1. Statement of Work.pdf
PDF 247 KB Posted
- Attached to
- 127EAW23R0018 - STF Window Replacements Federal contract opportunity
- Solicitation number
- 127EAW23R0018
- Issued by
- Department of Agriculture Forest Service
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A00002 - RFI Repsonses.pdf | ||
| RFI Official Responses - 2.pdf | ||
| RFI_Interior Photos.pdf | ||
| 1. Statement of Work - Revision 001.pdf | ||
| A00001 - SOW Revision and RFI Repsonses.pdf | ||
| RFI Official Responses - 1.pdf | ||
| 4. Fire Plan.pdf | ||
| 6. RFI Form.docx | DOCX document | |
| 5. Davis-Bacon Act WD # CA20230018.pdf | ||
| 127EAW23R0018.pdf | ||
| 3. Work Plans & Drawings.pdf | ||
| 2. Schedule.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quarters Window Replacement February 16, 2023
CONSTRUCTION SPECIFICATIONS FOR QUARTERS WINDOW
REPLACEMENT
UNITED STATES DEPARTMENT OF AGRICULTURE
FOREST SERVICE
STANISLAUS NATIONAL FOREST
TABLE OF CONTENTS
DIVISION 1 – GENERAL REQUIREMENTS
01010 – SUMMARY OF WORK 2
01040 – PROJECT COORDINATION 4
01060 – REGULATORY REQUIREMENTS 6
01300 – SHOP DRAWINGS AND SUBMITTALS 7
01401 – QUALITY CONTROL AND QUANTITY MEASUREMENT 9
01800 – PROJECT CLEAN UP 10
01900 – MOBILIZATION 11
DIVISION 6 – WOOD AND PLASTICS
06200 – FINISH CARPENTRY 12
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
07190 – BUILDING PAPER 16
07921 – JOINT SEALANTS 18
DIVISION 8 – DOORS AND WINDOWS
08561 – VINYL WINDOWS 23
08800 – GLASS AND GLAZING 24
SECTION 01010 – SUMMARY OF WORK
PART 1 – GENERAL
1.01 PROJECT DESCRIPTION
A. This project consists of the replacement of windows on multiple United States
Department of Agriculture Forest Service residential facilities.
B. The work consists of window replacements on 3 separate buildings, as well as option item window replacements on 5 additional buildings.
C. The work includes vinyl windows, hardware, glazing, finishing, and minor carpentry.
Finishing work shall include replacement and installation of all window finishes and restoration to previous condition (including mounting, sealing, priming, painting and coating).
D. The work shall conform to the specifications and the Contract Drawings identified on the following index of drawings:
G-01 Cover Sheet
G-02 General Notes and Schedule of Items
G-03 Overview
C-01 Summit – 1017
C-02 Hathaway – 1004
C-03 Hathaway – 1312
C-04 Option: Groveland – 1001
C-05 Option: Groveland – 1006
C-06 Option: Groveland – 1014 &1015
C-07 Option: Groveland – 1404
1.02 METHOD OF MEASUREMENT
A. Units: Items of work done under this Contract will be paid per the quantities shown in the
Schedule of Items.
1.03 BASIS OF PAYMENT
A. Payment: Payment will be made at the Contract price, as indicated in the Bid Schedule, and will include full compensation for the work described in the Contract. Payment will be made under:
ITEM NO. PAY ITEM PAY UNIT
0001 MOBILIZATION LS
0002 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 3'0" X 3'0" EA
0003 WINDOW, WHITE VINYL, FIXED: 3'6" X 2'0" EA
0004 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'0" X 5'0" EA
0005 WINDOW, WHITE VINYL, SINGLE HUNG: 2'0" X 3'0" EA
0006 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'0" X 3'6" EA
0007 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'0" X 4'0" EA
0008 WINDOW, WHITE VINYL, FIXED CENTER W/DUAL SLIDING: 5'6" X 4'6" EA
0009 WINDOW, WHITE VINYL, SINGLE HUNG: 2'0" X 3'6" EA
0010 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'0" X 3'0" EA
0011 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'0" X 1'0" EA
0012 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 3'0" X 3'0" EA
0013 WINDOW, WHITE VINYL, SINGLE HUNG: 2'3" X 4'6" EA
0014 WINDOW, WHITE VINYL, SINGLE HUNG: 3'0" X 4'6" 0
0015 WINDOW, WHITE VINYL, SINGLE HUNG: 2'3" X 3'0" EA
0016 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 2'9" X 2'9" EA
O0001 WINDOW, WHITE VINYL, FIXED CENTER W/DUAL SLIDING: 6'9" X 4'3" EA
O0002 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'9" X 4'3" EA
O0003 WINDOW, WHITE VINYL, SINGLE HUNG: 2'1" X 3'3" EA
O0004 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 3'5" X 3'3" EA
O0005 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 3'5" X 4'3" EA
O0006 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'0" X 3'0" EA
O0007 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 2'1" X 3'0" EA
O0008 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'0" X 5'0" EA
O0009 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 5'0" X 4'0" EA
O0010 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 3'0" X 3'0" EA
O0011 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'8" X 2'8" EA
O0012 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'0" X 1'0" EA
O0013 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 2'0" X 2'0" EA
O0014 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 2'0" X 3'0" EA
O0015 WINDOW, WHITE VINYL, HORIZONTAL SLIDING: 4'0" X 4'0" EA
1.04 CONTRACTOR USE OF PREMISES
A. General: During the construction period the Contractor will have full use of the barracks site for construction operations. The Contractor's use of the premises is limited to the barracks site and adjacent areas agreed upon by the Contracting Officer for storage of equipment and materials. No overnight camping by the Contractor’s personnel will be allowed.
