100 percent Drawings Compiled 2023 03 24.pdf
PDF 17 MB Posted
- Solicitation number
- 36C25023B0054
About this file
This document provides details on a federal contract opportunity from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10 for bathroom deficiency remediation project number 539-22-207. The solicitation number is 36C25023B0054 and seeks bids to complete bathroom repairs and upgrades at a VA facility. Key requirements include addressing deficiencies in bathrooms through activities such as plumbing repairs and replacements, fixture replacements, and accessibility upgrades. The project scope and related 100 percent drawings are available for review in the attached 17MB PDF file. The response due date and anticipated award date are not specified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25023B0054 0001.docx | DOCX document | |
| BID SUBMISSION.docx | DOCX document | |
| Abstract of Bids Bathroom Deficiency Remediation.pdf | ||
| 36C25023B0054_1.pdf | ||
| Attachment III - VHA Directive 1192.01.pdf | ||
| Attachment V - RFI Form.pdf | ||
| Attachment I - WD DBA.pdf | ||
| Attachment II - Limitation on Subcontracting Cert.pdf | ||
| Attachment IV - EMR Form.pdf | ||
| 100 percent Specs Compiled 03 24 23 RE 03 27 23.pdf | ||
| 36C25023B0054_1.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UP
DN
UP
UP
UP UP
UP
UP
DN
UP
UP
DN
UP
UP
UP
DN
UP
UP
UP
DN
UP
DN
UPDN
UP
DN
UP
UP
UP
UP
EXTERIOR ELEVATION
INTERIOR ELEVATION
SECTION/DETAIL NUMBER
DRAWING NUMBER
EQUIPMENT TAG
COLUMN GRID
NOTE
WINDOW OPENING
DOOR OPENING
ROOM NAME
ROOM NUMBER
WALL TYPE
CEILING HEIGHT
FINISH DESIGNATION
X
10'-8"
X
X
XX.X-X
XX
X
1/A101
X
A101
XX
TOILET ACCESSORY TAGX SIGNAGE TAG
A101
SIM
X
Ludlow Ave.
C lif to n A v e
CINCINNATI
STATE
TECH.
Hopple St.
M.L.K. Dr.
McMillan St.
UNIV. OF
CINCINNATI
W.H.T Rd.
VAMC
3200 VINE ST.
M.L.K. Dr.
V in e
S t.
ZOO
Jefferson A ve.
UNIV.
HOSPITAL
Mitchell Ave.
R ea di ng
R d.
V ic to ry
P kw
y. XAVIER
UNIV.
PHASE 2
AREA OF WORK
(Bid Item #4- Delete Phase 2 Work) A004C - Men Toilet A004D - H.A.C.
A004E - Women Toilet
PHASE 3
AREA OF WORK
B010 - Men Toilet
B008 - Unisex Toilet
PHASE 1
AREA OF WORK
A025 - H.A.C.
A026 - Men Toilet A026A - Women Toilet A026B - Locker Room
(Bid Item #3- Delete Work in Room B008)
(Bid Item #2- Delete Lockers)
(Bid Item #2- Delete Lockers)
(Bid Item #2- Delete Lockers)
JASON
H.
ROSS
2118221
IO
HO
FOET
A T
S
R E G I S
E T
R
ED RA
C H
TI
E C T
VA Project No.
RDC/JPA Project No.
Department of Veterans Affairs Medical Center
HEAPY ENGINEERING
MECHANICAL ELECTRICAL COMMISSIONING TECHNOLOGY
1400 WEST DOROTHY LANE
DAYTON, OH 45409
937.224.0861 P
ARCHITECTURE PLANNING INTERIOR DESIGN
524 FERNWOOD AVENUE
ALTAMONTE SPRINGS, FLORIDA 32701
407.830.6522 P
RDC / JOHN POE ARCHITECTS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
TERRACON CONSULTING, INC.
ENVIRONMENTAL
611 LUNKEN PARK DRIVE
CINCINNATI, OH 45226
513.321.5816 P
/2
/2
:0
:4
P
M
VA Cincinnati Bathroom Deficiency Remediation
03/24/2023
COVER SHEET
G001
JWKR
539-22-207
Cincinnati, OH
VA Cincinnati Bathroom Deficiency Remediation
3200 Vine Street Cincinnati, OH 45220 PROJECT #: 539-22-207
Kristina Amin
100% Bid Documents 22034.00
G001 COVER SHEET
G100 CODE DATA - BASEMENT
A101 NEW WORK PLAN - PHASE 1
A102 NEW WORK PLAN - PHASE 2
A103 NEW WORK PLAN - PHASE 3
A311 WALL SECTIONS
A401 INTERIOR ELEVATIONS
A402 INTERIOR ELEVATIONS
A601 SCHEDULES, SECTIONS & DETAILS
F001 ABBREVIATIONS, LEGEND & DRAWING INDEX
P001 ABBREVIATIONS, LEGEND & DRAWING INDEX
FX100 PARTIAL FLOOR PLANS - FIRE SUPPRESSION
PP101 NEW WORK PLANS - PHASE 1
PP102 NEW WORK PLANS - PHASE 2
PP103 NEW WORK PLANS - PHASE 3
P601 SCHEDULES, DETAILS & SWV DIAGRAMS
P602 DOMESTIC WATER DIAGRAMS
M001 ABBREVIATIONS, LEGEND & DRAWING INDEX
MD100 PARTIAL BASEMENT PLANS - REMOVALS
MH100 PARTIAL BASEMENT PLANS - NEW WORK
M501 SCHEDULES & DETAILS
E001 ABBREVIATIONS, LEGEND & DRAWING INDEX
ED100 PARTIAL BASEMENT PLANS - REMOVALS
EE100 PARTIAL BASEMENT PLANS - NEW WORK
E601 SCHEDULES & DIAGRAMS
E602 PANEL SCHEDULES
GENERAL CONSTRUCTION NOTES
7. CONTRACTOR IS RESPONSIBLE TO VERIFY SIZES OF ALL EQUIPMENT, ETC. TO
BE INSTALLED AS PART OF THIS PROJECT, AND WHERE NECESSARY, MAKE
SPECIAL PROVISIONS TO INSTALL EQUIPMENT THAT IS TOO LARGE TO FIT
THROUGH FINISHED OPENINGS.
8. CONTRACTOR SHALL PROVIDE WOOD BLOCKING AT TOILET ACCESSORIES,
HAND RAILS, BUMPER RAILS, SHELVING, CASEWORK, MOUNTING BRACKETS
AND OTHER WALL MOUNTED ITEMS, AS INDICATED IN THE CONTRACT
DOCUMENTS AND AS RECOMMENDED BY PRODUCT MANUFACTURERS. ALL
WOOD BLOCKING SHALL BE FIRE RETARDANT TREATED.
9. ALL EXPOSED NEW WORK IS TO RECEIVE NEW FINISHES UNLESS
SPECIFICALLY NOTED OTHERWISE. iF NO FINISH IS INDICATED AT A
PARTICULAR SURFACE, CONTRACTOR SHALL PROVIDE FINISH(S) AS
INDICATED AT SIMILAR CONDITIONS.
10. CONTRACTOR SHALL PROVIDE COMPLETE AND FULLY OPERATIONAL
SYSTEMS WHICH COMPLY WITH STATED CODES AND REGULATIONS. WHERE
THE OMISSION OF A PART OR ELEMENT OF A SYSTEM WOULD RESULT IN THE
NON-OPERATION, OR INCORRECT OPERATION OF A SYSTEM, CONTRACTOR
SHALL INCLUDE SAID PART OR ELEMENT AS PART OF THE WORK.
11. ALL PENETRATIONS THROUGH NEW AND/OR EXISTING SMOKE OR FIRE RATED
WALLS SHALL BE SMOKE/FIRE STOPPED AS REQUIRED BY THE RATING OF
THE WALL.
12. FIRE PROTECTION CONTRACTOR'S SPRINKLER DESIGN WILL BE SUBJECT TO
AN INDEPENDENT REVIEW BY A CERTIFIED FIRE PROTECTION ENGINEER
RETAINED BY THE OWNER. THE FIRE PROTECTION CONTRACTOR IS
RESPONSIBLE FOR MAKING ANY REQUIRED CHANGES TO THE DESIGN AS
IDENTIFIED BY THE OWNER'S FIRE PROTECTION ENGINEER AS NECESSARY
FOR COMPLIANCE WITH SPECIFIED NFPA REQUIREMENTS.
* PLEASE NOTE THAT THE TERM PROJECT ENGINEER REFERS TO THE
CONTRACTING OFFICER'S REPRESENTATIVE (C.O.R.).
1. ALL WORK SHALL COMPLY WITH THE LATEST NFPA 101 LIFE SAFETY CODE,
INTERNATIONAL BUILDING CODE, AND OTHER COES AS IDENTIFIED IN VHA
PROGRAM GUIDE PG-18-3, TOPIC 01, CODES, STANDARDS AND EXECUTIVE
ORDERS WHICH CAN BE FOUND ON THE DEPARTMENT OF VETERAN AFFAIRS,
TECHNICAL INFORMATION LIBRRARY WEBSITE.
