartment to the meter base, and comply with transformer location requirements under WAC 296-46B-450. Change order work requires additional invoicing and payment before work resumes. Late payments incur 1% monthly fees and may be transferred to collection after three months past due. The District reserves the right to postpone projects due to supply chain deficiencies and makes no warranty regarding installation timelines.

View the file

Other files for this federal contract opportunity

Other files attached to Electrical Installation for Modular Building, newest first.
File Type Posted
USDA - ARS - REVISED ELECTRICAL_7.23.25.pdf PDF
Electrical drawings Question Answers.docx DOCX document
USDA - ARS - REVISED PANEL SCHEDULE_7.23.25.pdf PDF
ARS_Prosser_Utilities_B300.pdf PDF
Wage Rates.pdf PDF
LPTA Evaluation Criteria for a Service Contract 1232SA26Q0125.docx DOCX document
1153441_ PGIRU- Bryla_ Prosser Mod. Building Elect. FY26- SOW.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BPUD Developer’s Commercial Form Rev. 03/25/2025

April 28, 2025

DEVELOPER’S AGREEMENT

Developer: US Department of Agriculture

24106 N Bunn Rd.

Prosser, WA 99350

Project: Mod Lab

24106 N Bunn Rd.

BPUD Work Request #741308

Dear Developer:

Due to supply chain deficiencies, Public Utility District No. 1 of Benton County, hereafter referred to as the “District” reserves the right to postpone/reschedule projects based on material or equipment availability. Notwithstanding any other provision herein to the contrary, the District makes no warranty or representation regarding when the transformer and other equipment will be installed, and Developer hereby waives and releases the District from any liability, claim or damage resulting from delays in the installation of such equipment.

The design has been completed for the overhead electrical distribution system for the referenced project. The District will install a three phase, 120/240 volt, overhead transformer bank for this service. All customer panels will be three phase, and all loads must be balanced. This project is subject to the approval of the Commission of the District. This design is for the

District electric facilities only, you must contact all other utilities for their requirements.

For this project, the District will consider you as the DEVELOPER. As the Developer, you will need to address the items outlined in this agreement before the District can complete their work and be able to provide power. The Developer has the responsibility to verify that subcontractors adhere to District requirements and specifications, and to comply with WAC 296-155-428. This agreement is not intended to represent a proposed schedule as to when the District may commence its work. Furthermore, there is no guarantee as to when either temporary or permanent power will be available at the job site. Construction scheduling of approved projects is subject to the availability of materials.

PLEASE NOTE

Important documents enclosed

Before this project can proceed, all documents contained within this letter must be completed and returned. To avoid delay of this project, please check to see that all information is correct and complete.

Mod Lab

Section 1.0 Project Requirements:

1.1 The following items need to be completed before this project will be released to the

District’s Operations Department for scheduling:

Sign and return the last page of this Developer’s Agreement, keep one for your records.

Arrange for the District to be granted easements as needed.

► Have the enclosed easement form signed and notarized by legal owners of property to us for recording. The person(s) who are executing the instrument need to provide evidence that they are authorized signees.

► When this has been completed, return the document to me and I will send it for recording.

► All easements are to be 10.00 feet in width.

Overhead electric facilities fees in the amount of $10,005.76 will need to be paid but not until after you receive an invoice. By signing the form at the end of this letter, you are agreeing to the fees listed below. These fees are per current District fee schedules.

» Primary fees for this project are: $10,005.76

» The fees are good for three months from the date of this Agreement. If these fees have not been paid within three months, they will need to be re-calculated. If the fees are paid within three months; the electric facilities will need to be scheduled for installation within one month of payment. Due to equipment and material delays the District cannot guarantee availability.

» If fees have not been paid after you are invoiced, and the work has not been completed within the one-year time frame, the job will be VOIDED. If you still require service after this time frame, you will need to re-submit plans for District review.

» Complete and return the customer Application for Service, being certain to provide the Unified Business Identification (UBI) number for the firm under whose name the electric service will be connected.

» Requests for both temporary and permanent services (if applicable) should be made at our Kennewick office located at 2721 W. 10th Avenue, Kennewick, WA, or the Prosser office located at 250 N Gap Rd.

Schedule a pre-construction meeting that will need to include all utilities, excavator, developer, and surveyor.

After all these items have been completed and all necessary information returned to the District, the work order will be forwarded to the District’s Operations Department. The Developer will be responsible for opening and backfilling all the trenches associated with this project per

District specifications; (please read Section 2.0 on Trench Requirements). The excavation contractor will need to coordinate when the trenches should be opened with our Assistant

Superintendent of Transmission and Distribution, Jessie Grad (509)222-9305. Mr. Grad will not have any information pertaining to this project and will not be able to schedule any work until the aforementioned items have been completed. Due to the amount of construction occurring in this area, it typically requires four to six weeks to schedule a crew.