B. Sanitation: Sanitation facilities are available at each site.
C. Utilities: Water is available and may be used by the Contractor’s personnel. Electrical power is available at the construction site.
D. While performing the work the Contractor shall take reasonable precautions to protect adjacent properties from damage. The Contractor at no additional cost to the Government shall restore any damage or injury caused by the Contractor in the course of this work.
PART 2 – PRODUCTS
NOT APPLICABLE
PART 3 – EXECUTION
3.01 REQUIREMENTS OF REGULATORY AGENCIES
A. All work performed shall comply with health, safety, and fire codes, OSHA regulations, and/or applicable regulations established by local, county, and state codes.
END OF SECTION 01010
SECTION 01040 – PROJECT COORDINATION
1.01 SCOPE
A. This Section specifies administrative and supervisory requirements necessary for Project coordination including, but not necessarily limited to:
1. Coordination.
2. Contractor's personnel.
3. General installation provisions.
4. Cleaning and protection.
1.02 COORDINATION
A. Coordination: Coordinate construction activities included under various Sections of these
Specifications to assure efficient and orderly installation of each part of the Work.
Coordinate construction operations included under different Sections of the
Specifications that are dependent upon each other for proper installation, connection, and operation.
1. Where installation of one part of the Work is dependent on installation of other components, either before or after its own installation, schedule construction activities in the sequence required to obtain the best results.
B. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.
1.03 SUBMITTALS
A. Coordination Drawings: Prepare and submit coordination Drawings where close and careful coordination is required for installation of products and materials fabricated off-site by separate entities, and where limited space availability necessitates maximum utilization of space for efficient installation of different components.
1. Indicate required installation sequences.
2. Comply with requirements contained in Section "Submittals."
PART 2 – PRODUCTS
NOT APPLICABLE
PART 3 – EXECUTION
3.01 GENERAL INSTALLATION PROVISIONS
A. Manufacturer's Instructions: Comply with manufacturer's installation instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in Contract Documents.
B. Inspect materials or equipment immediately upon delivery and again prior to installation.
Reject damaged and defective items.
C. Provide attachment and connection devices and methods necessary for securing Work.
Secure Work true to line and level. Allow for expansion and building movement.
D. Visual Effects: Provide uniform joint widths in exposed Work. Arrange joints in exposed
Work to obtain the best visual effect. Refer questionable choices to the Contracting
Officer for final decision.
E. Recheck measurements and dimensions, before starting each installation.
F. Install each component during weather conditions and Project status that will ensure the best possible results. Isolate each part of the completed construction from incompatible material as necessary to prevent deterioration.
3.02 CLEANING AND PROTECTION
A. During handling and installation, clean and protect construction in progress and adjoining materials in place. Apply protective covering where required to ensure protection from damage or deterioration.
B. Clean and maintain completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.
END OF SECTION 01040
SECTION 01060 – REGULATORY REQUIREMENTS
1.01 SCOPE
A. This section describes the codes and standards which apply to the work in this contract.
Additional codes and standard may be cited in sections to which they apply.
