Rev. #1 SOW for BARC West Electrical Substation Smart Meter Installation Project.doc
DOC document 260 KB Posted
- Attached to
- INSTALLATION OF ELECTRICAL METERS Federal contract opportunity
- Solicitation number
- 12305B21R0020
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers 2.pdf | ||
| Amendment 0002.pdf | ||
| Questions and Answers 1.pdf | ||
| Amendment 0001.pdf | ||
| Submittal Register For BARC Electrical High Voltage Substation Electrical Meter Installation Projetct (1).doc | DOC document | |
| Visitor Contractor Wellness Check.docx | DOCX document | |
| NEA Contractor Approval Procedure Template.docx | DOCX document | |
| RFI Form.docx | DOCX document | |
| 12305B21R0020.pdf | ||
| MD20210044 05142021.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES DEPARTMENT OF AGRICULTURE
BELTSVILLE AGRICULTURAL RESEARCH CENTER
FACILITIES SERVICE
ENGINEERING AND CONSTRUCTION BRANCH
BUILDING 426A, BARC-EAST
10300 BALTIMORE AVENUE
BELTSVILLE, MARYLAND 20705-2350
STATEMENT OF WORK AND SPECIFICATION
TO
INSTALL AN ADVANCED ELECTRIC METER/SMART METERS ON WEST SUBSTATION 13.2kV PEPCO INCOMING FEEDERS AND BARC OUTBOUND FEEDERS
BELTSVILLE AGRICULTURAL RESEARCH CENTER
BELTSVILLE, MARYLAND
Rev. #1 May 25, 2021
Section 01010 General Requirements
1.1 GENERAL INTENTION
A. Contractor shall completely prepare the site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work as required by the contract documents.
B. All employees of general contractor and subcontractors shall comply with ARS security management program, obtain permission of the ARS Location Manager, be identified by project and employer by wearing contractor issued identification badges at all times on ARS property, and restricted from unauthorized access.
C. Prior to commencing work, the general contractor shall provide proof that an OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
D. Training:
1. All employees of the general contractor or subcontractors shall have the 10-hour OSHA certified Construction Safety course and /or other relevant competency training. Supervisors shall have completed the 30-hour OSHA training.
2. Submit training records of all such employees to the Contracting Officer for approval before the start of work.
1.2 STATEMENT OF BID ITEMS
ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, and removal of existing structures and construction and certain other items to install an advanced electric meter on BARC East Substation 13.2kV incoming feeders. The new equipment shall be provided and installed by the contractor, complete and ready for use including:
A. Installation:
A.1 The Contractor shall Provide and install of (3) Three advanced electric meter on the BARC West Substation 13.2kV PEPCO Incoming feeders, with the following specifications: Schneider Electric ION 9000 or equal.
A.2 The Contractor is not responsible for software integration of the agency meter into the Government’s network, but the Contractor shall coordinate with the agency and agency’s local area network systems integrator to provide field assistance with this function.
Optional Installation of Three (3) Electrical Meter to BARC West Outbound Electrical Feeders as Funding Permits:
A.1 The Contractor shall Provide and install of (3) three advanced electric meter on the BARC West Substation 13.2kV BARC West Outbound Electrical feeders, with the following specifications: Schneider Electric ION 9000 or equal.
A.2 The Contractor is not responsible for software integration of the agency meter into the Government’s network, but the Contractor shall coordinate with the agency and agency’s local area network systems integrator to provide field assistance with this function.
B. Execution:
B.1 Provide advanced meter capable of measuring interval data at 15 min increments. Provide latest version of Schneider ION 9000 advanced smart meter or Siemens Sentron PAC4200 Smart Meter or equal. (Brand name provided only to identify the salient physical, functional or performance characteristics) and associated hardware /software peripherals necessary for Government IT staff to connect meters to existing Government sub-metering system.
B.2 Coordinate with and provide support to BARC IT personnel to establish secure communication with meter.
B.3 Indicate Government meter and Current Transformers (CT) on both review and as-built drawings sets.
B.4 The government expects one meter for each of the three feeders.
B.5 The Government Requires that the meters not to be connected to the protection/control network. The Meters shall be a physical separation with BARC IT Network System.