1.2 The following items need to be completed prior to the service being energized for this project:

Refer to the enclosed Standard Q-1A Meter Socket Terminal Clip Configuration

Refer to the enclosed Standard Q-1B Residential & Commercial Services Maximum

Lengths & Required Conduit Sizes

Refer to the enclosed Standard Q-5E Current Transformer (CT) Compartment

Requirements for Three Phase Services 201-800 Amps

Install a 1-inch conduit from the CT compartment to the meter base.

Refer to the enclosed Standard Q-10A Work Area Clearance

The potential fault current for this installation is/or can be up to 20,000 amps at the secondary bushings of the transformer.

Arrange to pick up a prewired 13-terminal meter base without frame from the District’s

Meter Shop. Your electrician will need to notify the Meter Shop two days in advance of when he will be picking up the meter base.

While the District will take all reasonable precautions to prevent phase failure or abnormal voltage variations, please be advised that the potential for these operating aberrations does exist and that it will be the customer’s responsibility to protect all equipment against them. As the Developer, it will be your responsibility to verify that the transformer location complies with WAC 296-46B-

450, Transformers. If it is found subsequent to the installation of the transformer that this regulation has been violated, the District will have no choice but to de-energize the transformer until the problem is rectified. This may include the District relocating the transformer at full cost to the Developer, per this Agreement.

The District develops the initial electrical distribution system design, per the Developer’s instructions, for a subdivision or plat at no charge. A charge of $75.00 per hour may be assessed the customer if the design is modified within four (4) months of initial design.

Section 3.0 Change Order Requirements:

If the Developer causes changes to the most recent design following initial Developer fee payment, the Developer shall be held fully responsible. If the District has initiated work and a change order has been found to be necessary, the District will stop work, redesign job, and issue an additional invoice for additional labor and material costs incurred or expected to be incurred.

Work will not resume until the additional invoice is paid in full. If circumstances require change order work to be completed due to hazardous conditions, costs for this will be captured via an additional invoice. The District will not energize customer’s equipment including temporary service until all invoices have been paid in full. If project circumstances necessitate that change order work be completed prior to invoicing, payment is required within 30 days. Any invoices not paid within 30 days from the invoice date will incur a 1% late fee, with an additional 1% fee applied for each subsequent month the invoice remains unpaid. Unpaid invoices more than three months late may be transferred to a collection agency.

BPUD Mapping Disclaimer

The District provides this data for your sole use “as is”. The requestor/receiver hereby acknowledges that the attached mapping information is not guaranteed to be accurate, correct or complete and any conclusions drawn from the information are the responsibility of the user.

Additionally, the requestor/receiver acknowledges that the attached mapping files are for illustration purposes only and are not suitable for site-specific decision making and in no way are the attached mapping files a suitable replacement for calling for Utility Locates before ground disturbing activities.

The requestor/receiver agrees not to disclose, lease, sell, distribute, make, transfer or assign the requested mapping data in any other transaction without the prior written consent of the

District.

It is further understood that this information is the work product of the District, created solely for the District’s use and for no other purpose.

This project is on hold. The District will be unable to provide information to any contractors until you contact me. The Work Request number and project name (mentioned on Page 1) should be referenced in any correspondence with the District. This includes conversations with

Jessie Grad regarding the scheduling of trenching and District work. If you have any questions, you may contact me at (509)582-1233.

Cordially Yours, Chad Brooks, Distribution Design Technician

Public Utility District

No. 1 of Benton County

CB:jam c: WO #741308 File

Enclosures

SEE NEXT PAGE FOR REQUIRED DEVELOPER’S SIGNATURE

Mod Lab Return this page to:

Page 6 of 6 Benton County PUD

Attn: Engineering Dept.

PO Box 6270

Kennewick, WA 99336

Due to supply chain deficiencies, the District reserves the right to postpone/reschedule projects based on material or equipment availability. Notwithstanding any other provision herein to the contrary, the District makes no warranty or representation regarding when the transformer and other equipment will be installed, and Developer hereby waives and releases the District from any liability, claim or damage resulting from delays in the installation of such equipment.

By signing below, you agree to the responsibilities as the Developer.

DEVELOPER / COMPANY BPUD Work Order #741308

Public Utility District No. 1 of Benton County

Signature Signature (BPUD Distribution Design Tech)

Printed Name

Date Signed:

SIGNATURE FOR FEES (IF APPLICABLE)

By signing below, you agree to pay the fees as mentioned earlier in this letter. After the District receives this signature page back, the project fees will be invoiced to you.