2. ALL WORK SHALL COMPLY WITH REQUIREMENTS OF THE LATEST
ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARD (ABAAS) AND
DEPARTMENT OF VETERANS AFFAIRS BARRIER FREE DESIGN GUIDE PG-18-13
WHICH CAN BE FOUND ON THE DEPARTMENT OF VETERANS AFFAIRS
TECHNICAL INFORMATION LIBRARY WEBSITE.
3. CONTRACTOR IS RESPONSIBLE TO VISIT THE SITE, EXAMINE AND ACCEPT
EXISTING CONDITIONS PRIOR TO BIDDING. SITE VISITS TO BE COORDINATED
WITH THE CONTRACTING OFFICER'S REPRESENTATIVE.
4. CONTRACTOR IS RESPONSIBLE TO REPAIR AND/OR REFINISH, TO MATCH
ADJACENT EXISTING SURFACES, ANY EXISTING MATERIALS TO REMAIN THAT
ARE DAMAGED DURING THE COURSE OF DEMOLITION OR NEW WORK.
5. WHERE REMOVAL OF EXISTING WORK IS REQUIRED FOR INSTALLATION OF
NEW WORK, CONTRACTOR SHALL REPAIR EXISTING CONSTRUCTION TO
REMAIN OR PROVIDE NEW CONSTRUCTION TO MATCH EXISTING ADJACENT
SURFACES TO REMAIN.
6. CONTRACTOR IS RESPONSIBLE TO FIELD VERIFY ALL CONDITIONS AND
DIMENSIONS PRIOR TO ORDERING, FABRICATING OR INSTALLING NEW
MATERIALS.
DRAWING INDEX
GRAPHIC SYMBOLS
N.T.S.Scale:
VICINITY MAP
KEYPLAN - Basement
Revisions Date
1 95% Resubmittal 03/09/2023
0-HR Smoke Partition - [OBC 710] / NFPA 101-8.4
1/2-HR Smoke Barrier - [OBC 710] / NFPA 101-8.4
1-HR Smoke Barrier - [OBC 709] / NFPA 101-8.5
2-HR Smoke Barrier - [OBC 709] / NFPA 101-8.5
1-HR Fire Barrier - [OBC 706] / NFPA 101-8.3
2-HR Fire Barrier - [OBC 706] / NFPA 101-8.3
Hazardous Area
Means of Egress
Existing Wall to Remain
New Wall
Emergency Lighting
Fire Extinguisher
Exit Sign
Exit
Suite Designation
CODE LEGEND
EX
PHASE 3:
B008 -Unisex Toilet B010 - Men Toilet/Shower
PHASE 1:
A025 - H.A.C.
A026 - Men Toilet A026A - Women Toilet/Shower A026B - Locker Room
PHASE 2:
A004C - Men Toilet/Shower A004D - H.A.C.
A004E - Women Toilet/Shower
JASON
H.
ROSS
2118221
IO
HO
FOET
A T
S
R E G I S
E T
R
ED RA
C H
TI
E C T
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:0
:5
P
M
VA Cincinnati Bathroom Deficiency Remediation
03/24/2023
CODE DATA - BASEMENT
G100
JWKR
539-22-207
Cincinnati, OH
Kristina Amin
100% Bid Documents 22034.00
N Scale: 1/16" = 1'-0"
B01 - BASEMENT - Life Safety Plan
Code: NFPA 101 Life Safety Code (2021 Edition)
Construction Type: Type II (222)
Occupancy: Health Care Occupancy
Area of Work: 1,409 SF - VA Cincinnati Bathroom Deficiency Remediation
Protection: Fully Suppressed
Chapter 4 - General
• 4.4.2.2 -Prescriptive-based life safety design meeting the requirements of Chapters 1 thru 3, Sections 4.5 thru 4.8, and
Chapters 6 thru 43 of this Code shall be deemed to satisfy the provisions of Sections 4.1 and 4.2.
• 4.4.2.3 -Where req’ts in Chapters 11 thru 43 differ from req’ts in Chapters 1 thru 4 and 6 thru 10, the req’ts of Chapters 11 thru 43 shall govern.
• 4.6.1.1 -The authority having jurisdiction (AHJ) shall determine whether the provisions of this Code are met.
• 4.6.7.1 -Rehabilitation category per 43.2.2.1.2 Renovation.
Chapter - 6 Classification of Occupancy and Hazard of Content
• 6.1.5 - Health Care Occupancy - (No Change)
• 6.2.2.1 -Hazard classification = Ordinary - (No Change)
Chapter 7 - Means of Egress
• 7.1.3.1 - Exit Access Corridors: 1/2 hr. fire rating is required for corridor walls per 19.3.6.2.2
• 7.3.1.2 – Occupant Load:
Basement Floor (Renovation):
HC - Inpatient treatment Dept: 994 sf @ 240 sf/occ = 5 occup (NO CHANGE in area or occupant load) Storage: 145 sf @ 300 sf/occ = 1 occup (NO CHANGE in area or occupant load) Total: 1,139 sf
Chapter 8 - Features of Fire Protection:
• Table 8.3.3.2.2 – Min Fire Protection for Openings in Fire-rated Assemblies:
Component Walls Fire Drs Vision Panel (size) FR Vision Panel FR Window Vert. shafts 2 hr 1-1/2 hr Max tested D-H-90 NP (stairs, exits):
Fire Barriers: 2 hr 1-1/2 hr Max tested D-H-90 NP
1 hr 3/4 hr Max tested D-H-45 3/4 hr Smoke Barriers: 1 hr 1/3 hr Max tested D-20 3/4 hr
1/2 hr 1/3 hr Max tested D-20 1/3 hr Smoke Part'ns: 1 hr 1/3 hr Max tested D-20 3/4 hr
1/2 hr 1/3 hr Max tested D-20 1/3 hr
• 8.3.4.2.1 – Firestop Systems – Penetrations that pass thru a fire barrier shall be protected by a firestop system or device.
• 8.3.4.2.2 – The firestop system or device shall be tested in accordance with ASTM E814 or UL 1479.
• 8.3.4.8 – Openings thru fire barriers for air-handling ductwork or air movement shall be protected per 9.2.1.
• 8.4.1 - Smoke Partitions shall limit the transfer of smoke.
• 8.5.1 - Smoke Barriers shall restrict the transfer of smoke and have 1/2 hour fire resistance rating per 19.3.7.3 (1 hour provided).
• 8.5.3 - Fire Barriers that meet requirements of Section 8.5 shall be permitted to be used as a smoke barrier.
Chapter 9 - Building Service and Fire Protection Equipment
• 9.6.1.3 – Fire Alarm System req’d for life safety shall be per NFPA 70 (2020) and 72 (2019).
• 9.7.1.1 – Supervised automatic sprinkler system as req’d by 9.7.1 and 19.3.5.3 and shall comply with NFPA 13 (2019).
Chapter 10 – Interior Finish, Contents, and Furnishings
• 10.2.2- Interior Finish Classification Limitations
Table A.10.2.2 - Interior Finish Classification Limitations: Health Care (Existing) Exit Access Corridors: Class A or B.
Other Spaces: Class A or B.
• 10.2.3.1.1 - Interior wall and ceiling finish materials shall be classified in accordance with NFPA 286 and comply with 10.2.3.2.
• 10.2.3.1.2 - Materials tested in accordance with 10.2.3.1.1 and complying with 10.2.3.2 shall also be considered to comply with the requirements of Class A in accordance with 10.2.3.3.
• 10.2.3.3 – Wall and Ceiling – Classifications characteristics:
(1) Class A: Flame spread: 0-25; Smoke dev.: 0-450.
(2) Class B: Flame spread: 26-75; Smoke dev.: 0-450.
(3) Class C: Flame spread: 76-200; Smoke dev.: 0-450.
• 10.2.3.3.1 – Existing interior finish exempt from smoke dev. criteria.
• 10.2.7.2 – Floor finish other than carpet: Min. Rad flux: .1 W/ cm².
• 10.2.8.1 – Wall and Ceiling finishes, where sprinkled:
Class C permitted in any location where Class B is req’d.
Class B permitted in any location where Class A is req’d.
• 10.2.8.2 – Floor finishes, where sprinkled:
Class II permitted in any location where Class I is req’d.
Provisions of 10.2.7.2 shall apply where Class II is req’d.
Chapter 19 - Existing Health Care Occupancies
• 19.1.1.1.4 - The area of work is an existing hospital and therefore falls under Chapter 19.
• 19.1.1.4.3.1 - For the purpose of the provisions of this chapter the following shall apply:
1. A minor rehabilitation shall involve the modification of not more than 50%, and not more than 4,500 s.f. of the area of the smoke compartment.