C. Testing:
C.1 Test and demonstrate complete power monitoring system operation to location facilities and IT personnel Identified by ARS.
The agency power meter is subject to ARS device security requirements. The ION 9000 has been scanned and has a remediation plan from Schneider Electric. If another meter is proposed as an alternative, then the Contractor must submit an RFI to Government IT Security personnel to determine if that meter has been scanned and has an acceptable remediation plan with the manufacturer. If not the Contractor must:
(a) provide a meter (installed, at contractor’s risk) temporarily for ARS to scan, with complete configuration information; (b) obtain written assurance from the manufacturer that the manufacturer will make reasonable efforts to remediate any high risk or critical vulnerabilities detected
SPECIFICATIONS
Section 26 27 13.10 30
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 100 (2000; Archived) The Authoritative Dictionary of IEEE Standards Terms
IEEE C2 (2012; Errata 2012; INT 1-4 2012; INT 5-7 2013; INT 8 2014) National Electrical
Safety Code
IEEE C37.90.1 (2012) Standard for Surge Withstand Capability (SWC) Tests for Relays and
Relay Systems Associated with Electric Power Apparatus
IEEE C57.13 (2008; INT 2009) Standard Requirements for Instrument Transformers
INTERNATIONAL ELECTROTECHNICAL COMMISSION (IEC)
IEC 61000-4-5 (2014) Electromagnetic Compatibility (EMC)- Part 4-5: Testing and Measurement Techniques - Surge Immunity Test
IEC 62053-22 (2003; ED 1.0) Electricity Metering Equipment (a.c.) - Particular Requirements - Part 22: Static Meters for Active Energy
(Classes 0,2 S and 0,5 S)
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
ANSI C12.18 (2006) Protocol Specification for ANSI Type 2 Optical Port
ANSI C12.20 (2010) Electricity Meters - 0.2 and 0.5 Accuracy Classes
ANSI C62.61 (1993) American National Standard for Gas Tube Surge Arresters on Wire Line
Telephone Circuits
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2014; AMD 1 2013; Errata 1 2013; AMD 2
2013; Errata 2 2013; AMD 3 2014; Errata
3-4 2014; AMD 4-6 2014) National
Electrical Code
1.2 DEFINITIONS
Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, shall be as defined in IEEE 100.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the
Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
a. Maintenance manual shall provide:
1. Condensed description of how the equipment operates.
2. Block diagram indicating major assemblies.
3. Troubleshooting information
4. Preventive maintenance.
5. Spare parts information.
b. Provide operation and maintenance manuals required by submittal item
"SD-10 Operation and Maintenance Data."
SD-02 Shop Drawings
SD-03 Product Data
Power Meters; G
Current Transformers; G
Potential Transformer; G
Communications Module; G
Protocol Modules; G
Data Recorder; G
Modem; G
Submittals shall include manufacturer's information for each component, device, and accessory provided with the meter, protocol module or communications module.
SD-06 Test Reports
Acceptance Checks and Tests; G
SD-10 Operation and Maintenance Data Power Meters; G
Communications Module; G
Protocol Modules; G
Data Recorder; G
Modem; G
SD-11 Closeout Submittals
System Function Verification; G
1.4 QUALITY ASSURANCE
1.4.1 Installation Drawings
Drawings shall indicate but not be limited to the following:
a. Elementary diagrams and wiring diagrams with terminals identified of advanced meter, current transformers, potential transformers, protocol modules, communications modules, and Ethernet connections.
b. One-line diagram, including meters, switch(es), current transformers, potential transformers, protocol modules, communications modules, Ethernet connections, and fuses. For each meter installation, provide a diagram identified by the building number.
1.4.2 Standard Products
Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship. Products shall have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year period shall include applications of equipment and materials under similar circumstances and of similar size. The product shall have been on sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period. Where two or more items of the same class of equipment are required; these items shall be products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in this section.
1.4.3 Alternative Qualifications
Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than
6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.
1.4.4 Material and Equipment Manufacturing Data
Products manufactured more than 2 years prior to date of delivery to site shall not be used, unless specified otherwise.