1.02 CODES AND STANDARDS
A. The following codes and standards shall apply to the work in this contract:
1. International Building Code (IBC)
2. American Disabilites Act (ADA)/American Barriers Act (ABA)
3. American Society for Testing and Materials (ASTM)
4. Underwriter's Laboratories, (UL)
B. Unless otherwise specified in this contract, reference to a specific standard or specification shall mean the latest edition or amendment in effect on the date of the invitation to bid.
PART 2 – PRODUCTS
NOT APPLICABLE
PART 3 – EXECUTION
NOT APPLICABLE
END OF SECTION 01060
SECTION 01300 – SHOP DRAWINGS AND SUBMITTALS
1.01 SCOPE
A. Perform all work necessary and required for the construction of the project as indicated.
Such work includes but is not limited to the following:
1. Shop Drawings
2. Catalog Data
1.02 SUBMITTALS
A. Submittals shall include all pertinent data required to understand the quality of components, dimensional relationships, integration with other materials, assembly techniques, structural aspects, color, finish, texture, and other such characteristics as may be necessary to fully describe the item and its intended use.
PART 2 – PRODUCTS
NOT APPLICABLE
PART 3 – EXECUTION
3.01 SUBMITTALS
A. Submittals and shop drawings shall be submitted in a timely fashion to allow 21 days for review by the Government. "No work shall begin until shops drawings and submittals are approved".
3.02 SHOP DRAWINGS
A. Original Submittal: One copy of all shop drawings shall be submitted for approval as required under 3.01 above prior to fabrication, installation or order placement to allow for checking and coordination.
B. Resubmittal: When a resubmittal is required, one print so indicating will be returned to the Contractor. After revision of the original, a new copy shall be submitted for approval.
C. Approval: Once approved, stamped documents shall be returned to the Contractor and shall be complied with as noted. Variation from the approved documents shall be likewise submitted and approved before being carried out.
3.03 CATALOG DATA
A. Submittals: One copy of catalog data is required for the original submittal and each resubmittal. Catalog data shall be submitted along with shop drawings. One copy will be returned unless additional copies are requested.
B. Data: Each submittal shall have all pertinent data contained therein that is applicable to the item submitted for approval.
3.04 IDENTIFICATION
A. Catalog Data: Each separate catalog brochure or page submitted shall have the identification shown. Catalog of brochures submitted containing multiple items for approval need have only cover identification. In such cases the identification shall include page and catalog item numbers.
B. In the event one or more of the multiple items are not approved in any submittal, the additional copies required will not be requested until all items are approved.
END OF SECTION 01300
SECTION 01401 – QUALITY CONTROL AND QUANTITY MEASUREMENT
1.01 SCOPE
A. This work shall consist of providing quality control in conformance with the Inspection of Construction provisions of this contract to ensure compliance with the drawings, specifications, and provisions of the contract, and measuring the quantities of completed work in conformance with the provisions of the applicable specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of this specification.
1.02 MEASUREMENT AND PAYMENT
A. No payment under this section.
PART 2 – PRODUCTS
NOT APPLICABLE
PART 3 – EXECUTION
3.01 QUALITY CONTROL SYSTEM AND QUANTITY MEASUREMENT
A. The Contractor shall provide and maintain a quality control system that will ensure that all services, supplies, and construction required under this contract conform to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all supplies, services, and construction conform to the contract requirements.
B. The Contractor shall also perform, or cause to be performed, all measurement of quantities of materials incorporated into the work or work processes that are to be measured under the provisions of the contract.
3.02 RECORDS OF INSPECTION, TESTS, AND MEASUREMENT
A. As-built Drawings - The Contractor shall maintain a set of the contract drawings depicting as-built conditions. These drawings shall be maintained in a current condition and shall be available for review. All variations from contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Engineer.
3.03 CERTIFICATIONS AND MEASUREMENTS
A. Offsite Produced Materials - The Contractor shall furnish certificates executed by the manufacturer, supplier, or vendor, stipulating that all offsite produced materials incorporated into the work meet the applicable requirements shown on the Drawings or stated in the specifications. Incidental purchases needed to remedy minor shortages of material shall be certified by the Contractor.
END OF SECTION 01401
SECTION 01800 – PROJECT CLEAN UP
1.01 DESCRIPTION
A. This section covers the disposal of excess material from any operation in which waste is generated.
1.02 MEASUREMENT AND PAYMENT
A. No separate payment shall be made for work specified in this section. Compensation for this work will be considered included in the payment for the completed project.
