OMB Control No. 2120-0595 (SF-30) FAA Template No. 11 (Reverse) (8/97)
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY 7. ADMINISTRATED BY (If other than Item 6)
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
*TO BE COMPLETED BY VENDOR IF NOT COMPLETE 10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended is not extended.
NOTE: If offers are handcarried, additional time should be allowed to access the depository facility due to heightened security requirements.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Item 8 and 15, and returning 1 copies of the amendment; (b) acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hours and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO.
AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return ___ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign)
BY
(Signature of Contracting Officer)
1. The purpose of Amendment 02 is to correct a typo on Page 3 of the Schedule of Items. The correct building number is highlighted on Line Item No. 10.
2. The closing date/time in Amendment 01 remains unchanged.
3. All other terms and conditions remain unchanged.
B.1 SCHEDULE OF ITEMS (Cont’d)
OPTION A ITEMS:
ITEM EST PAY UNIT TOTAL
NO. DESCRIPTION QTY UNIT PRICE PRICE
07 Demolition of D4 Bldg #2871 1.00 LS $_________ $_________ Hay Storage/Tack Room, recycle all metal and other recyclable materials
08 Asbestos materials remediation: 1.00 LS $_________ $_________ Remove and dispose of beige and light green window putty containing asbestos
09 Lead based paint disposal: 1.00 LS $_________ $_________ Dispose of window frames in tacked and in accordance with LBP disposal requirements
10 LS $_________ $_________ Site Reclamation for Bldg. #2871, 1.00 includes but not limited to erosion control, fill, top soil, & native seeding
Option A Subtotal Price: $_______________
OPTION B ITEMS:
ITEM EST PAY UNIT TOTAL
NO. DESCRIPTION QTY UNIT PRICE PRICE
11 Demolition of D5 Bldg #2827 1.00 LS $_________ $_________ Radio Bldg, Salmo Mtn, bldg base & 1 battery
12 Demolition of D5 Bldg #2840 1.00 LS $_________ $_________ Radio Bldg, Sullivan Mtn, portable bldg.
13 Demolition of D5 Bldg #2866 1.00 LS $_________ $_________ Mt. Leona Radio bldg. base
14 Demolition of prefabricated 1.00 LS $_________ $_________ Fiberglas shelter located at
SO office compound.
Option B Subtotal Price: $_______________
RFQ No. 1205M620Q0021 Forest Wide Buildings Demolition Page 3 of 184
Colville National Forest Firm-Fixed-Price (FFP) Service Stand-Alone Contract bajohnson03 Highlight
| Untitled |
| Untitled |
| Untitled |
| 1 CONTRACT ID CODE: |
| PAGE: 1 |
| OF PAGES: 2 |
| 6 ISSUED BY: 02 |
| 3 EFFECTIVE DATE: 5/29/2020 |
| 7: 995053 |
| 5 PROJECT NO If applicable: |
| 6 ISSUED BY_2: USDA Forest Service |
Attn: Brian A. Johnson, CO Mt. Baker-Snoqualmie National Forest 2930 Wetmore Ave., Ste 3A Everett, WA 98201-4067
| 7 ADMINISTRATED BY If other than Item 6: Same as Block 6 | |
| 10A: 3/26/2020 | |
| 10A MODIFICATION OF CONTRACTORDER NO: | |
| 10B DATED SEE ITEM 13: | |
| extended: On | |
| is not extended: Off | |
| undefined_4: | |
| B: | |
| undefined_5: | |
| undefined_6: | |
| C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: | |
| E IMPORTANT Contractor: | |
| undefined_7: | |
| is not: Off | |
| is required to sign this document and return: Off | |
| 15B CONTRACTOROFFEROR: | |
| 16B UNITED STATES OF AMERICA: Brian A. Johnson, Contracting Officer | |
| 15C DATE SIGNED: | |
| 2020-05-29T08:16:02-0700 | |
| BRIAN JOHNSON |
| 16C DATE SIGNED: 5/29/2020 |
| Text1: 1205M620Q0021 |
| Check Box2: Yes |
| Check Box3: Off |
| The above numbered solicitation is amended as set forth in Item 14 The hour and date specified for receipt of Offer is: On |
| Text4: |
| Text5: FOREST WIDE BUILDINGS DEMOLITION |
Colville National Forest Washington State