1.5 WARRANTY
The equipment items shall be supported by service organizations which are reasonably convenient to the equipment installation in order to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.
1.6 SYSTEM DESCRIPTION
1.6.1 System Requirements
The metering and reading system, consisting of commercial, off-the-shelf meters, protocol modules, communications modules, and communication channels, will be used to record the electricity consumption and other values as described in the sections that follow and as shown on the drawings.
1.6.2 Selection Criteria
Metering components are part of a system that includes the physical meter, data recorder function and communications (modem) method. Every building site identified shall include sufficient metering components to measure the electrical parameters identified and to store and communicate the values as required in the following sections. Contractor shall verify that the metering system installed on any building site is compatible with the facility-wide communication and meter-reading protocol system.
PART 2 PRODUCTS
2.1 POWER METERS
2.1.1 Physical and Common Requirements
a. Metering system components shall be installed according to the Metering
System Schedule shown in this specification.
c. Power meter shall be panel-mounted design. Meters shall be semi-flush, back-connected, dustproof, draw-out switchboard type. Cases shall have window removable covers capable of being sealed against tampering.
Meters shall be of a type that can be withdrawn through approved sliding contacts from fronts of panels or doors without opening current-transformer secondary circuits, disturbing external circuits, or requiring disconnection of any meter leads. Necessary test devices shall be incorporated within each meter and shall provide means for testing either from an external source of electric power or from associated instrument transformers or bus voltage.]
d. If existing meter base is usable, the meter base determines meter form factor. If a new meter is being installed, use meter and base form factor of 9S.
e. Use Class 200 meters for direct current reading without current transformers.]
f. Meter shall be a Class 20, transformer rated design.
g. Meter shall be rated for use at temperature from -40 degrees
Centigrade to +70 degrees Centigrade.
h. Meter shall have NEMA 3R enclosure for surface mounting.
i. Surge withstand shall conform to IEEE C37.90.1.
j. Meter shall have a standard 4-year warranty.
k. Meter shall comply with IEC 62053-22 (Part 21: Static Meter for Active
Energy, classes 0.2S and 0.5S), certified by a qualified third party test laboratory.
2.1.2 Voltage Requirements
a. Meter shall be capable of connection to the service voltage phases and magnitude being monitored. If the meter is not rated for the service voltage, provide suitable potential transformers to send an acceptable voltage to the meter.
b. Meter shall be capable of connection to the service voltage indicated in the Metering System Schedule:
c. Meter shall accept independent voltage inputs from each phase. Meter shall be auto-ranging over the full range of input voltages.
d. Voltage input shall be optically isolated to 2500 volts DC from signal and communications outputs. Components shall meet or exceed
IEEE C37.90.1 (Surge Withstand Capability).
e. The Contractor shall be responsible for determining the actual voltage ratio of each potential transformer. Transformer shall conform to
IEEE C57.13 and the following requirements.
1. Type: Dry type, of two-winding construction.
2. Weather: Outdoor or Indoor rated for the application.
3. Frequency: Nominal 60Hz, 50Hz for those bases that operate on 50Hz.
4. Accuracy: Plus, or minus 0.3% at 60Hz or 0.3% for those systems that operate at 50Hz.
2.1.3 Current Requirements
a. Meter shall accept independent current inputs from each phase. Current transformer shall be installed with a full load rating as shown in the schedule.
b. Single ratio current transformer shall have an Accuracy Class of 0.3 with a maximum error of +/- 0.3% at 5.0 amps.
c. Current transformer shall have:
1. Insulation Class: All 600 volt and below current transformers shall be rated 10 KV BIL. Current transformers for 2400 and 4160 volt service shall be rated 25 KV BIL.
2. Frequency: Nominal 60Hz, 50Hz for bases that operate on 50Hz.
3. Burden: Burden class shall be selected for the load.
4. Phase Angle Range: 0 to 60 degrees.
d. Meter shall accept current input from standard instrument transformers
(5A secondary current transformers.)
e. Current inputs shall have a continuous rating in accordance with
IEEE C57.13.
f. Multi-ratio current transformer where indicated shall have a top range equal to or greater than the actual load. The Contractor shall be responsible for determining the actual ratio of each transformer.
