Questions and Answers No. 2_Q0098.pdf

PDF 669 KB Posted

Attached to
BITTERROOT NATIONAL FOREST - Rock Creek Trail Bridge Replacement Federal contract opportunity
Solicitation number
12034320Q0098
Issued by
Department of Agriculture Forest Service R1-Northern Region

View the file

Other files for this federal contract opportunity

Other files attached to BITTERROOT NATIONAL FOREST - Rock Creek Trail Bridge Replacement, newest first.
File Type Posted
Amendment 1 Changes and QA Q0098.pdf PDF
Attach J-1 WD MT20200079_Q0098.pdf PDF
Attach J-4 Rock Creek Trail Bridge Drawings_Q0098.pdf PDF
Attach J-2 Rock Creek Experience Questionnaire_Q0098.pdf PDF
Rock Creek Trail Bridge RFQ_12034320Q0098.pdf PDF
Attach J-3 Rock Creek Trail Bridge_580-3.0_FSSS_Q0098.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION 12034320Q0098

ROCK CREEK TRAIL BRIDGE REPLACEMENT PROJECT

QUESTIONS AND ANSWERS #2

The Following questions have been received via email:

1. Question: I was looking for a weight load limit of the current condition of the bridge? And to make sure it hasn’t been de-rated.

Answer: The bridge is a pack/pedestrian bridge. There are no restrictions for packing and pedestrian use. It doesn't have a load rating like a highway bridge.