• 19.1.6.1 - Construction Type Limitations (Table 19.1.6.1): Type II (222), sprinklered, no story limitations. (No Change)
• 19.1.7 - Occupant Load per Table 7.3.1.2. (NO CHANGE)
• 19.3.4.1 - Health care occupancies shall be provided with a fire alarm system per Section 9.6.
• 19.3.5.3 - Building containing hospitals shall be protected throughout by approved, supervised automatic sprinkler systems per Section 9.7.
• 19.3.6.2.2 - Corridor walls shall have min. 1/2 hour fire resistance rating. (NO CHANGE)
• 19.3.6.2.3 - Corridor walls shall form a barrier to limit the transfer of smoke but are not required to be smoke barriers or smoke partitions.
• 19.3.6.3.1 - Corridor doors shall be doors constructed to resist the passage of smoke.
OCCUPANCY COUNT:
533 - TOTAL OCCUPANTS
267/MALE
267/FEMALE
FIXTURES NEEDED:
14 - TOTAL FIXTURES
7/MALE
7/FEMALE
EXISTING FIXTURE COUNT:
17 - TOTAL FIXTURES
8/MALE (6 STAFF / 2 PUBLIC)
6/FEMALE (4 STAFF / 2 PUBLIC)
3/UNISEX (1 STAFF / 2 PUBLIC)
PROPOSED FIXTURE COUNT:
18 - TOTAL FIXTURES
7/MALE (5 STAFF / 2 PUBLIC)
8/FEMALE (6 STAFF / 2 PUBLIC)
3/UNISEX (1 STAFF / 2 PUBLIC)
UP
UP
UP UP
UP
UP
DN
UP
UP
DN
UP
UP
UP
DN
UP
UP
UP
DN
UP
DN
UPDN
UP
DN
UP
UP
UP
UP
Toilet-Male
A026
H.A.C.
A025
Locker Room
A026B
Toilet-Female
A026A
A401
B13
A401
A
A401
A
A
A
A401
A401
A
A401
A
A401
A
A401
A401
A401
C
S1.0
S2.0
S2.0 S2.0S2.0
S2.0
S1.0S1.1
S1.0S2.0 S1.0
S2.0
S1.0
S2.0S2.0
S2.0
S2.0
S1.0
S2.0
S1.0
S1.0
3' - 8"
/8
1' - 4"5' - 8" 11' - 5 1/8"
5' - 9 7/8"
/4
6' - 0"
2' - 9 5/8" 2' - 9 5/8" 4' - 4" 3' - 0"
/8
4' - 7"3' - 11 1/4"
1' - 4"
5' - 0"
10' - 3 1/2"
/2
3' - 3 1/2"
1' - 9"
1' - 7 3/4"
/4
/4
/8
/8
/4
A026 A026A
A025
Existing Locker Count: 92 (Unisex) New Locker Count: 44 (Unisex) Half-height
2' - 6"
S2.0S1.0
4"
S2.0S1.0S1.0
9.35
S3.0S3.0
" 1
/4
S2.0
8'-0"
8'-0" 8'-3"
7'-6"
H.A.C.
A025
Toilet-Male
A026 Toilet-Female
A026A
Locker Room
A026B7'-6"
7'-5"
8'-0"
9.29
ACT-2
ACT-2
ACT-2
ACT
9.28
ACT-2
GYP
9.22
Locker Room
A026B
Toilet-Female
A026AToilet-Male
A026
H.A.C.
A025
PT-1
PT-1
PT-1PT-1
VCT-1VCT-1
VCT
H.A.C.
A025
Toilet-Male
A026 Toilet-Female
A026A
Locker Room
A026B
PT-2
PT-2
PTB-1
PTB-1
PTB-1
RB-1
P-1 P-1
PHASE 1
AREA OF WORK
A025 - H.A.C.
A026 - Men Toilet A026A - Women Toilet A026B - Locker Room
DEMOLITION LEGEND
Block wall to be demolished
Existing wall to remain
Door and frame to be demolished
2.55
2.59 2.60
2.60 2.61
2.57
2.57
2.572.57 2.572.57 2.572.57
2.572.57
2.58
2.592.59
2.55
2.55
2.61
2.60
A025 A026 A026B
A026A
2.54
2.72
2.54
2.72
2.53
2.72
2.542.54 2.53
2.10
2.10
2.58
1.038.05
1.03
8.05
2.07
2.07
2.53 2.72
2.07
2.07
2.07
2.72
2.07
2.04
2.16
9.31
2.63
2.07
2.52 2.52
9.31
REFLECTED CEILING PLAN LEGEND
Recessed downlight fixture
Supply Air Diffuser
Return Air Grille
2' x 4' light fixture
2' x 2' acoustical tile ceiling
Gypsum board / portland cement plaster ceiling / soffit - painted
Chain-hung light fixture
Exhaust Grille
2' x 2' light fixture
JASON
H.
ROSS
2118221
IO
HO
FOET
A T
S
R E G I S
E T
R
ED RA
C H
TI
E C T
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:0
:5
P
M
VA Cincinnati Bathroom Deficiency Remediation
03/24/2023
NEW WORK PLAN - PHASE 1
A101
JWKR
539-22-207
Cincinnati, OH
Kristina Amin
100% Bid Documents 22034.00
N Scale: 1/4" = 1'-0"2
PHASE 1 NEW WORK PLAN - Basement A025, A026, A026A, A026B
N Scale: 1/4" = 1'-0"3
PHASE 1 NEW WORK RCP - Basement A025, A026, A026A, A026B
N Scale: 1/4" = 1'-0"5
PHASE 1 FLOOR FINISH PLAN - Basement A025, A026, A026A, A026B
N Scale: 1/4" = 1'-0"4
PHASE 1 WALL FINISH PLAN - Basement A025, A026, A026A, A026B
KEYPLAN - Basement
N Scale: 1/4" = 1'-0"1
PHASE 1 DEMOLITION PLAN - Basement A025, A026, A026A, A026B
1.03 Temporary Construction Barrier.
2.04 Existing floor finish to remain. Protect in place during construction.
2.07 Demolish existing block wall from floor to deck.
2.10 Remove existing toilet partitions.
2.16 Existing to remain.
2.52 Remove existing wall covering.
2.53 Remove existing ceramic tile flooring and coved base. Prep floor to receive new finishes.
2.54 Remove existing VCT floor finish and rubber base. Prep floor to receive new finishes.
2.55 Remove floor mounted plumbing fixture. Repair floor penetrations. Prep floor to receive new finishes.
2.57 Remove existing metal lockers.
2.58 Remove existing shower surround and shower base. Prepare subfloor for new schedule finish and base.
2.59 Remove wall-mounted plumbing fixture.
2.60 Remove and salvage all existing wall-mounted grab bars and toilet room accessories.
2.61 Remove existing mirror.
2.63 Remove existing door and door frame.
2.72 Remove existing ACT ceiling.
8.05 Temporary construction entrance door and frame with locking hardware.
9.22 Gypsum board header. See Detail.
9.28 Gypsum board bulkhead. See Detail.
9.29 Gypsum board ceiling.
9.31 Ceramic [porcelian] wall tile.
9.35 Solid Surface sill.
A. Remove all existing partitions shown with dashed line. Repair wall and floor finishes to match adjacent surfaces at areas of removal or scheduled new surfaces as required.
B. See Plumbing, HVAC and Electrical Drawings for removal work associated with those trades.
C. Computer and communication cables and/or other wiring, piping, tubing, etc.
serving other areas and functions located above ceiling or in walls of area to be remodeled shall be maintained during demolition/construction process.
D. Repair existing walls to match adjacent undisturbed wall where cabinets, countertops, etc. are shown to be removed.
E. Prepare walls and floor slabs as required to receive new fininsh materials where existing finish is indicated to be removed.
F. Prepare existing floor surface throughout the entire area of demolition and construction for new covering. Pour cementitious topping to fill voids, feather all edges to match adjacent floor elevations and correct low areas. Review and coordinate new floor drain locations and any floor slopes prior to slab prep.
G. Protect existing structure, adjacent windows, doors, and other building elements during demolition.
H. Provide tile substrate as follows: All shower stalls and tiled surfaces will receive Cementious backer units. All Bathrooms, Restrooms, HAC will receive Water-resistant gyp. board.
KEYNOTES
GENERAL DEMO NOTES
GENERAL NOTES
A. All dimensions are taken to face of gypsum wallboard or unit masonry.
B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.
C. All wood blocking to be fire retardent treated.
D. First floor level 100'-0" equals 728'-0".
E. All partitions shall be type 'S1.0' unless noted otherwise.
A. All wood blocking shall be fire retardant.
B. Light fixtures, sprinkler heads, speakers, and HVAC devices shall be located as close as possible to the center of acoustical ceiling panels.
Confirm any deviation from this with the Project Engineer.
C. See P, M, E and FP drawings for additional information regarding final information and quantites of fixtures/devices to be installed in ceiling.