Current transformer shall conform to IEEE C57.13.
2.1.4 Electrical Measurements
Power meter shall measure and report the following quantities:
a. Kilowatt-hours ("kWh" in Metering Systems Schedule) of consumption.
Cumulative.
b. Kilowatts of demand ("kW" in Metering Systems Schedule). Peak average over a selectable demand interval between 5 and 60 minutes (typically
15 minutes).
c. Reactive power ("kVAR" in Metering Systems Schedule). Measured over the same interval as the peak kW reading.
d. Power factor ("PF" in Metering Systems Schedule). Measured over the same interval as the peak kW reading.
e. Time of use consumption ("TOU" in Metering Systems Schedule).
Kilowatt-hours recorded separately for each period set by programming into the meter. Time periods shall be capable of being changed without removal from service. The meter shall internally record and store Time of Use data.
1. Four (4) minimum TOU Rates (Registers)
2. Twenty (20) Year Calendar
3. Two (2) minimum seasons per year
f. Interval recording ("IR" in Metering Systems Schedule). Kilowatt-hours shall be recorded for each 15-minute interval and shall accumulate for 30 days. Memory for recording the interval readings shall be internal to the meter and ANSI C12.19 compliant.
Meter shall provide time-stamped readings for every measured parameter.
g. Meter readings shall be true RMS.
2.1.5 Meter Accuracy
Power meter shall provide the following accuracies. Accuracies shall be measured as percent of reading at standard meter test points.
a. Power meter shall meet ANSI C12.20 for Class 0.2 and IEC 62053-22 accuracy requirements.
2.1.6 An on the Meter Display, Output and Reading Capabilities
Meter shall include the following output signals.
a. The meter will have a face display plate and shall display every electrical parameter indicated to be recorded. Meters shall not be required to indicate interval data collected in a data logger with a communications output feature. Peak values, instantaneous and cumulative values shall be displayed.
2.1.7 Installation Methods
1. Meter base shall be located inside substation.
1. PTs (if required for proper voltage range) and CTs shall be physically connected to the service entrance cables inside the service entrance disconnect enclosure.
2.1.8 Disconnecting Switches
a. Disconnecting wiring blocks shall be provided between the current transformer and the meter. A shorting mechanism shall be built into the wiring block to allow the current transformer wiring to be changed without removing power to the transformer. The wiring blocks shall be located where they are accessible without the necessity of disconnecting power to the transformer. For multi-ratio current transformers provide a shorting block from each tap to the common lead.
b. Voltage-monitoring circuits shall be equipped with disconnect switches to isolate the meter base or socket from the voltage source.
2.1.9 Meter Programming
a. Power meter shall be programmable by software supplied by the meter manufacturer.
b. Software shall have a user-friendly, Windows-compatible interface.
c. Software shall operate on Windows operating systems.
d. Software shall allow the user to configure the meter, troubleshoot meter, query and display meter parameters and configuration data and stored values.
e. Meter firmware shall be upgradeable through one of the communications ports without removing the unit from service.
2.2 COMMUNICATIONS
2.2.1 Communications Methods
2.2.1.1 Optical Port
The optical port shall communicate with a hand-held reading device according to the following requirements.
a. Communications standards
1. ANSI C12.18
2. MV90 protocol
3. ANSI C12.20
b. Read operations
1. Current kWh values Demand (kW) values since last reset
3. Last reset value
4. Meter status
[ 5. Load profile]
c. Write operations
1. Meter setup
2.2.1.2 Serial Port
Provide serial port for connection to modem module where required in this specification.