PART 2 – PRODUCTS
NOT APPLICABLE
PART 3 – EXECUTION
3.01 WORKMANSHIP
A. The Contractor shall provide refuse containers and proper disposal for solid wastes generated by Contractor’s employees.
B. All debris and unused material shall be removed from the site. All debris shall be disposed of off National Forest land in accordance with local regulations. Site shall be restored to as near its original condition as possible.
C. At substantial completion the project areas shall be swept clean of all debris and dust.
Windows shall be cleaned of all dust and marks.
END OF SECTION 01800
SECTION 01900 – MOBILIZATION
1.01 SCOPE
A. This work consists of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.
1.02 MEASUREMENT AND PAYMENT
A. The accepted quantities will be paid for at the contract unit price for Item No. 01, Mobilization.
B. Progress payments will be made as follows:
1. When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.
2. When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.
3. Upon completion of all work on the project, any unpaid amount for Item 01, Mobilization, will be paid.
C. The total of all payments will not exceed the original contract amount for Item 01, Mobilization.
PART 2 – PRODUCTS
NOT APPLICABLE
PART 3 – EXECUTION
NOT APPLICABLE
END OF SECTION 01900
SECTION 06200 – FINISH CARPENTRY
1.01 SCOPE
A. This Section includes the following:
1. Exterior standing and running trim.
2. Interior standing and running trim.
B. Related Sections: The following Sections contain requirements that relate to this Section:
1. Division 7 Section "Joint Sealants" for sealants.
2. Division 9 Section "Painting" for back priming and finishing of finish carpentry.
1.02 DELIVERY, STORAGE, AND HANDLING
A. Delivery and Storage: Keep materials under cover and dry. Protect against exposure to weather and contact with damp or wet surfaces. Stack lumber as well as plywood and other panels. Provide for air circulation within and around stacks and under temporary coverings including polyethylene and similar materials.
1.03 PROJECT CONDITIONS
A. Environmental Conditions: Obtain and comply with finish carpentry manufacturer's and installer's coordinated advice for optimum temperature and humidity conditions for finish carpentry during its storage and installation.
B. Weather Conditions: Proceed with finish carpentry only when existing and forecasted weather conditions will permit exterior finish carpentry to be installed in compliance with manufacturer's recommendations and when substrate is completely dry.
PART 2 – PRODUCTS
2.01 MATERIALS, GENERAL
A. Softwood Lumber Standards: Comply with PS 20 "American Softwood Lumber
Standard" for lumber and with applicable grading rules of inspection agencies certified by American Lumber Standards Committee Board of Review.
B. Hardwood Lumber Standards: Comply with National Hardwood Lumber Association
(NHLA) rules.
C. Inspection Agencies: Inspection agencies and the abbreviations used to reference them with lumber grades and species include the following:
1. WCLIB - West Coast Lumber Inspection Bureau.
2. WWPA - Western Wood Products Association.
D. Grade Stamps: Provide lumber with each piece factory-marked with grade stamp of inspection agency evidencing compliance with grading rule requirements and identifying grading agency, grade, species, moisture content at time of surfacing, and mill.
2.02 EXTERIOR FINISH CARPENTRY
A. Standing and Running Trim: For trim and rails in form of boards and worked products, provide lumber complying with the following requirements including those of the grading agency listed with species.
1. Species: Redwood.
a. Redwood Inspection Services Grade: Construction Heart.
2. Texture: Surfaced (smooth).
2.03 INTERIOR FINISH CARPENTRY
A. Standing and Running Trim: For trim in form of boards and worked products, provide lumber complying with the following requirements.
1. Species: Western Red Cedar; WWPA or
2. Species: Douglas Fir; WWPA.
3. Select Grade: B and Better.
4. Finish Grade: Prime.
5. Texture: Surfaced (smooth).
6. Lumber for Transparent Finish (Stained or Clear): Solid lumber stock.
7. Lumber for Painted Finish: Glued-up lumber or solid lumber stock.
2.04 MISCELLANEOUS MATERIALS
A. Fasteners for Exterior Finish Carpentry: Stainless steel, noncorrosive aluminum or hot-dip galvanized nails, in sufficient length to penetrate minimum of 1-1/2 inches into substrate unless recommended otherwise by manufacturer.
1. Provide prefinished nails for face nailing of material to receive stain in color to match where face nailing is unavoidable.
2. Countersink nails and fill surface where face nailing is unavoidable.
B. Fasteners for Interior Finish Carpentry: Nails, screws, and other anchoring devices of type, size, material, and finish required for application indicated to provide secure attachment, concealed where possible.
