This document is a state and local contract indefinite delivery vehicle for general maintenance services, specifically Contract 115-26, covering the Central Office and Districts 5, 9, 10, and 11 in Ohio. The contract is awarded to Goodin Building, a construction services vendor, and involves multiple Ohio counties including Franklin, Coshocton, Fairfield, Guernsey, Knox, Licking, Muskingum, Perry, Adams, Brown, Highland, Jackson, Lawrence, Pike, Ross, Scioto, Belmont, Carroll, Columbiana, Harrison, Holmes, Jefferson, and Tuscarawas.

The contract establishes standardized labor rates and equipment rental pricing for various construction disciplines and equipment types. Labor rates are consistently set around $85-$95 per hour for trades like carpenters, electricians, plumbers, and heavy equipment operators, with a 100% overhead rate. Equipment rental rates are provided for a wide range of machinery including skid steer loaders, excavators, work trucks, dump trucks, trailers, man lifts, welders, and generators, with daily and weekly rental options. The contract allows for a 15% markup on materials, and differentiates between projects under and over $75,000 in terms of prevailing wage requirements. The pricing structure appears designed to provide flexible, transparent pricing for maintenance and construction services across multiple Ohio districts.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

References

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
Vendor References
Vendor Name:Goodin Building
Submit below the the name, email address, organization name, address, telephone numbers of at least three (3) references with whom they have provided public improvement and emergency maintenance and/or repairs to in the last five (5) years (see Section 11 of the Specifications).
NameEmail AddressOrganizationAddressTelephone Number
Tim MartyTimothy.Marty@dot.ohio.govODOT Dist 10338 Muskingum Drive, Marietta, Ohio 45750(p)740.568.3924
MICHAEL TOMEtome@ohio.eduOhio University Design and construction79 SOUTH COURT STREET ,Athens OH 45710740 593 9567
Jim Thomasjimt@bdtaid.comBDT Arch26 E. Park Dr., Athens, OH 45701OFFICE 740-592-2420

Vendor Contacts

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
Vendor Contacts
Vendor Name:Goodin Building
Position/FunctionNameEmail AddressTelephone NumberAlternate/Other Telephone Number
OwnerJohn P Goodingoodinbuilding@gmail.com7405900792
SuperintdentKeith Barnhartkbarnhart74@yahoo.com7405910711

mailto:goodinbuilding@gmail.com CO Labor

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
Central Office Project Labor Rates and Material Markup Pricing
These wage rates are applicable to projects with a total cost of less than $75,000
See Section 7.5 of the Specifications for payment of State Prevailing Wages for projects with a total cost over $75,000
Vendor Name:Goodin Building
Construction DisciplineCarpenterJourneyman ElectricianApprentice ElectricianPlumberPainterPlasterer/Drywall FinisherMasonCement FinisherLaborerRooferHeavy Equipment OperatorIron WorkerSupervisor
Item Number12345678910111213
Franklin County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
For projects subject to prevailing wages, the vendor shall pay the awarded vendor the appropriate prevailing wage rate plus the % of bid rates allotted for OverheadITEM 14% of Bid Rates for Overhead100.00%
All parts supplied by the vendor shall be considered "on contract". The Department will pay the awarded vendor the actual cost for all parts utilized in the performance of this contract, plus the vendor specified markup not to exceed 15%ITEM 15Parts % Markup (no more than 15%)15.00%

D5 Labor

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
DISTRICT 5 Project Labor Rates and Material Markup Pricing
These wage rates are applicable to projects with a total cost of less than $75,000
See Section 7.5 of the Specifications for payment of State Prevailing Wages for projects with a total cost over $75,000
Vendor Name:Goodin Building
Construction DisciplineCarpenterJourneyman ElectricianApprentice ElectricianPlumberPainterPlasterer/Drywall FinisherMasonCement FinisherLaborerRooferHeavy Equipment OperatorIron WorkerSupervisor
Item Number12345678910111213
Coshocton County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Fairfield County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Guernsey County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Knox County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Licking County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Muskingum County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Perry County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
For projects subject to prevailing wages, the vendor shall pay the awarded vendor the appropriate prevailing wage rate plus the % of bid rates allotted for OverheadITEM 14% of Bid Rates for Overhead100.00%
All parts supplied by the vendor shall be considered "on contract". The Department will pay the awarded vendor the actual cost for all parts utilized in the performance of this contract, plus the vendor specified markup not to exceed 15%ITEM 15Parts % Markup (no more than 15%)15.00%