2.2.1.3 Ethernet
For those meters using the Ethernet, logged information shall be sent using open standard Internet Protocols.
a. On-board Ethernet port support
1. HTTP
2. SMTP
(a) Modbus
b. Distribute stored data by
1. FTP
2.2.2 Communications Protocols and Methods
Communications protocols and methods shall be native to the meter. Provide communications module(s) as required to accomplish the following.
a. Meter shall include an IR port ("IR" in Metering Systems Schedule) for communication to external devices such as handheld readers that support a minimum speed of 9600 baud.
b. [Meter shall include one RS-232 ("RS232" in Metering Systems
Schedule) or[ one RS-485 ("RS485" in Metering Systems Schedule) digital communication port. Each port shall be user configurable with regard to speed, protocol, address, and other communications parameters. Ports shall support a minimum communication speed of 9600 baud for the RS232 port.]
c. Meter shall have a port that can be configured as a 10/100 Base-T
Ethernet port ("BaseT" in Metering Systems Schedule)
2.2.3 Communications Channels Surge Protection
Communications equipment shall be protected against surges induced on its communications channels. Communication interfaces to all field equipment shall be protected to meet the requirements of IEEE C37.90.1 or the requirements of IEC 61000-4-5, test level 4, while the equipment is operating. Fuses shall not be used for surge protection. Metallic cables and conductors which serve as communications channels between buildings shall have surge protection installed at equipment rated for the application installed at each end, within 3 feet 0.9 meters of the building cable entrance. Surge protectors shall meet the requirements of the applicable extension of ANSI C62 (for example, ANSI C62.61).
2.3 METER DATA PROTOCOL
Power meters shall have communicating data protocols native or provided in supplemental modules to communicate with the communications methods that follow.
2.3.1 Open Protocol
Power meter shall support the following open protocols. Contractor shall verify that the meter native protocol is consistent with the facility data recording and communication and data storage system. Contractor shall provide additional converters and modules as required for a complete measurement, recording, communicating and data storage system.
a. Meter shall be fully supported by MV-90 software system or existing AMR software that is MV-90 compatible.
b. For systems that use proprietary software, an alternative, competitive software system must be available.
Systems capable of using more than one brand of commercially available meters are expected. In addition, if proprietary meter reading software is used, meters are to be capable of being read by more than one manufacturer's software.
2.4 SPARE PARTS
2.4.1 Parts List
Provide spare parts as follows:
a. Power meter - two for each type used.
b. Current transformer - three for each type used.
c. Potential transformer - three for each type used.
d. Communications module - one for each type used.
e. Protocol module - one for each type used.
f. Other electronic and power components - one for each type used.
2.5 METERING SYSTEM SCHEDULE
Metering System Schedule is available at http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf
PART 3 EXECUTION
3.1 INSTALLATION
Electrical installations shall conform to IEEE C2, NFPA 70, and to the requirements specified herein. Provide new equipment and materials unless indicated or specified otherwise.
3.1.1 Existing Condition Survey
The Contractor shall perform a field survey, including inspection of all existing equipment, resulting clearances, and new equipment locations intended to be incorporated into the system, and furnish an existing conditions report to the Government. The report shall identify those items that are non-workable as defined in the contract documents. The Contractor shall be held responsible for repairs of modifications necessary to make the system performs as required.
3.1.2 Scheduling of Work and Outages
The Contract Clauses shall govern regarding permission for power outages, scheduling of work, coordination with Government personnel, and special working conditions.
3.2 FIELD APPLIED PAINTING
Where field painting of enclosures is required to correct damage to the manufacturer's factory-applied coatings, provide manufacturer's recommended coatings and apply in accordance with manufacturer's instructions.
3.3 FIELD QUALITY CONTROL
3.3.1 Performance of Acceptance Checks and Tests
3.3.1.1 Meter Assembly
a. Visual and mechanical inspection
1. Compare equipment nameplate data with specification and approved shop drawings.
2. Inspect physical and mechanical condition.
3. Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, verifying tightness of accessible bolted electrical connections by calibrated torque-wrench method.
4. Verify grounding of metering enclosure.
5. Verify the presence of surge arresters.
6. Verify that the CT ratio and the PT ratio are properly included in the meter multiplier or the programming of the meter.
b. Electrical tests
[ 1. Calibrate watthour meters according to manufacturer's published data.]
2. Verify that correct multiplier has been placed on face or meter where applicable.
3. Prior to system acceptance, the Contractor will demonstrate and confirm the meter is properly wired and is displaying correct and accurate electrical information.
3.3.1.2 Current Transformers
a. Visual and mechanical inspection
1. Compare equipment nameplate data with specification and approved shop drawings.
2. Inspect physical and mechanical condition.
3. Verify correct connection.
4. Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, verifying tightness of accessible bolted electrical connections by calibrated torque-wrench method.