Signature

Printed Name

Company

Name:

Date Signed:

Address of where to send bill:

(Name of Company)

(Contact Name)

(Mailing Address)

Phone #:

Developer’s Agreement Email this signed page to engservice@bentonpud.org

Payment Options: You may mail or deliver a check to our offices. Credit card payments are not accepted for primary fees.

Revised 03/22/2024 C:\Users\LOCAL_~1\Temp\vault\2025_04_28_10_06_39_834\741308_FeeSheet.doc

ELECTRIC FACILITIES CHARGE SHEET

PUBLIC UTILITY DISTRICT NO. 1 of BENTON COUNTY

Customers - Aid to Construction fees must be paid via check or cash

DEVELOPER: US Department of Agriculture W.O. # 741308

PROJECT: Mod Lab S.O. #

LOCATION: 24106 N Bunn Rd.

PERMITS:

(Identify Permit Here) =$ 0.00 253.60/253.61

QUIT CLAIM FEES:

Quit Claim Deeds Per Line Extension Policy 24(D)

@ $500 each =$ 0.00 253.60

EASEMENT CHARGE

(1) Easements Per Line Extension Policy 24(D) @ $303 each =$ 303.00 253.60

SPECIAL CHARGES (Aid to Construction)

Construction assembly units and labor-overhead (New OH) =$ 9,702.76 253.60

Remove/Retire assembly units and labor-overhead (Existing OH) =$ 0.00 253.62

Construction assembly units and labor- underground (New UG) =$ 0.00 253.61

Remove/Retire assembly units and labor-underground (Existing UG) =$ 0.00 253.63

Primary/Design Fees Undergound (New UG) =$ 0.00 253.61

Primary/Design Fees Overhead (New OH) =$ 0.00 253.60

TOTAL AMOUNT DUE = $10,005.76

WORK WILL NOT BEGIN UNTIL THIS AMOUNT IS PAID

Calculations of line length will be on the basis of average length per lot or unit for the entire development. Development of adjacent undeveloped parcels common to a line route may be considered when calculating per lot line lengths.

Engineered by: Chad Brooks Date: 4/28/2025 Misc. Receipt #

X Rate Schedule Description

11 Residential/Farm

21 Small General Service

X 22 Medium General Service

23 Large General Service – Non Time-of-Use

24 Large General Service – Time-of-Use

33 Large Industrial

71 Small Agricultural Irrigation

72 Large Agricultural Irrigation

73 Large Agricultural Irrigation Pumping Station With Miles Of Line Charge

74 Agricultural Irrigation Sprinkler Wheelturning

75 Agricultural Irrigation Sprinkler Wheelturning With Miles Of Line Charge

APPLICATION FOR SERVICE

Please e-mail completed applications to:

EngService@bentonpud.org or you may fax (509) 586-6876

Rev 09/2020

SO#

Temp#

SERVICE LOCATION INFORMATION:

SERVICE ADDRESS:

CITY: State: Zip:

SUBDIVISION/PLAT:

LOT: BLOCK: TAX ID#

HAVE YOU EVER HAD SERVICE WITH BENTON PUD? YES NO PHONE NUMBER: ( )

ACCOUNT INFORMATION:

BILLING NAME:

SSN# Benton PUD will contact you to obtain SSN or other proof of identity

UBI#:_______________

MAILING ADDRESS: CITY: STATE: ZIP:

CO-APPLICANT:

SSN# Benton PUD will contact you to obtain SSN or other proof of identity

UBI#: _______________

PHONE: ( ) Email Address:

CONTACT INFORMATION:

GENERAL CONTRACTOR: PHONE NUMBER: ( )

ELECTRICIAN: PHONE NUMBER: ( )

SERVICE INFORMATION:

TYPE OF SERVICE: OVERHEAD UNDERGROUND RESIDENTIAL COMMERCIAL ELECTRIC VEHICLE

NEW SERVICE ALTERED SERVICE IRRIGATION SECURITY LIGHT

TEMPORARY SERVICE: The District offers only metered temporary services. ______Y _____N ELECTRIC INTENSIVE LOAD

If temporary service, is pole installed and ready for inspection?

____Y____N (Will Call)

If underground service, is Trench Open & Ready for Inspection?

_____Y _____N (Will Call)

LOAD INFORMATION:

HOUSE DUPLEX APARTMENT MFG. HOME SHOP COMMERCIAL ___________ SQ. FEET

SERVICE SIZE: 200 AMP 320 AMP OTHER ________ AMPS OR KW ________

TYPE OF HEAT:

HEAT PUMP DUCTLESS INVERTER ____ TON CEILING CABLE IN WALL ELECTRIC FORCED BASEBOARD

OTHER ELECTRIC HEAT ____ TOTAL KW GAS OIL OTHER NO HEAT

ADDITIONAL LOADS:

AIR CONDITIONING ____ TON PUMP SIZE ____ HORSEPOWER WATER HEATER: HEAT PUMP ELEC. GAS

HOT TUB ____ KW SAUNA ____ KW POOL ____ KW

ADDITIONAL INFORMATION:

By initialing below, I acknowledge I have read important information about my Benton PUD Account:

• Benton PUD may require a deposit for electric service.