CO Equipment

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
CENTRAL OFFICE VENDOR OWNED EQUIPMENT RATES
Vendor Name:Goodin Building
County Where Equipment Will Be UtilizedFRANKLIN
Equipment DescriptionEQUIPMENT RATES INCLUDING MOBILIZATION WITHOUT OPERATOR
Skid Steer LoaderHourly$0.00
Daily$325.00
Weekly$975.00
mini excavator up to 12kHourly$0.00
Daily$450.00
Weekly$1,225.00
small excavator up to 16kHourly$0.00
Daily$785.00
Weekly$2,400.00
large excavtor up tp 24 kHourly$0.00
Daily$3,150.00
Weekly$9,200.00
1 ton work truckHourly$0.00
Daily$225.00
Weekly$840.00
3/4 ton work truckHourly$0.00
Daily$165.00
Weekly$425.00
2 ton work truckHourly$0.00
Daily$345.00
Weekly$1,365.00
single axle dump truckHourly$185.00
Daily$650.00
Weekly$2,589.00
tandem axle dump truckHourly$225.00
Daily$950.00
Weekly$3,600.00
10k trailerHourly$0.00
Daily$275.00
Weekly$750.00
20 k trailerHourly$0.00
Daily$485.00
Weekly$1,500.00
24' electric man liftHourly$0.00
Daily$365.00
Weekly$1,280.00
40' articulating man liftHourly$0.00
Daily$1,065.00
Weekly$4,250.00
welderHourly$0.00
Daily$325.00
Weekly$1,250.00
8k watt geneartorHourly$0.00
Daily$225.00
Weekly$800.00
concrete coring rigHourly$0.00
Daily$500.00
Weekly$1,850.00

D5 Equipment

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
DISTRICT 5 VENDOR OWNED EQUIPMENT RATES
Vendor Name:Goodin Building
County Where Equipment Will Be UtilizedCOSHOCTONFAIRFIELDGUERNSEYKNOXLICKINGMUSKINGUMPERRY
Equipment DescriptionEQUPMENT RATES INCLUDING MOBILIZATION WITHOUT OPERATOR
Skid Steer LoaderHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$325.00$325.00$325.00$325.00$325.00$325.00$325.00
Weekly$975.00$975.00$975.00$975.00$975.00$975.00$975.00
mini excavator up to 12kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$450.00$450.00$450.00$450.00$450.00$450.00$450.00
Weekly$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00
small excavator up to 16kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$785.00$785.00$785.00$785.00$785.00$785.00$785.00
Weekly$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00
large excavtor up tp 24 kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00
Weekly$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00
1 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Weekly$840.00$840.00$840.00$840.00$840.00$840.00$840.00
3/4 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$165.00$165.00$165.00$165.00$165.00$165.00$165.00
Weekly$425.00$425.00$425.00$425.00$425.00$425.00$425.00
2 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$345.00$345.00$345.00$345.00$345.00$345.00$345.00
Weekly$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00
single axle dump truckHourly$185.00$185.00$185.00$185.00$185.00$185.00$185.00
Daily$650.00$650.00$650.00$650.00$650.00$650.00$650.00
Weekly$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00
tandem axle dump truckHourly$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Daily$950.00$950.00$950.00$950.00$950.00$950.00$950.00
Weekly$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00
10k trailerHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$275.00$275.00$275.00$275.00$275.00$275.00$275.00
Weekly$750.00$750.00$750.00$750.00$750.00$750.00$750.00
20 k trailerHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$485.00$485.00$485.00$485.00$485.00$485.00$485.00
Weekly$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00
24' electric man liftHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$365.00$365.00$365.00$365.00$365.00$365.00$365.00
Weekly$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00
40' articulating man liftHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00
Weekly$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00
welderHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$325.00$325.00$325.00$325.00$325.00$325.00$325.00
Weekly$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00
8k watt geneartorHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Weekly$800.00$800.00$800.00$800.00$800.00$800.00$800.00
concrete coring rigHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$500.00$500.00$500.00$500.00$500.00$500.00$500.00
Weekly$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00