5. Verify that required grounding and shorting connections provide good contact.
b. Electrical tests
1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable.
2. Perform insulation-resistance test.
3. Perform a polarity test.
4. Perform a ratio-verification test.
3.3.1.3 Potential Transformers
a. Visual and mechanical inspection
1. PT's are rigidly mounted.
2. PT's are correct voltage.
3. Verify that adequate clearances exist between primary and secondary circuit.
b. Electrical tests
1. Perform a ratio-verification test.
3.3.2 Follow-Up System Function Verification
Upon completion of acceptance checks and tests, the Contractor shall show by demonstration in service that circuits and devices are in good operating condition and properly performing the intended function. As an exception to requirements stated elsewhere in the contract, the Contracting Officer shall be given 5 working days' advance notice of the dates and times of checking and testing.
3.3.3 Training
The Contractor shall conduct a training course for meter configuration, operation, and maintenance of the system as specified. The training shall be oriented for all components and systems installed under this contract.
Training manuals shall be delivered for six trainees with two additional copies delivered for archiving at the project site. The
Contractor shall furnish all audiovisual equipment and all other training materials and supplies. A training day is defined as eight hours of classroom instruction, including two 15-minute breaks and excluding lunchtime, Monday through Friday, during the daytime shift in effect at the training facility. For guidance in planning the required instruction, the
Contractor shall assume that attendees have a high school education or equivalent, and are familiar with utility systems. Approval of the planned training schedule shall be obtained from the Government at least 30 days prior to the training.
a. Training: The course shall be taught at the project site within thirty days after completion of the installation for a period of one day. A maximum of six personnel will attend the course. The training shall include:
1. Physical layout of each piece of hardware.
2. Meter configuration, troubleshooting and diagnostics procedures.
3. Repair instructions.
4. Preventive maintenance procedures and schedules.
5. Testing and calibration procedures.
1.3 PROJECT COORDINATION
E. Construction Project Schedule: See contract, FAR 52.236-15 Schedules for Construction Contracts. The Contractor will not begin actual work until the construction project schedule has been approved by the Contracting Officer. The Contractor shall submit one electronic copy of the updated construction project schedule with each progress payment request.
F. Scheduling: The total contract period shall be 60 calendar days from the point of contract award. A period of 5 calendar days shall be allotted for the submittal, 5 calendar days for review and re-submit process. A period of 10 days shall be allotted for ordering materials. The work on-site shall be limited to one sixty (60) calendar days. The final inspection shall be scheduled a maximum of 43 calendar days from point of contract award, leaving 2 days for punch list remedies. The contractor shall submit a copy of his proposed schedule to the CO for approval. Please note that the shipping time line is 10 delivery time after approved submittals. The actual construction work period shall be 45 calendar days.
G. Contract Inspector’s Daily Report:
H. Contractor shall submit to the Contracting Officer a daily report listing the names of all those present on the job site each day, along with their Job Classification, hours of work and a brief description of the work performed by each on that day. The Contract Inspector’s Daily Report is to be submitted at the beginning of work each day for the previous day’s work and shall be maintained throughout the term of the contract.
I. Formal Meetings:
1. Any meeting (deemed formal by the contractor, the COR, or the Contracting Officer) will have the minutes of said meeting prepared by the contractor (and a copy provided to the Contracting Officer). The minutes will include: Date, Name of Attendees (with contact info), Old Business, and New Business subjects (or narratives). Regardless of who requests a meeting (the COR or the Contractor or the Contracting Officer) the contractor may be required to provided hard copy pictures of the issues to be discussed. Each issue will be linked to a contract specification section number and/or subject area by page number. Issues discussed will also include an action/completion date.