• A soft credit check will be conducted to determine credit worthiness and verify identity.

• When signing up for service at a new location, a Start Service fee will be added to the first monthly bill.

• Benton PUD policies and rates are approved by Benton PUD’s Commission and are the governing documents under which customers receive electric service from Benton PUD. The policies can be found on our website at www.bentonpud.org. You can request a hard copy be mailed to you by calling Customer Service at (509) 582-2175.

SIGNATURE DATE:

PHONE: ( ) MOBILE:

http://www.bentonpud.org/ o z i5

.9õ o

8" Min.

2'Max.

xo

(o ?o

Hinges on CT cabinet must be on the side opposite the meter base

6'Max.

5'Min.

1" Conduit

Mounting base for current transformers

(by customer, see table on sht. 2)

Conduit(s) to transformer

Prefered Alternate

2'Min.

Finished Grade

TMG

8t29t2020 1 of2

SHT

REilTûtl

BY: JAD

DAÏE: 03126110

Current Transformer (CT) Enclosure Requirements for

Three Phase Services 400-800 Amps

TITLE:

Q.5E z õ

¡5 e À

Pre-Approved Three Phase Current Transformer Cabinet & Mounting Bases GT Service Type Cabinet Dimensions GT Gabinets GT Mounting Bases

Service Size

Number of Load

Conductors width Height Depth Cooper B-Line

Part# Milbank Part #

Cooper B-Line Part #

Milbank Paft#

EUSERC

Drawing #

4004 1-2 30" 49" 11" 30481 I HRTCT cT30481 1-HC 6067H4 or

6067HAL

K4798 or

K4904 329A or

400-800A 1-4 36" 48" 11" 36481 lHRTCT cT36481 1-HC

6067HEE

or

6067HEEL

K4798 or

K4722

Notes:

1. Details shown are minimum District standards and are not intended to depict Washington State Labor and lndustries requirements.

2. Current transformer enclosure and mounting base to be supplied and installed by the customer.

3. Customer shall ensure the load conductors are compatible with the connectors on the EUSERC 3288 style current transformer mounting base. All mechanical cable termination blocks shall be provided by the customer.

4. Current transformers to be supplied and installed by District.

5. The current transformer mounting base shall have a 50,000 Amp minimum fault current rating.

6. The enclosure shall be raintight, with a sealable, hinged, cover.

7. Reference District standard Q-1 B for conduit and conductor requirements.

8. Customer owned and installed service wires for single phase services are limited to (6) sets of conductors and shall not exceed 750 kcmil aluminum or copper.

9. The customer shall make up and terminate the load side connections in the current transformer enclosure.

10. The customer service entrance conduits must exit the enclosure on the load side of the current transformer mounting base. The District will not allow customer conductors or conduit in the District's terminating and pull space.

11. A pre-wired meter base shall be provided by the District and installed by customer.

12. Bonding must be in accordance with the current NEC requirements.

13. Meter sockets shall be installed within 24" of non-hinge side of enclosure.

14. lf estimated load isoverTSkVA (1201208V) or150kVA (2771480V) and currenttransformermetering isneededtofacilitate known additional load growth, customer may be allowed to install current transformer enclosure.

15. Current transformer metering may be allowed within the secondary compartment of the transformer at the discretion of the District if estimated load is at least 100kVA. Current transformer metering, specifically for services which are fed by a District 75kVA or smaller transformer shall be metered within a current transformer enclosure.

TMG

8n9t2020 2 oÍ2

BY: JAD

DArE:03/26/10

Current Transformer (CT) E nclosure Req uirement fror

Three Phase Services 400- 800 Amps

TITLE:

8-5E (Gont.)

o i5

.9ã c

6' 6'

6'

Typical Overhead

10'

1 0'

Typical Underground

BEilMÎ(

IFUO

Work Area Clearance

Utility Poles and Junction Boxes

TITLE:

TMG

u12n020 1of I Ktsv NU: 2 lËi'!å ,Ìóå-- ""'?lulL¡o

DWG- NO.

Q.IOA)RAWN BY: DDB

TRAWDATE: 111031'10

Description : Brooks- USDA,24106 N Bunn Rd.

Map Number: 92519-7403

W/O#: 741308 Project Manager: CHAD M BROOKS

Address: 24106 N Bunn Rd. Issue Date: 04/23/2025

City/St.: Prosser, WA Warehouse:

Phone: Page 1 of 2

I

File details come from the government source that posted it. Updated .