1. Countersink nails, fill surface flush, and sand where face nailing is unavoidable.
2. Where finish carpentry materials are exposed in areas of high humidity, provide fasteners and anchorages with hot-dip galvanized coating complying with ASTM A 153.
C. Adhesives: Comply with manufacturer's recommendations for adhesives.
2.05 FABRICATION
A. Wood Moisture Content: Comply with requirements of specified inspection agencies and manufacturer's recommendations for moisture content of finish carpentry in relation to relative humidity conditions existing during time of fabrication and in installation areas.
Provide finish carpentry with moisture content that is compatible with Project requirements.
B. Fabricate finish carpentry to dimensions, profiles and details indicated.
PART 3 – EXECUTION
3.01 EXAMINATION
A. Examine substrates for compliance with requirements for installation tolerances and other conditions affecting installation and performance of finish carpentry. Do not proceed with installation until unsatisfactory conditions have been corrected.
3.02 PREPARATION
A. Clean substrates of projections and substances detrimental to application.
B. Condition finish carpentry to average prevailing humidity conditions in installation areas before installation for a minimum of 24 hours unless longer conditioning recommended by manufacturer.
3.03 INSTALLATION, GENERAL
A. Do not use finish carpentry materials that are unsound, warped, bowed, twisted, improperly treated or finished, not adequately seasoned, or too small to fabricate with proper jointing arrangements.
1. Do not use manufactured units with defective surfaces, sizes, or patterns.
B. Install finish carpentry plumb, level, true, and aligned with adjacent materials. Use concealed shims where required for alignment.
1. Scribe and cut finish carpentry to fit adjoining work. Refinish and seal cuts as recommended by manufacturer.
2. Install to tolerance of 1/8 inch in 8 feet for plumb and level. Install adjoining finish carpentry with 1/16 inch maximum offset for flush installation and 1/8 inch maximum offset for reveal installation.
3. Coordinate finish carpentry with materials and systems that may be in or adjacent to standing and running trim and rails. Provide cutouts for mechanical and electrical items that penetrate exposed surfaces of trim and rails.
C. Finish in accordance with specified requirements.
D. Refer to Division 9 Sections for final finishing of finish carpentry.
E. Anchor finish carpentry work to anchorage devices or blocking built-in or directly attached to substrates. Secure to grounds, stripping and blocking with countersunk, concealed fasteners and blind nailing as required for a complete installation. Except where prefinished matching fastener heads are required, us fine finishing nail for exposed nailing, countersunk and filled flush with finished surface, and matching final finish where transparent is indicated.
3.04 STANDING AND RUNNING TRIM AND RAILS
A. Install with minimum number of joints practical, using full-length pieces from maximum lengths of lumber available. Stagger joints in adjacent and related standing and running trim and rails. Cope at returns and miter at corners to produce tight-fitting joints with full-surface contact throughout length of joint. Use scarf joints for end-to-end joints. Plane back of casings to provide uniform thickness across joints if required.
1. Drill pilot holes in hardwood prior to nailing or fastening to prevent splitting. Fasten to prevent movement or warping. Countersink nail heads on exposed carpentry work and fill holes.
2. Fit exterior joints to exclude water.
3.05 ADJUSTING
A. Repair damaged or defective finish carpentry where possible to eliminate functional or visual defects. Where not possible to repair, replace finish carpentry. Adjust joinery for uniform appearance.
3.06 CLEANING
A. Clean finish carpentry on exposed and semi exposed surfaces. Touch up factory-applied finishes to restore damaged or soiled areas.
3.07 PROTECTION
A. Provide final protection and maintain conditions that ensure finish carpentry is without damage or deterioration at time of Substantial Completion.
END OF SECTION 06200
SECTION 07190 – BUILDING PAPER
1.01 DESCRIPTIONS
A. Provide self adhering polymer modified bituminous sheet flashing system with low VOC primer and accessories as required for complete watertight seal at window penetrations.
1.02 SECTION REQUIREMENTS
A. Submit Product Data for type of building paper product and accessories specified.
B. Submit shop drawings for metal flashings, as related to underlayment.
1. Clearly indicate general construction, configurations, jointing methods and locations, fastening methods and locations and installation details.
C. Provide for correcting failure of building paper to resist penetration of water.
D. Repair building paper and pay for or replace damaged materials or surfaces.
E. Warranty Period: Two years.
PART 2 – PRODUCTS
2.01 MATERIALS
A. Self-Adhering Polymer Modified Bituminous Sheet Membrane (Water Barrier
Membrane): Conform ASTM D1970.