D. All ACT ceilings in bathrooms to be Clean Room Type Washable ACT system.
D. See Electrical Drawings for lighting specifications.
E. All gypsum board ceilings to be painted P-4 unless noted otherwise.
F. Ceiling height as noted on plan.
GENERAL RCP NOTES
N
(BID ITEM #2- Delete Lockers)
(BID ITEM #2- Delete Lockers)
UP
UP
UP UP
UP
UP
DN
UP
UP
DN
UP
UP
UP
DN
UP
UP
UP
DN
UP
DN
UPDN
UP
DN
UP
UP
UP
UP
Toilet-Male
A004C
Toilet-Female
A004E
Existing Locker Count: 6 (Men) + 6 (women) = 12 New Locker Count: 8 (Unisex) Half-height
HAC
A004D
Locker Alcove
A004G
A401
A
A
A401
A401
A401
A
A
A
A401
A401
A401
A401
S1.0
S2.0S1.0
S1.0
S2.0
S2.0
S1.0
S2.03
/4
10' - 5"
7' - 1 5/8"
/2
4' - 4"
/4
3' - 0"
Corridor
C*B*2
/8
S1.0
3' - 0"
3' - 3 3/4" 7' - 1 1/4"
A004C A004E
S3.0
S3.0
A601
9.35
9.35
9"
S2.0
S2.0
12.1012.10
12.10
23.01
A311
E1.0
7'-8"
7'-8"
7'-8"
Toilet-Male
A004C
HAC
A004D
Toilet-Female
A004E
Locker Alcove
A004G
Corridor
C*B*2
7'-7"
7'-7"
9.29
7'-7"
9.29
ACT-2
ACT
ACT-2
9.28
9.28
9.28
GYP
GYP
9.25
ACT-2
7'-8"
ACT
7'-8"
Toilet-Male
A004C
HAC
A004D
Locker Alcove
A004G
Toilet-Female
A004E
Corridor
C*B*2
PT-2
PT-2
RB-1
RB-1
PTB-1
PTB-1
?CG-1
CG-1
CG-1
CG-1CG-1
PT-1
Toilet-Male
A004C
HAC
A004D
Toilet-Female
A004E
Locker Alcove
A004G
Corridor
C*B*2
PT-1
VCT-1
VCT
PHASE 2
AREA OF WORK
A004C - Men Toilet A004D - H.A.C.
A004E - Women Toilet
DEMOLITION LEGEND
Block wall to be demolished
Existing wall to remain
Door and frame to be demolished
A004C
A004D
A004E
A004F 2.592.61
2.57
2.60
2.55
2.57
2.59
2.55
2.60
2.16
2.10
2.10
Corridor
C*B*2
2.58 2.58
1.038.05
2.07 2.07
2.72
2.53 2.53
2.042.04
2.072.07
2.07
2.072.07
2.07
2.54
2.72
2.65
2.72
2.06
2.08
2.52 2.52 9.31
2.71
2.642.64
REFLECTED CEILING PLAN LEGEND
Recessed downlight fixture
Supply Air Diffuser
Return Air Grille
2' x 4' light fixture
2' x 2' acoustical tile ceiling
Gypsum board / portland cement plaster ceiling / soffit - painted
Chain-hung light fixture
Exhaust Grille
2' x 2' light fixture
JASON
H.
ROSS
2118221
IO
HO
FOET
A T
S
R E G I S
E T
R
ED RA
C H
TI
E C T
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:0
:0
P
M
VA Cincinnati Bathroom Deficiency Remediation
03/24/2023
NEW WORK PLAN - PHASE 2
A102
JWKR
539-22-207
Cincinnati, OH
Kristina Amin
100% Bid Documents 22034.00
N Scale: 1/4" = 1'-0"2
PHASE 2 NEW WORK PLAN - Basement A004C, A004D, A004E
N Scale: 1/4" = 1'-0"3
PHASE 2 NEW WORK RCP - Basement A004C, A004D, A004E
N Scale: 1/4" = 1'-0"4
PHASE 2 WALL FINISH PLAN -Basement A004C, A004D, A004E
N Scale: 1/4" = 1'-0"5
PHASE 2 FLOOR FINISH PLAN - Basement A004C, A004D, A004E
KEYPLAN - Basement
N Scale: 1/4" = 1'-0"1
PHASE 2 DEMOLITION PLAN - Basement A004C, A004D, A004E
1.03 Temporary Construction Barrier.
2.04 Existing floor finish to remain. Protect in place during construction.
2.06 Existing suspended ceiling system, fixtures, and devices to remain.
2.07 Demolish existing block wall from floor to deck.
2.08 Remove existing half height wall tile.
2.10 Remove existing toilet partitions.
2.16 Existing to remain.
2.52 Remove existing wall covering.
2.53 Remove existing ceramic tile flooring and coved base. Prep floor to receive new finishes.
2.54 Remove existing VCT floor finish and rubber base. Prep floor to receive new finishes.
2.55 Remove floor mounted plumbing fixture. Repair floor penetrations. Prep floor to receive new finishes.
2.57 Remove existing metal lockers.
2.58 Remove existing shower surround and shower base. Prepare subfloor for new schedule finish and base.
2.59 Remove wall-mounted plumbing fixture.
2.60 Remove and salvage all existing wall-mounted grab bars and toilet room accessories.
2.61 Remove existing mirror.
2.64 Remove and salvage existing acoustical ceiling tile and grid, light fixtures, and other ceiling mounted devices for reinstallation following above-ceiling work.
2.65 Remove and salvage existing Shower Mixing Valve for reinstallation in new location.
2.71 Remove existing Gyp ceiling.
2.72 Remove existing ACT ceiling.
8.05 Temporary construction entrance door and frame with locking hardware.
9.25 ACT ceiling system.
9.28 Gypsum board bulkhead. See Detail.
9.29 Gypsum board ceiling.
9.31 Ceramic [porcelian] wall tile.
9.35 Solid Surface sill.
12.10 Locker room bench wall mounted.
23.01 New exhaust louver location. See Mechanical Drawings.
A. Remove all existing partitions shown with dashed line. Repair wall and floor finishes to match adjacent surfaces at areas of removal or scheduled new surfaces as required.
B. See Plumbing, HVAC and Electrical Drawings for removal work associated with those trades.
C. Computer and communication cables and/or other wiring, piping, tubing, etc.
serving other areas and functions located above ceiling or in walls of area to be remodeled shall be maintained during demolition/construction process.
D. Repair existing walls to match adjacent undisturbed wall where cabinets, countertops, etc. are shown to be removed.
E. Prepare walls and floor slabs as required to receive new fininsh materials where existing finish is indicated to be removed.
F. Prepare existing floor surface throughout the entire area of demolition and construction for new covering. Pour cementitious topping to fill voids, feather all edges to match adjacent floor elevations and correct low areas. Review and coordinate new floor drain locations and any floor slopes prior to slab prep.
G. Protect existing structure, adjacent windows, doors, and other building elements during demolition.
H. Provide tile substrate as follows: All shower stalls and tiled surfaces will receive Cementious backer units. All Bathrooms, Restrooms, HAC will receive Water-resistant gyp. board.
KEYNOTES
GENERAL DEMO NOTES
GENERAL NOTES
A. All dimensions are taken to face of gypsum wallboard or unit masonry.
B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.
C. All wood blocking to be fire retardent treated.
D. First floor level 100'-0" equals 728'-0".
E. All partitions shall be type 'S1.0' unless noted otherwise.
A. All wood blocking shall be fire retardant.
B. Light fixtures, sprinkler heads, speakers, and HVAC devices shall be located as close as possible to the center of acoustical ceiling panels.
Confirm any deviation from this with the Project Engineer.
C. See P, M, E and FP drawings for additional information regarding final information and quantites of fixtures/devices to be installed in ceiling.
