12010918R0004Amd1.pdf
PDF 70 KB Posted
- Solicitation number
- 12010918R0004
About this file
Not Listed
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12010918R0004Amd2.pdf | ||
| Bridge_Pics.pdf | ||
| 12010918R0004HoonahBridgeReplace.pdf | ||
| FSSS_Hoonah_2018_(85761,_8508,_8510).pdf | ||
| HRD_Bridge_2018_(85761,_8508,_8510).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 3
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
May 3, 2018 905213
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
Tongass National Forest 123 Scow Bay Loop Road PO Box 309 Petersburg, AK 99833
Same as block 6
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
12010918R0004 2018 Hoonah Bridge Replacements (85761, 8508, 8510)
9B. DATED (SEE ITEM 11)
3May2018
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
Reference: Page 6 of 28, SECTION C--DESCRIPTION/SPECIFICATIONS, C.2 Description, h. Remove 30’ steel bridge on road 8510, see Table 1.
Change paragraph h. to read: h. Remove 30’ steel bridge on road 8508, see Table 1.
Reference: Page 21 of 28, SECTION J--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS, change Contruction Plans from: Culvert Replacement NFSR 2050050 MP 0.82 to 2018 Hoonah Bridge Replacements (85761, 8508, 8510).
Reference: Construction Plans: Culvert Replacement NFSR 2050050 MP 0.82. Replace tables on sheets 3 and 4 with attached tables WORK DETAILS, Amendment 1, 3May2018 and SUMMARY OF ESTIMATED QUANTITIES, Amendment 1, 3May2018, Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Kim Toland, Supervisory Contract Specialist Officer
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
May 3, 2018 (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
WORK DETAILS, Amendment 1, 3May2018 Base Option
85761 MP 0.053 8508 MP 13.172 8510 MP 9.226
ROAD
NUMBER: 85761 ROAD
NUMBER: 8508 ROAD
NUMBER: 8510
PROJECT
MILEPOST: 0.053 PROJECT
MILEPOST: 13.172
PROJECT
MILEPOST
9.226
MILEPOST WORK DESCRIPTION MILEPOST WORK DESCRIPTION MILEPOST WORK DESCRIPTION
0.053
REMOVE EXISTING 50' LOG
STRINGER BRIDGE, BACKWALLS,
SILLS AND ALL ASSOCIATED
HARDWARE. PLACE LOGS AT A
LOCATION DESIGNATED BY THE
COR. DISPOSE OF ALL GEOTEXTILE
FABRIC, HARDWARE AND CABLE AT
APPROPRIATE LOCATION OFF NFS
LANDS.
13.172
REMOVE EXISTING 30' STEEL BRIDGE,
BACKWALLS, SILLS AND ALL
ASSOCIATED HARDWARE. INVENTORY
ALL BRIDGE PIECES AND
HARDWARE. STORE BRIDGE PARTS
AT LOCATION DETERMINED BY
COR. ANY DAMAGED OR MISSING
ITEMS SHALL BE REPLACED BY THE
CONTRACTOR, NO ADDITIONAL
PAYMENT SHALL BE MADE.
9.226
REMOVE EXISTING 30' LOG STRINGER
BRIDGE, BACKWALLS, SILLS AND ALL
ASSOCIATED HARDWARE. PLACE
LOGS AT A LOCATION DESIGNATED
BY THE COR. DISPOSE OF ALL
GEOTEXTILE FABRIC, HARDWARE
AND CABLE AT APPROPRIATE
LOCATION OFF NFS LANDS.
BRIDGE TO BE INSTALLED IS
CURRENTLY STORED AT THE FOREST
SERVICE OWNED THORNE BAY
SORTYARD. CONTRACTOR IS
RESPONSIBLE FOR
TRANSPORTATION OF BRIDGE TO
HOONAH ROAD SYSTEM. REMOVE
BRIDGE AND ALL ASSOCIATED
HARDWARE FROM THE CURRENT
LOCATION AND TRANSPORT TO
INSTALLATION SITE.