1. Type: Grace Construction Products/Vycor Ice and Water Shield typical, Vycor Ultra where under metal flashing.
2. Primers and Edge Sealers: Types as recommended by system manufacturer for specific applications and as required to achieve complete watertight installation.
PART 3 – EXECUTION
3.01 PREPARATION
A. Install building paper over surfaces which are dry, free of ridges, warps and voids which could damage paper.
B. Coordinate installation with installation of components and items projecting through building paper.
3.02 TYPICAL UNDERLAYMENT INSTALLATION
A. Install building paper in accordance with recommendations of building paper manufacturer and of manufacturers of products to cover building paper; comply with applicable code requirements.
1. Apply layer of self-adhering polymer modified bituminous sheet material over plywood sheathing at rough openings and outside corners, extending minimum 18-inches from penetrations and corners.
2. Layer: Provide two layers building paper underlayment at siding applications; weatherlap joints.
3. Layer: Provide one layer building paper underlayment at roofing applications; weatherlap joints.
4. Secure underlayment in place, stagger joints between layers; lap ends minimum
6-inches; stagger end joints.
B. Apply lap cement at rate of approximately 1-1/4 gallons per square on underlayment starter strip.
C. Weatherlap items projecting through building paper and seal with plastic cement.
END OF SECTION 07190
SECTION 07921 – JOINT SEALANTS
1.01 SCOPE
A. The scope of this Section includes joint sealants for the following locations:
1. Exterior joints in vertical surfaces and non-traffic horizontal surfaces as indicated below:
a. Perimeter joints at frames of doors and windows.
2. Interior joints in vertical surfaces and horizontal non-traffic surfaces as indicated below:
a. Perimeter joints of exterior openings where indicated.
b. Perimeter joints between interior wall surfaces and frames of interior doors and windows.
B. Related Sections: The following Sections contain requirements that relate to this Section:
1. Section 08800 “Glass and Glazing” for sealants used in glazing.
1.02 SYSTEM PERFORMANCE REQUIREMENTS
A. Provide elastomeric joint sealants that have been produced and installed to establish and to maintain airtight continuous seals.
B. Provide joint sealants for interior applications that have been produced and installed to establish and maintain airtight continuous seals.
1.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 1
Specification Sections.
B. Product data from manufacturers for each joint sealant product required.
1. Certification by joint sealant manufacturer that sealants plus the primers and cleaners required for sealant installation comply with local regulations controlling use of volatile organic compounds.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Deliver materials to Project site in original unopened containers or bundles with labels indicating manufacturer, product name and designation, color, expiration period for use, pot life, curing time, and mixing instruction for multicomponent materials.
B. Store and handle materials in compliance with manufacturer’s recommendations to prevent their deterioration or damage due to moisture, high or low temperatures, contaminants, or other causes.
1.05 PROJECT CONDITIONS
A. Environmental Conditions: Do not proceed with installation of joint sealants under the following conditions:
1. When ambient and substrate temperature conditions are outside the limits permitted by joint sealant manufacturer or below 40 deg F.
2. When joint substrates are wet.
B. Joint Width Conditions: Do not proceed with installation of joint sealants where joint widths are less than allowed by joint sealant manufacturer for application indicated.
C. Joint Substrate Conditions: Do not proceed with installation of joint sealants until contaminants capable of interfering with their adhesion are removed from joint substrates.
PART 2 – PRODUCTS
2.01 MATERIALS, GENERAL
A. Compatibility: Provide joint sealants, joint fillers, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by sealant manufacture based on testing and field experience.
B. Colors: To be as selected by Contracting Officer.
2.02 ELASTOMERIC JOINT SEALANTS
A. Elastomeric Sealant Standard: Provide manufacturer’s standard chemically curing elastomeric sealants that comply with ASTM C 920 and other requirements indicated on each Elastomeric Joint Sealant Data Sheet at the end of this Section, including those requirements referencing ASTM C 920 classifications for Type, Grade, Class, and Uses.
1. Two-Part Nonsag Polysulfide Sealant: Type M; Grade NS; Class 12-1/2; Uses NT, M, G, A and, as applicable to joint substrates indicated, O.
2. One-Part Polysulfide Sealant: Type S; Grade NS; Class 12-1/2; Uses T, M G, A and, as applicable to joint substrates indicated, I.
