This document contains an amendment to a solicitation for an epoxy flooring installation project. The United States Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Northeast Area is seeking to install epoxy flooring systems in several buildings located at its Beltsville, Maryland facility. The square footage of each building is provided. The amendment corrects the date of an organized site visit and incorporates seven questions and answers relating to product specifications, pricing for recommended upgrades, and logistics regarding occupancy and heating requirements for curing. Contractors are instructed to provide alternate pricing for recommended upgraded products and installation details.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12305B23R0042 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ARS-12305B

BELTSVILLE MD 20705

BLDG 003, RM 223, BARC-WEST

10300 BALTIMORE AVENUE

USDA ARS NEA AAO ACQ/PER PROP

09/05/20230002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

09/05/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Install Epoxy Flooring Systems, BARC, Beltsville, MD

1. The date of the second organized site visit is corrected to September 20, 2023, at 9:00

AM Eastern Time.

2. The seven Questions and Answers on the last page are hereby incorporated.

END

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

ROGER D. AMMONS

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Questions and Answers 12305B23R0042 1104396 Install Epoxy Flooring System

Question 1: It is relatively difficult to determine the actual total square footage of the project because of the non-clarity of some of the attachments. Please provide the square footage of each building, to allow the calculation of the total square footage.

Answer 1:

1. B1080 1080sqft

2. B1082 1080sqft

3. B1083 1080sqft

4. B1182 2625sqft

5. B1194 1787sqft

6. B1207 1875sqft

7. B1381 384sqft

8. B1382 384sqft

9. B1383 384sqft

10. B229, Rm#101 1568sqft

11. B229, Rm#102 1568sqft

Question 2: The spec looks fine for some of the buildings, but the spec is not what's needed in 229 and the 1380's building. The animal feces and the chemicals used need a heavier coating that will last long and more slip resistant since it's sloped. Recommend using a product like urethane cement with a urethane topcoat.

Answer 2: Contractor to provide alternate pricing for recommended upgrade.

Question 3: Do you want to cove base up the wall? In building 1081 that is done it has a cove base, but spec doesn't call for it.

Answer 3: Contractor to provide alternate pricing for cove base upgrade.

Question 4: If you drill holes in 1080 you will see that it's impossible to patch them without putting another coat of quartz and epoxy on the floor.

Answer 4: Contractor to provide alternate pricing for second coat & epoxy.

Question 5: Will each line item be a separate trip, or can we buckle some of them together?

Answer 5: These buildings used for housing animals. Sometimes they occupied or vacant at different time of year.

Question 6: One building had caught fire. Will that area be fixed or are we doing the floor part first before the repair?

Answer 6: Floor part is a first and for curing purpose contractor needs to figure out option.

Question 7: Do all these buildings have heat? As we get closer to winter, we will need heat to get the product to cure properly.

Answer 7: Some of the buildings have heat. For other buildings contractor needs to figure out source of heat to cure

END