D9 Labor

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
DISTRICT 9 Project Labor Rates and Material Markup Pricing
These wage rates are applicable to projects with a total cost of less than $75,000
See Section 7.5 of the Specifications for payment of State Prevailing Wages for projects with a total cost over $75,000
Vendor Name:Goodin Building
Construction DisciplineCarpenterJourneyman ElectricianApprentice ElectricianPlumberPainterPlasterer/Drywall FinisherMasonCement FinisherLaborerRooferHeavy Equipment OperatorIron WorkerSupervisor
Item Number12345678910111213
Adams County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Brown County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Highland County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Jackson County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Lawrence County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Pike County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Ross County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Scioto County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
For projects subject to prevailing wages, the vendor shall pay the awarded vendor the appropriate prevailing wage rate plus the % of bid rates allotted for OverheadITEM 14% of Bid Rates for Overhead100.00%
All parts supplied by the vendor shall be considered "on contract". The Department will pay the awarded vendor the actual cost for all parts utilized in the performance of this contract, plus the vendor specified markup not to exceed 15%ITEM 15Parts % Markup (no more than 15%)15.00%

D9 Equipment

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
DISTRICT 9 VENDOR OWNED EQUIPMENT RATES
Vendor Name:Goodin Building
County Where Equipment Will Be UtilizedADAMSBROWNHIGHLANDJACKSONLAWRENCEPIKEROSSSCIOTO
Equipment DescriptionEQUPMENT RATES INCLUDING MOBILIZATION WITHOUT OPERATOR
Skid Steer LoaderHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$325.00$325.00$325.00$325.00$325.00$325.00$325.00$325.00
Weekly$975.00$975.00$975.00$975.00$975.00$975.00$975.00$975.00
mini excavator up to 12kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$450.00$450.00$450.00$450.00$450.00$450.00$450.00$450.00
Weekly$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00
small excavator up to 16kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$785.00$785.00$785.00$785.00$785.00$785.00$785.00$785.00
Weekly$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00
large excavtor up tp 24 kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00
Weekly$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00
1 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$225.00$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Weekly$840.00$840.00$840.00$840.00$840.00$840.00$840.00$840.00
3/4 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$165.00$165.00$165.00$165.00$165.00$165.00$165.00$165.00
Weekly$425.00$425.00$425.00$425.00$425.00$425.00$425.00$425.00
2 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$345.00$345.00$345.00$345.00$345.00$345.00$345.00$345.00
Weekly$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00
single axle dump truckHourly$185.00$185.00$185.00$185.00$185.00$185.00$185.00$185.00
Daily$650.00$650.00$650.00$650.00$650.00$650.00$650.00$650.00
Weekly$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00
tandem axle dump truckHourly$225.00$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Daily$950.00$950.00$950.00$950.00$950.00$950.00$950.00$950.00
Weekly$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00
10k trailerHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$275.00$275.00$275.00$275.00$275.00$275.00$275.00$275.00
Weekly$750.00$750.00$750.00$750.00$750.00$750.00$750.00$750.00
20 k trailerHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$485.00$485.00$485.00$485.00$485.00$485.00$485.00$485.00
Weekly$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00
24' electric man liftHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$365.00$365.00$365.00$365.00$365.00$365.00$365.00$365.00
Weekly$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00
40' articulating man liftHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00
Weekly$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00
welderHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$325.00$325.00$325.00$325.00$325.00$325.00$325.00$325.00
Weekly$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00
8k watt geneartorHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$225.00$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Weekly$800.00$800.00$800.00$800.00$800.00$800.00$800.00$800.00
concrete coring rigHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$500.00$500.00$500.00$500.00$500.00$500.00$500.00$500.00
Weekly$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00