BRIDGE TO BE INSTALLED IS
CURRENTLY STORED AT THE FOREST
SERVICE OWNED THORNE BAY
SORTYARD. CONTRACTOR IS
RESPONSIBLE FOR TRANSPORTATION
OF BRIDGE TO HOONAH ROAD
SYSTEM. REMOVE BRIDGE, SILLS,
BACKWALLS AND ALL ASSOCIATED
HARDWARE FROM THE CURRENT
LOCATION AND TRANSPORT TO
INSTALLATION SITE.
AQUIRE CULVERT FROM
MANUFACTURER BASED ON PROJECT
SPECIFICATIONS. FACILITATE
TRANSPORATION TO
HOONAH. TRANSPORT CULVERT
FROM HOONAH DOCKS TO WORK
SITE.
PREPARE INSTALLATION SITE, ROAD
APPROACHES, AND ASSOCIATED
WORK ITEMS AS SHOWN ON THE
DRAWINGS. PERFORM ALL WORK
NECESSARY FOR THE PLACEMENT
AND INSTALLATION OF THE
BRIDGE. TRANSPORT AND INSTALL
70' STEEL BRIDGE AND THRIE BEAM
GUARDRAIL. SEE DRAWINGS FOR
DETAILS. FABRICATE, DELIVER AND
INSTALL TIMBER SUBSTRUCTURE.
PREPARE INSTALLATION SITE, ROAD
APPROACHES, AND ASSOCIATED
WORK ITEMS AS SHOWN ON THE
DRAWINGS. PERFORM ALL WORK
NECESSARY FOR THE PLACEMENT
AND INSTALLATION OF THE
BRIDGE. TRANSPORT AND INSTALL 40'
GLULAM SLAB BRIDGE.
PREPARE INSTALLATION SITE, ROAD
APPROACHES, AND ASSOCIATED
WORK ITEMS AS SHOWN ON THE
DRAWINGS. PERFORM ALL WORK
NECESSARY FOR THE PLACEMENT
AND INSTALLATION OF THE
CULVERT. SEE DRAWINGS FOR
DETAILS.
FURNISH MATERIALS AND INSTALL
MODIFIED THRIE BEAM
GUARDRAIL. SEE DRAWINGS FOR
DETAILS.
INSTALL APPROACH RAILS. INSTALL APPROACH RAILS.
INSTALL FOUR (4) OBJECT MARKERS
AND POSTS AT BRIDGE ENDS.
INSTALL FOUR (4) OBJECT MARKERS
AND POSTS AT BRIDGE ENDS.
SUMMARY OF ESTIMATED QUANTITIES, Amendment 1, 3May2018
ITEM NO. DESCRIPTION PAY UNIT
BASE BID OPTION
All 85761
MP 0.053
MP
13.172
MP 9.226
15101 Mobilization Lump Sum 1
15102 Transport two government furnished bridges from Thorne Bay Sortyard to work sites on Hoonah road system
Lump Sum 1
15201 Construction Survey and Staking, Method 1, Tolerance A Each 1 1 1
20301 - 50 Bridge removal - 50' log stringer Lump Sum 1
20301 - 30S Bridge removal, transport and storage- 30' Steel Bridge Lump Sum 1
20301 - 30T Bridge removal - 30' Log Stringer Bridge Lump Sum 1
20401 Excavation CY 170 130 30
20404 Borrow, Unclassified - Cat finish, Compaction Method D, Finishing Method C, Includes Haul CY 100 415
25101-4 Placed Rip Rap, Class 4 CY 100 80 40
30103 Crushed Aggregate, Type Base, Grading C, Compaction B CY 50 20 25 57102 - Rd 85761
Local Transport and Installation of 70' Steel Girder Bridge and rails. Government Furnished Each 1
57102 - Rd
Local Transport and Installation of 40' Glulam Slab Bridge, Sills, Backwall. Government Furnished Each 1
57104 Modify Government furnished guard rails on Glulam Slab Bridge. Lump Sum 1
57105 Prefabricated bridge substructure. Fabricate, deliver and install. Lump Sum 1
57106 Furnish and Install approach rails. Each 1 1 60201-Rd 8510 Furnish, Transport and Install 60" Corrugated Metal Pipe LF 45
62507 Seeding, Dry method (without mulch) Acre 0.5 0.5 0.5
63306 Object Markers Each 4 4