3. One-part Non-Acid-Curing Silicone Sealant: Type S; Grade NS; Class 25; and complying with the following requirements for Uses, modules and additional joints movement capability.
a. Uses NT, M, G, A and, as applicable to joint substrates indicated, O.
4. One-Part Acid-Curing Silicone Sealant: Type S; Grade NS; Class 25; Uses NT, G, A and, as applicable to joint substrates indicated, O.
5. One-Part Mildew-Resistant Silicone Sealant: Type S; Grade NS; Class 25; Uses NT, G, A, and, as applicable to nonporous joint substrates indicated, O; formulated with fungicide for sealing interior joints with nonporous substrates around showers, sinks and plumbing fixtures.
2.03 LATEX JOINT SEALANTS
A. General: Provide manufacturer's standard one-part, nonsag, mildew-resistant, paintable latex sealant of formulation indicated that is recommended for exposed applications on interior and protected exterior locations and that accommodates indicated percentage change in joint width existing at time of installation without failing either adhesively or cohesively.
B. Acrylic-Emulsion Sealant: Provide product complying with ASTM C 834 that accommodates joint movement of not more than 5 percent in both extension and compression for a total of
10 percent.
C. Silicone Emulsion Sealant: Provide product complying with ASTM C 834 and, except for weight loss measured per ASTM C 792, with ASTM C 920 that accommodates joint movement of not more than 25 percent in both extension and compression for a total of 50 percent.
2.04 JOINT SEALANT BACKING
A. General: Provide sealant backings of material and type that are nonstaining; are compatible with joint substrates, sealants, primers and other joint fillers; and are approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.
B. Bond-Breaker Tape: Polyethylene tape or other plastic tape as recommended by sealant manufacturer for preventing sealant from adhering to rigid, inflexible joint filler materials or joint surfaces at back of joint where such adhesion would result in sealant failure.
Provide self-adhesive tape where applicable.
2.05 MISCELLANEOUS MATERIALS
A. Primer: Material recommended by joint sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint sealant-substrate tests and field tests.
B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials, free of oily residues or other substances capable of staining or harming in any way joint substrates and adjacent nonporous surfaces, and formulated to promote optimum adhesion of sealants with joint substrates.
C. Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.
PART 3 – EXECUTION
3.01 EXAMINATION
A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with requirements for joint configuration, installation tolerances, and other conditions affecting joint sealant performance. Do not proceed with installation of joint sealants until unsatisfactory conditions have been corrected.
3.02 PREPARATION
A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with recommendations of joint sealant manufacturer and the following requirements:
1. Remove all foreign material from joint substrates that could interfere with adhesion of joint sealant, including dust, paints (except for permanent, protective coatings tested and approved for sealant adhesion and compatibility by sealant manufacturer), old joint sealants, oil, grease, waterproofing, water repellents, water, surface dirt, and frost.
2. Clean concrete, masonry and porous joint substrate surfaces by brushing, grinding, blast cleaning, mechanical abrading, or a combination of these methods to produce a clean, sound substrate capable of developing optimum bond with joint sealants. Remove loose particles remaining from above cleaning operations by vacuuming or blowing out joints with oil-free compressed air.
3. Remove laitance and form release agents from concrete.
4. Clean metal, glass, porcelain enamel and nonporous surfaces with chemical cleaners or other means that do not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants.
C. Joint Priming: Prime joint substrates where indicated or where recommended by joint sealant manufacturer. Apply primer to comply with joint sealant manufacturer's recommendations.
Confine primers to areas of joint sealant bond; do not allow spillage or migration onto adjoining surfaces.
D. Masking Tape: Use masking tape where required to prevent contact of sealant with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.
3.03 JOINT DIMENSIONS
A. Butyl Base-Type Sealant: The minimum joint width shall be 1/4 inch, and the depth shall be one to three times the width of the joint, with the maximum depth 3/4 inch.
B. Silicone Rubber, Acrylic and Polyurethane Sealant: The minimum joint width shall be
1/4 inch, and the depth shall be approximately one-half the width but in no case less than
1/4 inch. Other width-to depth ratios shall conform to the following:
If JOINT WIDTH is: JOINT DEPTH shall be
For Nonporous Surfaces Minimum Maximum
1/4" (minimum) 1/4" 1/4"
1/4" to 1/2" 1/2 of width Equal to width
Over 1/2" Not Permitted
For Porous Surfaces
1/4" (minimum) 1/4" 1/4"
1/4" to 1/2" 1/4" Equal to width
1/2" to 1" 1/2" Equal to width
3.04 INSTALLATION OF JOINT SEALANTS
A. General: Comply with joint sealant manufacturer's printed installation instructions applicable to products and applications indicated, except where more stringent requirements apply.