D10 Labor

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
DISTRICT 10 Project Labor Rates and Material Markup Pricing
These wage rates are applicable to projects with a total cost of less than $75,000
See Section 7.5 of the Specifications for payment of State Prevailing Wages for projects with a total cost over $75,000
Vendor Name:Goodin Building
Construction DisciplineCarpenterJourneyman ElectricianApprentice ElectricianPlumberPainterPlasterer/Drywall FinisherMasonCement FinisherLaborerRooferHeavy Equipment OperatorIron WorkerSupervisor
Item Number12345678910111213
Athens County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Gallia County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Hocking County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Meigs County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Monroe County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Morgan County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Noble County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Vinton County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Washington County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
For projects subject to prevailing wages, the vendor shall pay the awarded vendor the appropriate prevailing wage rate plus the % of bid rates allotted for OverheadITEM 14% of Bid Rates for Overhead100.00%
All parts supplied by the vendor shall be considered "on contract". The Department will pay the awarded vendor the actual cost for all parts utilized in the performance of this contract, plus the vendor specified markup not to exceed 15%ITEM 15Parts % Markup (no more than 15%)15.00%

D10 Equipment

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
DISTRICT 10 VENDOR OWNED EQUIPMENT RATES
Vendor Name:Goodin Building
County Where Equipment Will Be UtilizedATHENSGALLIAHOCKINGMEIGSMONROEMORGANNOBLEVINTONWASHINGTON
Equipment DescriptionEQUPMENT RATES INCLUDING MOBILIZATION WITHOUT OPERATOR
Skid Steer LoaderHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$325.00$325.00$325.00$325.00$325.00$325.00$325.00$325.00$325.00
Weekly$975.00$975.00$975.00$975.00$975.00$975.00$975.00$975.00$975.00
mini excavator up to 12kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$450.00$450.00$450.00$450.00$450.00$450.00$450.00$450.00$450.00
Weekly$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00
small excavator up to 16kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$785.00$785.00$785.00$785.00$785.00$785.00$785.00$785.00$785.00
Weekly$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00
large excavtor up tp 24 kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00
Weekly$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00
1 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$225.00$225.00$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Weekly$840.00$840.00$840.00$840.00$840.00$840.00$840.00$840.00$840.00
3/4 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$165.00$165.00$165.00$165.00$165.00$165.00$165.00$165.00$165.00
Weekly$425.00$425.00$425.00$425.00$425.00$425.00$425.00$425.00$425.00
2 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$345.00$345.00$345.00$345.00$345.00$345.00$345.00$345.00$345.00
Weekly$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00
single axle dump truckHourly$185.00$185.00$185.00$185.00$185.00$185.00$185.00$185.00$185.00
Daily$650.00$650.00$650.00$650.00$650.00$650.00$650.00$650.00$650.00
Weekly$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00
tandem axle dump truckHourly$225.00$225.00$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Daily$950.00$950.00$950.00$950.00$950.00$950.00$950.00$950.00$950.00
Weekly$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00
10k trailerHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$275.00$275.00$275.00$275.00$275.00$275.00$275.00$275.00$275.00
Weekly$750.00$750.00$750.00$750.00$750.00$750.00$750.00$750.00$750.00
20 k trailerHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$485.00$485.00$485.00$485.00$485.00$485.00$485.00$485.00$485.00
Weekly$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00
24' electric man liftHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$365.00$365.00$365.00$365.00$365.00$365.00$365.00$365.00$365.00
Weekly$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00
40' articulating man liftHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00
Weekly$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00
welderHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$325.00$325.00$325.00$325.00$325.00$325.00$325.00$325.00$325.00
Weekly$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00
8k watt geneartorHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$225.00$225.00$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Weekly$800.00$800.00$800.00$800.00$800.00$800.00$800.00$800.00$800.00
concrete coring rigHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$500.00$500.00$500.00$500.00$500.00$500.00$500.00$500.00$500.00
Weekly$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00