D. All ACT ceilings in bathrooms to be Clean Room Type Washable ACT system.
D. See Electrical Drawings for lighting specifications.
E. All gypsum board ceilings to be painted P-4 unless noted otherwise.
F. Ceiling height as noted on plan.
GENERAL RCP NOTES
N
(BID ITEM #4 - Delete Phase 2 Work)(BID ITEM #2- Delete Lockers) (BID ITEM #4 - Delete Phase 2 Work)
(BID ITEM #4 - Delete Phase 2 Work)
(BID ITEM #4 - Delete Phase 2 Work)
(BID ITEM #4 - Delete Phase 2 Work) (BID ITEM #2- Delete Lockers)
UP
UP
UP UP
UP
UP
DN
UP
UP
DN
UP
UP
UP
DN
UP
UP
UP
DN
UP
DN
UPDN
UP
DN
UP
UP
UP
UP
A402
D
Toilet-Unisex
B008
S2.0-SS2.0-SS2.0-S
2' - 4"5' - 2 1/8" 3' - 0"
S1.0 S2.0 S1.0
S2.0
S2.0
/2
B008
S3.0 9.35
8'-0"
8'-0"
Toilet-Male
B010
7'-11"
7'-0"
8'-0"
7'-11"
9.29
ACT-2
ACT-2
ACT-2
9.28
GYP
A601
9.22
9.28
Toilet-Unisex
B008
PT-2
PTB-1
RB-1
P-1
Toilet-Unisex
B008
PT-1
VCT
Toilet-Male
B010
PT-1
VCT-1
VCT-1
VCT
Toilet-Male
B010
PT-2
PTB-1
CG-1CG-1
RB-1P-1
P-1
RB-1
PTB-1
P-1
PHASE 3
AREA OF WORK
B008 - Unisex Toilet B010 - Women Toilet
DEMOLITION LEGEND
Block wall to be demolished
Existing wall to remain
Door and frame to be demolished
B010
2.55
2.61
2.612.612.61
2.60
2.16
2.59 2.53
2.55
2.56
2.502.502.502.50
2.102.10
1.03
8.05
2.072.072.07
2.72
2.10
9.319.319.31
A601
B008
2.55
2.60
2.582.58 2.59
1.038.05
2.532.53
2.07
2.72
2.07 9.31
Toilet-Male
B010
A402
E
S1.0
S1.0
S2.0
S1.0
S1.0
S2.0S2.0 S2.0
S2.0
S2.0
10'-11 3/8"
4' - 3"
/8
5' - 6"
5' - 4 3/8"
2' - 6 1/8"2' - 6"3' - 0"
1' - 0 3/8"
TP
B010
Existing Locker Count: 0 (Men) + 0 (Women) = 0 New Locker Count: 6 (Unisex) Half-height
S2.0
S1.0
S2.0
S2.0
S2.0
S3.0
S3.0
S3.0
S3.0
A601
9.35
12.10
8'-0"
Toilet-Unisex
B008
7'-11"
9.29
ACT-2
GYP
9.284
A601
REFLECTED CEILING PLAN LEGEND
Recessed downlight fixture
Supply Air Diffuser
Return Air Grille
2' x 4' light fixture
2' x 2' acoustical tile ceiling
Gypsum board / portland cement plaster ceiling / soffit - painted
Chain-hung light fixture
Exhaust Grille
2' x 2' light fixture
JASON
H.
ROSS
2118221
IO
HO
FOET
A T
S
R E G I S
E T
R
ED RA
C H
TI
E C T
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:0
:1
P
M
VA Cincinnati Bathroom Deficiency Remediation
03/24/2023
NEW WORK PLAN - PHASE 3
A103
JWKR
539-22-207
Cincinnati, OH
Kristina Amin
100% Bid Documents 22034.00
N Scale: 1/4" = 1'-0"2 PHASE 3 NEW WORK PLAN - Basement B008, B010
N Scale: 1/4" = 1'-0"3 PHASE 3 NEW WORK RCP - Basement B008, B010
N Scale: 1/4" = 1'-0"4 PHASE 3 WALL FINISH PLAN - Basement B008, B010
N Scale: 1/4" = 1'-0"5 PHASE 3 FLOOR FINISH PLAN - Basement B008, B010
KEYPLAN - Basement
N Scale: 1/4" = 1'-0"1 PHASE 3 DEMOLITION PLAN - Basement B008, B010
1.03 Temporary Construction Barrier.
2.07 Demolish existing block wall from floor to deck.
2.10 Remove existing toilet partitions.
2.16 Existing to remain.
2.50 Remove existing masonry block walls.
2.53 Remove existing ceramic tile flooring and coved base. Prep floor to receive new finishes.
2.55 Remove floor mounted plumbing fixture. Repair floor penetrations. Prep floor to receive new finishes.
2.56 Remove existing shower base. Prepare subfloor for new schedule finish and base.
2.58 Remove existing shower surround and shower base. Prepare subfloor for new schedule finish and base.
2.59 Remove wall-mounted plumbing fixture.
2.60 Remove and salvage all existing wall-mounted grab bars and toilet room accessories.
2.61 Remove existing mirror.
2.72 Remove existing ACT ceiling.
8.05 Temporary construction entrance door and frame with locking hardware.
9.22 Gypsum board header. See Detail.
9.28 Gypsum board bulkhead. See Detail.
9.29 Gypsum board ceiling.
9.31 Ceramic [porcelian] wall tile.
9.35 Solid Surface sill.
12.10 Locker room bench wall mounted.
A. Remove all existing partitions shown with dashed line. Repair wall and floor finishes to match adjacent surfaces at areas of removal or scheduled new surfaces as required.
B. See Plumbing, HVAC and Electrical Drawings for removal work associated with those trades.
C. Computer and communication cables and/or other wiring, piping, tubing, etc.
serving other areas and functions located above ceiling or in walls of area to be remodeled shall be maintained during demolition/construction process.
D. Repair existing walls to match adjacent undisturbed wall where cabinets, countertops, etc. are shown to be removed.
E. Prepare walls and floor slabs as required to receive new fininsh materials where existing finish is indicated to be removed.
F. Prepare existing floor surface throughout the entire area of demolition and construction for new covering. Pour cementitious topping to fill voids, feather all edges to match adjacent floor elevations and correct low areas. Review and coordinate new floor drain locations and any floor slopes prior to slab prep.
G. Protect existing structure, adjacent windows, doors, and other building elements during demolition.
H. Provide tile substrate as follows: All shower stalls and tiled surfaces will receive Cementious backer units. All Bathrooms, Restrooms, HAC will receive Water-resistant gyp. board.
KEYNOTES
GENERAL DEMO NOTES
GENERAL NOTES
A. All dimensions are taken to face of gypsum wallboard or unit masonry.
B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.
C. All wood blocking to be fire retardent treated.
D. First floor level 100'-0" equals 728'-0".
E. All partitions shall be type 'S1.0' unless noted otherwise.
A. All wood blocking shall be fire retardant.
B. Light fixtures, sprinkler heads, speakers, and HVAC devices shall be located as close as possible to the center of acoustical ceiling panels.
Confirm any deviation from this with the Project Engineer.
C. See P, M, E and FP drawings for additional information regarding final information and quantites of fixtures/devices to be installed in ceiling.
D. All ACT ceilings in bathrooms to be Clean Room Type Washable ACT system.
D. See Electrical Drawings for lighting specifications.
E. All gypsum board ceilings to be painted P-4 unless noted otherwise.
F. Ceiling height as noted on plan.
GENERAL RCP NOTES
FINISH LEGEND
FINISH CATEGORY CODE FINISH TYPE MANUFACTURER PRODUCT / COLOR COMMENTS
06 41 16 PLASTIC LAMINATE CLAD ARCHITECTURAL CABINETS
06 41 16 PLASTIC LAMINATE CLAD
ARCHITECTURAL CABINETS
PL-1 PLASTIC LAMINATE WILSONART HD Laminate, Ashbee Oak #17000K-57, Aligned Texture, AEON Scratch Resistant
Bathroom Aprons
09 30 13 CERAMIC PORCELAINTILING
09 30 13 CERAMIC PORCELAINTILING PT-1 PORCELAIN TILE CROSSVILLE Empire #VS75 White White UN Unpolished, 12x24 Grout 02 Pewter
09 30 13 CERAMIC PORCELAINTILING PT-2 PORCELAIN TILE CROSSVILLE Empire #VS75 Cadet White White PO Polished, 12x24 Grout 01 Alabaster
09 30 13 CERAMIC PORCELAINTILING PTB-1 PORCELAIN TILE
BASE
CROSSVILLE Empire #VS75 White White UN Unpolished, 6x12 Grout 02 Pewter
09 51 00 ACOUSTICAL CEILING
09 51 00 ACOUSTICAL CEILING ACT-1 CEILING FINISHES ARMSTRONG Ultima Part 1910, Size 24” x 24”, Color: White Acoustic Ceiling Tile 24 x 24
09 51 00 ACOUSTICAL CEILING ACT-2 CEILING FINISHES ARMSTRONG Clean Room VL 868B, 24" x 24"x 5/8"; White Grid
09 65 13 RESILIENT BASE AND ACCESSORIES
09 65 13 RESILIENT BASE AND
ACCESSORIES
RB-1 RUBBER BASE JOHNSONITE Rubber Cove Base 6", Color: #80 Fawn
09 65 13 RESILIENT BASE AND
ACCESSORIES
VCT-1 RESILIENT
FLOORING
TBD New Flooring Match the Existing
09 91 00 PAINTING
09 91 00 PAINTING P-1 INTERIOR PAINT BENJAMIN MOORE TBD Semi Gloss - All Walls To Be Painted P-1 Unless Noted Otherwise.
