DOL WD AZ120037 07202012.doc

DOC document 41 KB Posted

Attached to
Asbestos Removal/Abatement Services
Solicitation number
12-247-SOL-00073
Issued by

About this file

Department of Labor Wage Determination

View the file

Other files

File Type Posted
Amendment No. Three.pdf PDF
Amendment No. Two.pdf PDF
Asbestos Report.pdf PDF
SF-30 Amend 1.pdf PDF
Attachment A.PDF PDF
Invitation Memo.PDF PDF
Standard Form 18.pdf PDF
Attachment B.PDF PDF
SOW Asbestos Abatement.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Decision Number: AZ120037 07/20/2012 AZ37

State: Arizona

Construction Type: Building

County: Maricopa County in Arizona.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Modification Number Publication Date

0 07/20/2012

ASBE0073-002 08/01/2011

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 37.76 11.92

BOIL0627-001 01/01/2012

Rates Fringes

BOILERMAKER......................$ 31.39 25.46

BRAZ0003-009 07/01/2010

Rates Fringes

BRICKLAYER.......................$ 24.62 4.57

CARP0408-009 07/01/2011

Rates Fringes

CARPENTER (Excludes

Acoustical Ceiling

Installation, Drywall

Finishing/Taping, Drywall

Hanging, Form Work, and Metal

Stud Installation)...............$ 23.00 8.49

CARP1327-001 07/01/2011

Rates Fringes

CARPENTER (Drywall Hanging

Only)............................$ 19.25 6.46

ELEC0640-005 06/21/2011

Rates Fringes

ELECTRICIAN (Includes Low

Voltage Wiring; Excludes

Installation of Alarms and

Sound and Communication

Systems).........................$ 25.01 3%+7.50

ENGI0428-012 01/01/2012

Rates Fringes

POWER EQUIPMENT OPERATOR:

(1) Oiler...................$ 19.89 9.34

(2) Crane under 15 tons.....$ 23.16 9.34

(3) Crane,15 tons to 100 tons, Tower Crane...........$ 24.24 9.34

(4) Crane, 100 tons and over........................$ 25.27 9.34

IRON0075-011 08/01/2011

Rates Fringes

IRONWORKER, STRUCTURAL AND

ORNAMENTAL.......................$ 26.52 19.35

Zone 1: 0 to 50 miles from City Hall in Phoenix or Tucson

Zone 2: 050 to 100 miles - Add $4.00

Zone 3: 100 to 150 miles - Add $5.00

Zone 4: 150 miles & over - Add $6.50

LABO0383-005 10/01/2011

Rates Fringes

LABORER (MASON TENDER-BRICK).....$ 15.00 4.10

PAIN0086-006 04/01/2012

Rates Fringes

DRYWALL FINISHER/TAPER

ZONE A......................$ 19.00 5.03

ZONE B......................$ 22.50 5.03

ZONE PAY:

ZONE A: Free Zone: A distance of 0 to 100 miles from the old

Phoenix courthouse.

ZONE B: A distance of 101 miles and over from the old Phoenix courthouse: $3.50 per hour over ZONE A

PLAS0394-001 07/01/2011

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 22.84 8.57

PLUM0469-002 07/01/2011

Rates Fringes

PLUMBER/PIPEFITTER

Zone A......................$ 32.50 15.15

SFAZ0669-001 04/01/2012

Rates Fringes

SPRINKLER FITTER (Fire

Sprinklers)......................$ 29.53 18.42

SHEE0359-002 07/01/2012

Rates Fringes

SHEET METAL WORKER: (HVAC

Duct Installation Only)

Zone 1......................$ 30.42 14.82

SUAZ2012-020 05/30/2012

Rates Fringes

ACOUSTICAL CEILING MECHANIC......$ 21.14 3.14

CARPENTER (Form Work Only).......$ 19.67 5.45

CARPENTER (Metal Stud

Installation)....................$ 16.23 0.00

CAULKER..........................$ 16.01 0.00

ELECTRICIAN (Alarm

Installation)....................$ 18.31 4.68

ELECTRICIAN (Installation of

Sound and Communication

Systems).........................$ 17.20 2.87

FIREPROOFER......................$ 15.00 0.00

GLAZIER..........................$ 18.67 1.44

INSTALLER - SIGN.................$ 19.16 3.58

INSULATOR - BATT.................$ 11.96 3.06

IRONWORKER, REINFORCING..........$ 14.92 0.00

LABORER: Asphalt Raker..........$ 15.18 1.30

LABORER: Common or General......$ 13.80 2.24

LABORER: Concrete Saw (Hand

Held/Walk Behind)................$ 21.00 7.37

LABORER: Fence Erection.........$ 19.73 0.00

LABORER: Landscape &

Irrigation.......................$ 11.33 0.43

LABORER: Mason Tender -

Cement/Concrete..................$ 15.24 3.90

LABORER: Pipelayer..............$ 15.10 0.85

LABORER: Plaster Tender.........$ 12.00 0.00

LABORER: Power Tool Operator....$ 14.85 4.20

LATHER...........................$ 16.15 0.00

MASON - STONE....................$ 18.48 0.82

MILLWRIGHT.......................$ 20.00 2.87

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 19.20 2.47

OPERATOR: Bulldozer.............$ 21.12 6.14

OPERATOR: Drill Rig Caissons....$ 19.06 2.39

OPERATOR: Drill.................$ 19.16 0.00

OPERATOR: Forklift..............$ 17.36 0.00

OPERATOR: Grader/Blade..........$ 21.00 7.07

OPERATOR: Loader (Front End)....$ 18.55 0.95

OPERATOR: Paver.................$ 21.09 3.96

OPERATOR: Roller................$ 25.00 0.00

OPERATOR: Scraper...............$ 21.41 0.00

OPERATOR: Screed................$ 22.17 4.42

OPERATOR: Trencher..............$ 15.01 0.58

PAINTER: Brush, Roller, Spray and Steel..................$ 16.53 2.63

PLASTERER........................$ 16.71 0.00

ROOFER, Includes

Waterproofing, and

Installation of Metal Roofs......$ 16.71 1.67

SHEET METAL WORKER, Excludes

HVAC Duct Installation...........$ 18.85 2.79

TERRAZZO WORKER/SETTER...........$ 21.13 0.00

TILE FINISHER....................$ 12.50 0.00

TILE SETTER......................$ 15.00 0.00

TRUCK DRIVER: Dump Trucks.......$ 15.55 1.42

TRUCK DRIVER: Pickup Truck......$ 11.00 0.87

TRUCK DRIVER: Water Truck.......$ 17.72 4.21

TRUCKDRIVER: 3 and 4 Axle.......$ 19.29 1.36

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be

July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rate.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007

5/13/2010. SU indicates the rates are not union rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

File details come from the government source that posted it. Updated .