1.4 SAFETY SUBMITTALS
J. Contractor shall submit a "site specific" Safety Plan to the Contracting Officer that describes how the contractor is to comply with all applicable OSHA standards and NFPA codes pertaining to construction work to include, but not limited to: General Safety and Health Provisions, Occupational Health and Environmental Controls, Personal Protective and Life Saving Equipment, Hand and Power Tools, Welding and Cutting, Electrical, Scaffolds, Fall Protection, Excavations, Demolition, Stairways and Ladders, Toxic and Hazardous Substances, Confined Space Entry, Lockout/Tagout, Respiratory Protection, Hearing Protection. Safety Plan shall identify Contractor and sub-contractor employees who are authorized/qualified to perform electrical work. No work shall proceed until written approval of the Safety Plan by the Contracting Officer. Safety Plan shall describe how the Contractor and/or sub-contractors are to secure equipment, supplies, tools, and chemical products. Contractor and/or sub-contractor equipment, supplies, tools, and chemical products are to be under the control of the Contractor at all times, equipment, supplies tools, and chemical products found not to be under the control of the Contractor or sub-contractor are subject to confiscation and will be reported to the Contracting Officer.
K. The Contractor shall inspect the entire construction site daily, including days without construction work if there are NFPA 101 Life Safety Code deficiencies existing while construction work is shut down, the results of that inspection shall be documented on the attachment “DAILY INSPECTION FORM”, and the form is to be signed and submitted to the Contracting Officer.
L. Contractor shall provide continuous monitoring for noise, dust, chemical vapor generation, volatile organic compounds, and vibration. At no time shall noise exposure to any ARS staff exceed 75 dB. Contractor shall provide to the Contracting Officer a written weekly update of the all test results and also for proposed work for the subsequent two weeks (a two week “look-ahead”)involving any construction activity that will produce loud noises, heavy vibrations, strong smells, or significant dust inside ARS staff occupied space.
M. Contractor and sub-contractors shall notify in writing the Contracting Officer at least one week prior to executing high risk work (this may be included in the two week “look-ahead” update). High risk work includes, but is not limited to, tasks requiring Lockout/Tag Out, live electrical work, hot work, work at heights, trenching/ shoring, crane operations, and confined space entry. Contractor’s Competent Person shall provide the Contracting Officer written weekly documented safety inspection results.
N. Contractor shall provide to the Contracting Officer for approval, copies of Safety Data Sheets (SDS) for EVERY CHEMICAL WITHOUT EXCEPTION prior to bringing such chemical on the work site.
O. HOT WORK PERMITS:
1. The Contractor will not be permitted to work without this permit when performing hot work.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
P. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
Q. Contractor Personnel
1. Upon receipt of contract award, the Contractor shall provide information about applicable contract employees requiring routine physical access to the construction site, including that of all sub-contractors. Completion of the attached forms, additionally Form SF-87 fingerprint cards (2 sets), and successful completion of the background investigation are required before Contractor staff may enter the work site. All background investigation information shall be provided directly to:
ARS-NEA-BARC-Security-Access-Control@ars.usda.gov Or, Personnel Security Office
10300 Baltimore Ave
Beltsville, MD 20705
Each employee shall be furnished with a badge by the Government for access to construction site. This badge must be worn so as to be clearly visible at all times while on the work site.
R. Security Procedures:
1. Contractor’s employees shall not enter the project site without appropriate badges. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” as defined in the contract, The Contractor shall give a ten (10) day notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of ARS premises is allowed without written permission of the Contracting Officer.
4. ARS reserves the right to close down or shut down the project site and order the Contractor’s employees off the premises in the event of a national emergency or Government shutdown. The Contractor may return to the site only with the written approval of the Contracting Officer.
S. Document Control:
1. The Contractor is responsible for safekeeping of all drawings, project manuals and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. These documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
3. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the ARS.
T. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies and Contractor must be on site to receive all deliveries.
2. Separate permits shall be issued for Contractor and its employees for parking in designated areas only.
1.6 FIRE SAFETY
U. Applicable Publications: Publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2007 Surface Burning Characteristics of Building Materials
2. National Fire Protection Association (NFPA):
10-2013 Standard for Portable Fire Extinguishers
30-2015 Flammable and Combustible Liquids Code
51B-2014 Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2017 National Electrical Code
241-2013 Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926
Safety and Health Regulations for Construction
V. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to the Contracting Officer for review for compliance with contract requirements. Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, ARS safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of ARS equipment, etc. Documentation shall be provided to the Contracting Officer that individuals have undergone contractor’s safety briefing.
W. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
X. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 20 feet exposing overall length, separate by 10 feet.
Y. Temporary Construction Partitions: Install and maintain temporary construction partitions to provide smoke-tight separations between construction areas and adjoining areas. Construct partitions of gypsum board or treated plywood (flame spread rating of 25 or less in accordance with ASTM E84) on both sides of fire retardant treated wood or metal steel studs.
Z. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.
AA. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with Contracting Officer.
AB. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to the Contracting Officer.
AC. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA 241 and NFPA 10.
AD. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.
AE. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Provide fire watch for impairments more than 4 hours in a 24-hour period. Request interruptions in accordance with Article, OPERATIONS AND STORAGE AREAS, and coordinate with the Contracting Officer. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the Contracting Officer. Parameters for the testing and results of any tests performed shall be recorded by the General Contractor and copies provided to the Contracting Officer.
AF. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with the Contracting Officer.
AG. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Coordinate with the Contracting Officer. Designate contractor's responsible project-site fire prevention program manager to coordinate permit hot work. See Hot Work Permit below.
AH. Fire Hazard Prevention and Safety Inspections: Inspect entire construction area weekly. Coordinate with, and report findings and corrective actions weekly to the Contracting Officer.
AI. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
AJ. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily.
AK. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.
1.7 OPERATIONS AND STORAGE AREAS
AL. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
AM. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
AN. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
AO. Working space and space available for storing materials shall be as determined by the Contracting Officer.
AP. Workers are subject to rules of the Location applicable to their conduct which shall be provided by the Contracting Officer.
AQ. Execute work so as to interfere as little as possible with normal functioning of Location as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied during construction except as permitted by the Contracting Officer where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by the ARS in quantities sufficient for not more than two work days.
3. Where access by ARS personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment may be permitted subject to fire and safety requirements.
AR. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the ARS operations will not be hindered. Contractor shall permit access to ARS personnel through construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by ARS so that operations will continue during the construction period.
AS. When an unoccupied building is turned over to Contractor to complete construction as required, Contractor shall accept entire responsibility until contract completion.
AT. Utilities Services: Maintain existing utility services for ARS at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the Contracting Officer.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior written approval of the Contracting Officer. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Contracting Officer’s prior knowledge and written approval.
2. Contractor shall submit a request to interrupt any such services to the Contracting Officer, in writing, Two weeks advanced notice and again 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of ARS. Interruption time approved by ARS may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the Contracting Officer. It is the Contractor's responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the mitigating life safety measures to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
5. In case of a contract construction emergency, service will be interrupted on approval of the Contracting Officer. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
AU. To minimize interference of construction activities with flow of ARS traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads; walks and entrances must be approved by the Contracting Officer.
AV. Coordinate the work for this contract with other construction operations as directed by Contracting Officer. This includes the scheduling of traffic and the use of roadways, as specified in Article 1.14, USE OF ROADWAYS.
1.8 ALTERATIONS
AW. Survey: Before any work is started, the Contractor shall make a thorough survey with the Contracting Officer, of areas of the building in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed, to the Contracting Officer.
1. Shall note any discrepancies between drawings and existing conditions at site.
2. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and Contracting Officer.
1.9 DISPOSAL AND RETENTION
AX. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re‑installation and reuse. Store such items where directed by Contracting Officer.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from ARS property.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the ARS during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
AY. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
AZ. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
1.10 AS-BUILT DRAWINGS
BA. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
BB. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the Contracting Officer’s review, as often as requested.
BC. Contractor shall deliver two approved completed sets of as-built drawings to the Contracting Officer within 15 calendar days after each completed phase and after the acceptance of the project by the Contracting Officer.
BD. Paragraphs A, B, & C shall also apply to all shop drawings.
1.11 USE OF ROADWAYS
BE. For hauling, use only established public roads and roads on ARS property and, when authorized by the Contracting Officer, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the Contractor at Contractor's expense.
1.12 TEMPORARY TOILETS
BF. Provide for use of all Contractors’ workers ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when…
This is the start of the file's text. The full file is on GovTribe.