09 91 00 PAINTING P-2 PAINT(DOOR
FRAMES)
BENJAMIN MOORE TBD High Gloss Enamel - Door Frames
10 21 13 TOILET COMPARTMENTS
10 21 13 TOILET COMPARTMENTS TP-1 TOILET PARTITION TBD Stainless Steel Toilet Partitions
10 26 00 WALL AND DOOR PROTECTION
10 26 00 WALL AND DOOR
PROTECTION
CG-1 CORNER GAURD TBD Stainless Steel Match the Existing
10 26 00 WALL AND DOOR
PROTECTION
HR-1 HAND RAIL INPRO Match the Existing
12 36 61.16 SOLID SURFACING COUNTERTOPS
12 36 61.16 SOLID SURFACING
COUNTERTOPS
SS-1 SOLID SURFACE WILSONART Hot Stone #9201GS Bathroom Countertops N
(BID ITEM #3- Delete Rm# B008 Work)
(BID ITEM #2- Delete Lockers)
(BID ITEM #3- Delete Rm# B008 Work)
(BID ITEM #3- Delete Rm# B008 Work)
(BID ITEM #3- Delete Rm# B008 Work)
(BID ITEM #3- Delete Rm# B008 Work)
(BID ITEM #2- Delete Lockers)
S1.0
4 7/8"
9.219.21
9.02
9.80
7.82
7.82
STRUCTURE ABOVE
FIN. CEILING
FLOOR SLAB
9.04
S1.1
9.219.21
9.03
9.80
7.82
7.82
7 1/4"
9.04
S2.0
9.02
9.02
7.82
7.82
4 1/4"
9.80
@ INTERIOR WALL
LOCATIONS
9.21
9.04
S2.0-S
NON-RATED
SMOKE PARTITION
9.21
5.06
9.80
7.82
7.82
4 1/4"
9.04
T1.0
9.21
9.02
9.80
4 1/4"
9.16
1-HR RATED
FIRE BARRIER
U.L. #U465
S3.0
5/8"
9.23
E1.0
4.13
4 1/2"
4.16
7.12
7 5/8"
1' - 1 1/8"
FLOOR SLAB
E1.0
5.05
5.04
23.02
23.01
4.17
4.17
2.49
JASON
H.
ROSS
2118221
IO
HO
FOET
A T
S
R E G I S
E T
R
ED RA
C H
TI
E C T
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:0
:1
P
M
VA Cincinnati Bathroom Deficiency Remediation
03/24/2023
WALL SECTIONS
A311
JWKR
539-22-207
Cincinnati, OH
Kristina Amin
100% Bid Documents 22034.00
2.49 Remove existing 4-1/2" thick stone panel (Approx. size 30"x30") and 8" CMU.
4.13 8" concrete masonry unit.
4.16 Stone Veneer
4.17 Masonry tie.
5.04 Steel lintel.
5.05 Steel lintel plate.
5.06 3-5/8" cold formed metal framing @ 16" O.C.
7.12 Rigid thermal wall insulation.
7.82 Continuous acoustic sealant @ non-rated walls / fire-rated sealant @ rated walls each side.
9.02 3 5/8" non-structural metal framing @ 16" o.c.
9.03 6" non-structural metal framing @ 16" o.c.
9.04 Deflection track.
9.16 Plastic sheeting
9.21 5/8" Type 'X" gypsum board. Painted finish.
9.23 5/8" Type "X" gypsum board laminated to existing wall face.
Extend to above finished ceiling.
9.80 Acoustic insulation
23.01 New exhaust louver location. See Mechanical Drawings.
23.02 Duct. See Mechanical Drawings.
SECTION NOTES
N.T.S.Scale:
Exterior Louver
X
X
Toilet Accessory
Equipment
Signage
Keynote
Material Finish
SYMBOL LEGEND
A
A401
A401
A401
A
A
A
A401
A401
A401
A401
Toilet-Male
A004C
Toilet-Female
A004EHAC
A004D
Locker Alcove
A004G
Corridor
C*B*2
K
I
C
LA
J
22.06
22.06
C
L A
M
I
10.51 B
B
A601
A311
PT-2
O I
K
PL-1SS-1
C
B8 2'-9"
H
C
G
A
26.01
PTB-1
P-1
N
C
A
H
10.12
9.35
12.10
1' - 10"
" 3
22.05 J
L
B
A
P-1 PT-2
C
N A
CC
10.12
22.05
PL-1
PT-2
SS-1
I
M
O
2'-9"
B8
H
C
10.12
G
A
26.01
12.10
2' - 6"1
A311
A
B
L
PTB-1
P-1P-1
10.51
P-1
10.53
10.52
10.52
12.10
PTB-1
P-1
1' - 10"
P-1
RB-1
HR-1
P-1 P-1A
HR-1
A CG-1CG-1
CG-1
RB-1 RB-1
ACG-1
4' - 4"
P-1
A
10.53
10.52 1' - 10" 12.10
RB-1
10.54
A401
A
A401
A
A
A
A401
A401
A
A401
A
A401
Toilet-Male
A026
Toilet-Female
A026A
Locker Room
A026B
A401
I
M
I
I
K
K
A B
C
B CA
JJ
JJ
22.06
L
L
L
22.06
22.06
10.03
10.0310.03
10.03
AC
PTB-1
P-1
M
P-1
I
PTB-1
PT-2
PTB-1
PL-1
SS-1
O
2'-9"
B8
26.01
PTB-1
B
A
L
10.11
PT-2
C
I
O
PTB-1
P-1
PL-1
SS-1
I
K
B8
4'-0"
P-1
H
C
G
A
26.01
C
PT-2
P-1 N
PTB-1
A
C
H
10.12
22.05
P-1P-1
PTB-1
B
A
PL-1
SS-1
J
B8
2'-6"
10.11
O
26.01
P-1 P-1
10.51
10.53
10.52
P-1
10.51
10.53
10.5210.52
P-1
10.51
10.53
10.52
12.10
10.53
10.51
10.52
10.54
A
A401
H.A.C.
A025
22.04
10.04
22.04
10.04
10.02
PT-2
PTB-1
22.04
PL-1
W1
2'-0"
PT-2
JASON
H.
ROSS
2118221
IO
HO
FOET
A T
S
R E G I S
E T
R
ED RA
C H
TI
E C T
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:0
:3
P
M
VA Cincinnati Bathroom Deficiency Remediation
03/24/2023
INTERIOR ELEVATIONS
A401
BMKR
539-22-207
Cincinnati, OH
Kristina Amin
100% Bid Documents 22034.00
A. See sheet A101 detail 5/ A102 detail 5/ A103 detail 5 for Floor Finish Plan.
B. See sheet A511 for Casework Details.
C. See sheet A103 for Finish Materials Legend.
D. Provide tile substrate as follows: All shower stalls and bathroom walls will receive Cementious backer units. All Bathrooms, Restrooms, HAC will receive Water-resistant gyp. board.
9.35 Solid Surface sill.
10.02 Utility cabinet.
10.03 Surface mounted garment hook
10.04 Mop and broom holder.
10.11 Toilet partition overhead bracing.
10.12 Solid surface standard shower enclosure system.
10.51 Metal lockers match the existing
10.52 Metal trim panel. Paint to match lockers.
10.53 Sloped top by locker manufacturer.
10.54 Adjustable leveling feet.
12.10 Locker room bench wall mounted.
22.04 Mop sink
22.05 Shower controls.
22.06 Undermount solid surface sink bowl.
26.01 Light fixture. See Electrical Drawings.
ELEVATION NOTES
GENERAL INT. ELEVATION NOTES
A2 13456
B1314151617
Scale: 1/4" = 1'-0"
PHASE 2 - Basement A004C, A004D, A004E
Scale: 1/4" = 1'-0"
PHASE 1 - Basement A026, A026A, A026B
2122232425
Scale: 1/4" = 1'-0"
Basement A025
C2627
SIGNAGE SCHEDULE
Type Mark Count
MOUNTING
HEIGHT
A 9 51" A.F.F. TO
BOTTOM
(BID ITEM #2- Delete Lockers)
(BID ITEM #4 - Delete Phase 2 Work)(BID ITEM #2- Delete Lockers)
X
Toilet Accessory
Equipment
Signage
Keynote
Material Finish
SYMBOL LEGEND
Toilet-Unisex
B008
A
A402
A
A402
22.06
G
C
A
10.12
L
A
B
I
M
A
A402
A402
A
Toilet-Male
B010
BC
L
KI 22.06 10.51
10.03
GC A
10.12
10.01
10.01
10.01
A601
B8 2'-6"
PL-1
P-1
O
SS-1
M
26.01
PTB-1
PT-2
C
P-1
H
C
A
10.12
A
B
L
PTB-1
10.03
H
C
P-1 P-1P-1
G
A
10.12
PTB-1
P-1P-1
10.51
A
10.52
10.01
10.53
RB-1RB-1
" 3
PT-2
PL-1 SS-1
P-1
C
O
B8 2'-6"
H
C
G
A
C
10.12 10.1126.01
22.05
P-1
2.16
PTB-1
3' - 6"
12.10
PTB-1
1'-0"
3'-3"
P-1
PTB-1
B
A
L
1' - 0"
3' - 3"
Note: Flush valve located on accessible side
6"
B
A
M
IN
D
C
Note:
Beginning of reflective surface
MIN.