D11 Labor

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
DISTRICT 11 Project Labor Rates and Material Markup Pricing
These wage rates are applicable to projects with a total cost of less than $75,000
See Section 7.5 of the Specifications for payment of State Prevailing Wages for projects with a total cost over $75,000
Vendor Name:Goodin Building
Construction DisciplineCarpenterJourneyman ElectricianApprentice ElectricianPlumberPainterPlasterer/Drywall FinisherMasonCement FinisherLaborerRooferHeavy Equipment OperatorIron WorkerSupervisor
Item Number12345678910111213
Belmont County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Carroll County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Columbiana County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Harrison County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Holmes County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Jefferson County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
Tuscarawas County Standard Wage Rate$ 85.00$ 85.00$ 70.00$ 95.00$ 85.00$ 90.00$ 90.00$ 95.00$ 85.00$ 90.00$ 90.00$ 85.00$ 75.00
For projects subject to prevailing wages, the vendor shall pay the awarded vendor the appropriate prevailing wage rate plus the % of bid rates allotted for OverheadITEM 14% of Bid Rates for Overhead100.00%
All parts supplied by the vendor shall be considered "on contract". The Department will pay the awarded vendor the actual cost for all parts utilized in the performance of this contract, plus the vendor specified markup not to exceed 15%ITEM 15Parts % Markup (no more than 15%)15.00%

D11 Equipment

115-26 CENTRAL OFFICE, DISTRICT 5, DISTRICT 9, DISTRICT 10 AND DISTRICT 11 GENERAL MAINTENANCE CONTRACT
DISTRICT 11 VENDOR OWNED EQUIPMENT RATES
Vendor Name:Goodin Building
County Where Equipment Will Be UtilizedBELMONTCARROLLCOLUMBIANAHARRISONHOLMESJEFFERSONTUSCARAWAS
Equipment DescriptionEQUPMENT RATES INCLUDING MOBILIZATION WITHOUT OPERATOR
Skid Steer LoaderHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$325.00$325.00$325.00$325.00$325.00$325.00$325.00
Weekly$975.00$975.00$975.00$975.00$975.00$975.00$975.00
mini excavator up to 12kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$450.00$450.00$450.00$450.00$450.00$450.00$450.00
Weekly$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00$1,225.00
small excavator up to 16kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$785.00$785.00$785.00$785.00$785.00$785.00$785.00
Weekly$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00$2,400.00
large excavtor up tp 24 kHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00
Weekly$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00$9,200.00
1 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Weekly$840.00$840.00$840.00$840.00$840.00$840.00$840.00
3/4 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$165.00$165.00$165.00$165.00$165.00$165.00$165.00
Weekly$425.00$425.00$425.00$425.00$425.00$425.00$425.00
2 ton work truckHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$345.00$345.00$345.00$345.00$345.00$345.00$345.00
Weekly$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00$1,365.00
single axle dump truckHourly$185.00$185.00$185.00$185.00$185.00$185.00$185.00
Daily$650.00$650.00$650.00$650.00$650.00$650.00$650.00
Weekly$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00$2,589.00
tandem axle dump truckHourly$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Daily$950.00$950.00$950.00$950.00$950.00$950.00$950.00
Weekly$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00$3,600.00
10k trailerHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$275.00$275.00$275.00$275.00$275.00$275.00$275.00
Weekly$750.00$750.00$750.00$750.00$750.00$750.00$750.00
20 k trailerHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$485.00$485.00$485.00$485.00$485.00$485.00$485.00
Weekly$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00
24' electric man liftHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$365.00$365.00$365.00$365.00$365.00$365.00$365.00
Weekly$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00
40' articulating man liftHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00$1,065.00
Weekly$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00$4,250.00
welderHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$325.00$325.00$325.00$325.00$325.00$325.00$325.00
Weekly$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00
8k watt geneartorHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$225.00$225.00$225.00$225.00$225.00$225.00$225.00
Weekly$800.00$800.00$800.00$800.00$800.00$800.00$800.00
concrete coring rigHourly$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Daily$500.00$500.00$500.00$500.00$500.00$500.00$500.00
Weekly$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00$1,850.00

General Maintenance Worksheet

Labor
HoursRateTotal
Total Labor0$0.00
Rented Equipment
Total CostTotal

Total Rented Equipment $0.00

Vendor Owned Equipment
QtyRateTotal

Total Owned Equipment $0.00

MaterialsMarkup %15.00%
QtyCostExt. CostMarkup $Total
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
Total Materials$0.00$0.00
Subcontractors
WorkVendorTotal
Total Subcontractors$0.00
Mobilization/Service Call Fee
QtyCostTotal
$0.00
$0.00
Total Mobilization/Service Call Fee$0.00
TOTAL PROJECT AMOUNT$0.00