7"
O
T o D is p e n s e r
O p e n in g
A D
A /A
B A
A S
A c c e s s ib le
T o
O p e ra b le
M e c h a n is m
I
N
F
A
/8
H
E
M
K
J L
1'-6"
D
8"
"m a x m in
Shower control space
2' - 3"max
Shower control space
3' - 0" 3' - 0"
1' - 6"
TILE TO PAINTED GYP. TILE COVE-SHAPED PROFILETILE OUTSIDE CORNER EDGE PROFILE
9.31
9.31
9.67
9.31
9.66
9.31
9.33
9.65 9.33
9.52
9.68
9.36
9.38
9.37
JASON
H.
ROSS
2118221
IO
HO
FOET
A T
S
R E G I S
E T
R
ED RA
C H
TI
E C T
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:0
:4
P
M
VA Cincinnati Bathroom Deficiency Remediation
03/24/2023
INTERIOR ELEVATIONS
A402
BMKR
539-22-207
Cincinnati, OH
Kristina Amin
100% Bid Documents 22034.00
TOILET ACCESSORIES SCHEDULE
MARK ITEM JSN #
PROVIDED
BY
INSTALLED
BY
O W
N E
R
C O
N T
R A
C T
O R
O W
N E
R
C O
N T
R A
C T
O R
A GRAB BAR 18" LENGTH B-6806 X 18 X X
B GRAB BAR 42" LENGTH B-6806 X 42 X X
C GRAB BAR 36" LENGTH B-6806 X 36 X X
G Shower Seat X X
H Shower Curtain Rod X X
I Soap Dispenser BY OWNER X X
J Sanitary Napkin Dispenser BY OWNER X X
K Paper Towel Dispenser BY OWNER X X
L Toilet Tissue Dispenser B-2888 X X
M Paper Towel-Waste Combo-Partial Recess X X
N Robe Hook X X
O Mirror - 24" x 36" B-290 2436 X X
A. See sheet A101 detail 5/ A102 detail 5/ A103 detail 5 for Floor Finish Plan.
B. See sheet A511 for Casework Details.
C. See sheet A103 for Finish Materials Legend.
D. Provide tile substrate as follows: All shower stalls and bathroom walls will receive Cementious backer units. All Bathrooms, Restrooms, HAC will receive Water-resistant gyp. board.
ELEVATION NOTES
GENERAL INT. ELEVATION NOTES
Scale: 1/4" = 1'-0"
PHASE 3 - Basement B008
D
E
Scale: 1/4" = 1'-0"
PHASE 3 - Basement B010
2.16 Existing to remain.
9.31 Ceramic [porcelian] wall tile.
9.33 Porcelian floor tile.
9.36 .0625" Silicone Adhesive
9.37 Full mortar bed (min. 1/8").
9.38 Waterproofing / crack isolation membrane.
9.52 Existing VCT.
9.65 Anodized aluminum type edge strips embedded in tile setting bed shall be used at all horizontal unfinished edges of wall tile and base. Size and profile to be used with appropriate tile thickness.
9.66 Anodized aluminum type edge strips embedded in tile setting bed shall be used at all floor to wall tile intersections. Size and profile to be consistent with tile thickness.
9.67 Anodized aluminum type edge strips embedded in tile setting bed shall be used at all exterior corners. Size and profile to be consistent with tile thickness.
9.68 Metal [stainless steel] edge trim.
10.01 Corner protection.
10.03 Surface mounted garment hook
10.11 Toilet partition overhead bracing.
10.12 Solid surface standard shower enclosure system.
10.51 Metal lockers match the existing
10.52 Metal trim panel. Paint to match lockers.
10.53 Sloped top by locker manufacturer.
12.10 Locker room bench wall mounted.
22.05 Shower controls.
22.06 Undermount solid surface sink bowl.
26.01 Light fixture. See Electrical Drawings.
01_Typical Mounting Heights - Toilet Accessories
Tile Transitions Flooring Transition VCT - PT
(BID ITEM #2- Delete Lockers)
(BID ITEM #3- Delete Rm# B008 Work)
SEE PLAN
1/2" 1/2"
H1 J1
8.02
9.21
9.80
8.02
9.09
9.21
9.80 8.04
S1
9.08
7.82 7.82 1/2" 1/2"
2"
SEE
SCHED. 2"
S E
E S
C H
E D
U L E
SEE SCHED.
S E
E S
C H
E D
U L E
F
9.30
9.18
9.29
9.02
Varies
9.02
9.309.30
9.21
9.18
Drywall to extend 6" above finished ceiling.
/8
/8
Slope 1/4"-1/8" : 12" max
9.34
9.35
9.34
9.33
9.28
9.30
26.01
9.34
9.02
9.29
22.05
/2
Shower controls to be min 1-1/2" above grab bars, not to exceed 48" A.F.F.
A
C
H
Controls 27" max
A601
Sim
9.34
9.39
9.36
9.02
Air Gap
Gap 3/16"
22.08
7.01
7.02
9.33
9.35
9.55
9.37
22.09
/2
M
A X
9.42
B8
Sink
2'-1"
/4
/4
1"
11" 5" 8"
12.27
12.20
22.06
12.19
W1
1'-2" 1"
26.01
12.29
12.30
12.31
12.22
12.21
9.27
JASON
H.
ROSS
2118221
IO
HO
FOET
A T
S
R E G I S
E T
R
ED RA
C H
TI
E C T
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:0
:4
P
M
VA Cincinnati Bathroom Deficiency Remediation
03/24/2023
SCHEDULES, SECTIONS & DETAILS
A601
JWKR
539-22-207
Cincinnati, OH
Kristina Amin
100% Bid Documents 22034.00
DOOR SCHEDULE
DOOR
DOOR DESCRIPTION FRAME DESCRIPTION
Sill Detail
FIRE
RATING
HDWE
SET REMARKSTYPE MAT'L
SIZE
TYPE MAT'L HEAD JAMB# W H T
A004C F WD 1 3'-0" 7'-0" 1 3/4" 1 HM H-1 J-1 S-1 N/A HW-2
A004E F WD 1 3'-0" 7'-0" 1 3/4" 1 HM H-1 J-1 S-1 N/A HW-2
A025 F WD 1 3'-0" 7'-0" 1 3/4" 1 HM H-1 J-1 S-1 N/A HW-1 Knock-down frame required
A026 F WD 1 3'-0" 7'-0" 1 3/4" 1 HM H-1 J-1 S-1 N/A HW-4
A026A F WD 1 3'-0" 7'-0" 1 3/4" 1 HM H-1 J-1 S-1 N/A HW-4
B008 F WD 1 3'-0" 7'-0" 1 3/4" 1 HM H-1 J-1 S-1 N/A HW-2
B010 F WD 1 3'-0" 7'-0" 1 3/4" 1 HM H-1 J-1 S-1 N/A HW-3
7.01 Waterproofing membrane.
7.02 Extend waterproof membrane past shower pan. Top of
membrane must be above top of drain.
7.82 Continuous acoustic sealant @ non-rated walls / fire-rated sealant @ rated walls each side.
8.02 Temporary hollow metal frame.
8.04 Hospital stops @ all interior hollow metal frames.
9.02 3 5/8" non-structural metal framing @ 16" o.c.
9.08 Metal framing box header.
9.09 Double metal framing at jambs, typ.
9.18 5/8" Type "X" gypsum board.
9.21 5/8" Type 'X" gypsum board. Painted finish.
9.27 Gypsum board soffit.
9.28 Gypsum board bulkhead. See Detail.
9.29 Gypsum board ceiling.
9.30 Clean Room type washable ACT system.
9.33 Porcelian floor tile.
9.34 3/4" Solid Surface.
9.35 Solid Surface sill.
9.36 .0625" Silicone Adhesive
9.37 Full mortar bed (min. 1/8").
9.39 Cementitious Backer Board
9.42 Add tapered floor fill to ensure 1/2" maximum transition between finished surfaces.
9.55 Existing Concrete Slab
9.80 Acoustic insulation
12.19 Integral solid surface backsplash.
12.20 Solid surface material over 3/4" plywood, with 1/4" eased edge.
12.21 Plastic laminate over 3/4" particle board.
12.22 Adjustable shelf. Plastic laminate over 3/4" particle board.
12.27 Removable panel with concealed fasteners: Plastic laminate over 3/4" plywood.
12.29 4" wire pull. [Recessed pull.]
12.30 Self-latching, key-operated lock.
12.31 Concealed hinge.
22.05 Shower controls.
22.06 Undermount solid surface sink bowl.
22.08 Shower drain. See Plumbing Drawings.
22.09 Shower Receptor/Base.
26.01 Light fixture. See Electrical Drawings.
N.T.S.Scale:
H.M. Frame Details
N.T.S.Scale:
H.M. Frame Types N.T.S.Scale:
Door Types
DETAIL NOTES
N.T.S.Scale:
Typical Bulkhead Detail N.T.S.Scale:
Typical Header Detail N.T.S.Scale:
Typical Shower Detail Scale: 1 1/2" = 1'-0"7 Shower Waterproofing and Drain
A. See interior elevations on sheet A401-A404 for further information.
GENERAL CASEWORK NOTES
N.T.S.Scale:
Casework Sections N.T.S.Scale:
Casework Sections
ABBREVIATIONS
AC - AIR COMPRESSOR
ACC - ACCESS
AD - ACCESS DOOR
ADB - ACID DILUTION BASIN
ADJ - ADJUSTABLE
AFF - ABOVE FINISHED FLOOR
AFG - ABOVE FINISHED GRADE
ALT - ALTERNATE
AP - ACCESS PANEL
APPROX - APPROXIMATE
ARCH - ARCHITECT OR ARCHITECTURAL
ASSY - ASSEMBLY
BFP - BACKFLOW PREVENTER
BLDG - BUILDING
BOB - BOTTOM OF BEAM
BOD - BOTTOM OF DUCT
BOE - BOTTOM OF EQUIPMENT
BOF - BOTTOM OF FOOTING
BOG - BOTTOM OF GRILLE
BOP - BOTTOM OF PIPE
BOT - BOTTOM
BTWN - BETWEEN
CA - COMPRESSED AIR
CFCI - CONTRACTOR FURNISHED CONTRACTOR
INSTALLED
CLG - CEILING
CONN - CONNECT OR CONNECTION
CONTR - CONTRACTOR
COR - CONTRACTING OFFICER'S REPRESENTATIVE
CORR - CORRIDOR
CTR - CENTER
CWS - COMBINATION WATER SERVICE
D - DEPTH
DET - DETAIL
DIA - DIAMETER
DIM - DIMENSION
DN - DOWN
DS - SPRINKLER (DRY)
DWG - DRAWING
EA - EACH
EC - ELECTRICAL (DIVISION 26)
EJ - EXPANSION JOINT
ELEC - ELECTRICAL
ELEV - ELEVATOR
EQ - EQUAL
EQUIP - EQUIPMENT
ETR - EXISTING TO REMAIN
EQS - EQUIPMENT SUPPLIER
EXP - EXPANSION
EXT - EXTERIOR
EX - EXISTING
F - FIRE SUPPRESSION (STANDPIPE/SPRINKLER MAIN)
FCE - FIRE CONTROL EQUIPMENT
FCO - FLOOR CLEANOUT
FD - FLOOR DRAIN
FDC - FIRE DEPARTMENT CONNECTION
FDV - FIRE DEPARTMENT VALVE
FF - FINISHED FLOOR ELEVATION
FHC - FIRE HOSE CABINET
FLR - FLOOR
FPM - FEET PER MINUTE
FR - FIRE RISER
FS - FIRE SERVICE
FSC - FIRE SUPPRESSION (DIVISION 21)
FT - FEET
FTG - FOOTING
GA - GAUGE
GAL - GALLON
GALV - GALVANIZED
GC - GENERAL TRADES
GPM - GALLONS PER MINUTE
HC - HVAC (DIVISION 23)
HD - HUB DRAIN
HP - HORSEPOWER OR HIGH POINT
HR - HOSE REEL
HT - HEAT TRACE
HVAC - HEATING, VENTILATING, AND AIR CONDITIONING
ID - INSIDE DIAMETER
INV - INVERT ELEVATION
IN - INCHES
JS - JANITOR SINK
L - LENGTH
LBS - POUNDS
MAX - MAXIMUM
MB - MOP BASIN
MC - MECHANICAL (DIVISION 23)
MEZZ - MEZZANINE
MFR - MANUFACTURER
MIN - MINIMUM
MISC - MISCELLANEOUS
MTD - MOUNTED
MTG - MOUNTING
N/C - NORMALLY CLOSED
NIC - NOT IN CONTRACT
N/O - NORMALLY OPEN
NOM - NOMINAL
NPT - NATIONAL PIPE THREAD
NTS - NOT TO SCALE
OA - OUTDOOR AIR
OD - OUTSIDE DIAMETER
OFCI - OWNER FURNISHED CONTRACTOR
INSTALLED
OFOI - OWNER FURNISHED OWNER INSTALLED
PC - PLUMBING (DIVISION 22)
OR PUMPED CONDENSATE RETURN
PIV - POST INDICATOR VALVE
PLBG - PLUMBING
PS - PRE-ACTION/DELUGE SPRINKLER
PRESS - PRESSURE
PRV - PRESSURE REGULATING VALVE
PSF - POUNDS PER SQUARE FOOT
PSI - POUNDS PER SQUARE INCH
PSV - PRESSURE SUSTAINING VALVE
PSIG - POUNDS PER SQUARE INCH GAUGE
RAD - RADIUS
REC - RECESSED
REQD - REQUIRED
RI - ROUGH IN
RPM - REVOLUTIONS PER MINUTE
S - SPRINKLER (WET)
SCH - SCHEDULE
SD - SPRINKLER DRAIN
SHT - SHEET
SK - SINK
SPEC - SPECIFICATIONS
SQ - SQUARE
STD - STANDARD
STRUC - STRUCTURAL OR STRUCTURE
SUC - SITE UTILITY CONTRACTOR
TEMP - TEMPERATURE
TOB - TOP OF BEAM
TOD - TOP OF DUCT
TOE - TOP OF EQUIPMENT
TOF - TOP OF FOOTING
TOJ - TOP OF JOIST
TOP - TOP OF PIPE
TOS - TOP OF SLAB OR TOP OF STEEL
TYP - TYPICAL
UNO - UNLESS NOTED OTHERWISE
VEL - VELOCITY
VIB - VALVE IN BOX
VOL - VOLUME
W/ - WITH
W/O - WITHOUT
WIV - WALL INDICATOR VALVE
WS - WATER SERVICE
VALVES AND FITTINGS
T
P
FOB
FOT
CONCENTRIC PIPE REDUCER
ECCENTRIC PIPE REDUCER
GAUGE - PRESSURE
GAUGE - TEMPERATURE OR THERMOMETER
UNION
CLEANOUT
STRAINER
STRAINER - WITH A BLOW DOWN VALVE AND HOSE
CONNECTION
VALVE - DRAIN WITH HOSE END CONNECTION
VALVE - PRESSURE REGULATING
VALVE - SAFETY RELIEF. PIPE DISCHARGE AIR
GAPPED TO FLOOR DRAIN UNLESS NOTED
OTHERWISE.
PLUG - PRESSURE AND TEMPERATURE TEST
TRAP PRIMER
GAUGE - VACUUM WITH STOP
CLEANOUT - TO GRADE OR FINISHED FLOOR
END CAP
MIXING FAUCET
PLUG
HOSE BIB
WALL HYDRANT
VALVE - PLUG
VALVE - SHUTOFF AND BOX
VALVE - SHUTOFF ON RISER
V
VB
TP
CO
VALVE - SOLENOID
S
P/T VALVE - PRESSURE AND TEMPERATURE SAFETY
RELIEF. PIPE DISCHARGE AIR GAPPED TO
FLOOR DRAIN UNLESS NOTED OTHERWISE.
VALVE - CHECK
VALVE - SHUTOFF: BALL, GATE, BUTTERFLY VALVE
(REFER TO SPECIFICATIONS FOR REQUIRED TYPE
BASED ON APPLICATIONS)
AUTOMATIC FLOW CONTROLLER WITH P/T PLUG IN
AND OUT
VALVE - COMBINATION SHUTOFF AND
BALANCING (REFER TO SPECIFICATIONS FOR
REQUIRED TYPE BASED ON APPLICATIONS)
A1
P1 P1OR
A1
OH
P2
B
P2
GENERAL FLOOR PLAN NOTES
RISER OR STACK NUMBER
DETAIL: B = DETAIL DESIGNATION
P2 = SHEET WHERE DETAIL IS LOCATED
FIRE SUPPRESSION HAZARD CLASSIFICATION AND
HAZARD CLASSIFICATION GROUP
SECTION: 1 = SECTION DESIGNATION
P2 = SHEET WHERE DETAIL IS LOCATED
EQUIPMENT REFERENCE. LETTER DESIGNATION
VARIES. REFER TO SCHEDULES.
EQUIPMENT, DEVICE, OR PLUMBING FIXTURE MARK.
LETTER DESIGNATIONS REFER TO SCHEDULES.
CONNECT TO EXISTING
PLAN NOTE. APPLIES ONLY TO THE SHEET WHICH
IT IS SHOWN UNLESS NOTED OTHERWISE.
DETAIL NOTE. APPLIES ONLY TO THE ASSOCIATED DETAIL.
"UP TO" SYMBOL (ITEM ON FLOOR ABOVE)
EXISTING PIPE TO REMAIN
EXISTING PIPE TO BE REMOVED
EXPANSION JOINT
WATER METERM
PIPING SYMBOLS
BOTTOM CONNECTION (45°)
BRANC…