B. Elastomeric Sealant Installation Standard: Comply with recommendations of ASTM C 962 for use of joint sealants as applicable to materials, applications, and conditions indicated.
C. Latex Sealant Installation Standard: Comply with requirements of ASTM C 90 for use of latex sealants.
D. Installation of Sealant Backings: Install sealant backings to comply with the following requirements:
1. Install joint fillers of type indicated to provide support of sealants during application and at position required to produce the cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.
a. Do not leave gaps between ends of joint fillers.
b. Do not stretch, twist, puncture, or tear joint fillers.
c. Remove absorbent joint fillers that have become wet prior to sealant application and replace with dry material.
E. Installation of Sealants: Install sealants by proven techniques that result in sealants directly contacting and fully wetting joint substrates, completely filling recesses provided for each joint configuration, and providing uniform, cross-sectional shapes and depths relative to joint widths that allow optimum sealant movement capability. Install sealants at the same time sealant backings are installed.
F. Tooling of Nonsag Sealants: Immediately after sealant application and prior to time skinning or curing begins, tool sealants to form smooth, uniform beads of configuration indicated, to eliminate air pockets, and to ensure contact and adhesion of sealant with sides of joint. Remove excess sealants from surfaces adjacent to joint. Do not use tooling agents that discolor sealants or adjacent surfaces or are not approved by sealant manufacturer.
1. Provide concave joint configuration per Figure 5A in ASTM C 62, unless otherwise indicated.
3.05 CLEANING
A. Clean off excess sealants or sealant smears adjacent to joints as work progresses by methods and with cleaning materials approved by manufacturers of joint sealants and of products in which joints occur.
3.06 PROTECTION
A. Protect joint sealants during and after curing period from contact with contaminating substances or from damage resulting from construction operations or other causes so that they are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated joint sealants immediately so that any installations with repaired areas are indistinguishable from original work.
END OF SECTION 07921
SECTION 08561 – VINYL WINDOWS
1.01 DESCRIPTIONS
A. Provide polyvinyl chloride (PVC) windows with integral flashing, and glazing specified in Section 08800, and accessories as required for complete, weathertight installation.
B. Special Coordination: Coordinate installation with Section 07190 Building Paper to ensure watertight installation of flanged type windows; refer to Part 3 of Section 07190 for special window installation requirements.
1.02 SECTION REQUIREMENTS
A. Submittals: Submit Product Data, Shop Drawings.
PART 2 – PRODUCTS
2.01 VINYL WINDOWS
A. Provide vinyl windows that comply with AAMA/NWWDA 101/I.S.2.
1. Comply with California Building Code and AAMA 101 for each type of window indicated.
2. Provide AAMA-certified vinyl windows with an attached label.
3. Provide units labeled and certified according to NFRC’s Product Certification
Program, with maximum U-value of 0.30 BTU/sq. ft. x h x deg F, as determined according to NFRC 100, and a maximum Solar Heat Gain Coefficient of 0.30 as determined according to NFRC 200.
4. Equip units with vinyl-coated glass-fiber mesh insect screens at operable sashes.
5. Window Color: White.
6. Insulated Glass: Refer to Section 08800 Glass and Glazing.
PART 3 – EXECUTION
3.01 INSTALLATION
A. Set units level, plumb, and true to line, without warp or rack of frames and panels and anchor securely in place.
B. Set sill members in bed of sealant or with gaskets, as indicated, to provide weathertight construction.
C. Adjust operating panels, screens, and hardware for smooth operation and weather tight closure. Lubricate hardware and moving parts.
3.02 FIELD QUALITY CONTROL
A. On-Site Tests: Conduct tests for air and water infiltration with window manufacturer’s representative present, correct units failing tests.
1. Test: Conduct in accordance with AAMA 502.
2. Air Infiltration: Maximum infiltration of 1.5 times amount specified.
3. Water Penetration: Conduct at static pressure of 3.00 psf (min).
END OF SECTION 08561
SECTION 08800 – GLASS AND GLAZING
1.01 SECTION REQUIREMENTS
A. Submittals: Product Data.
B. Fire-Reistance-Rated-Assemblies: Products identical to those tested per NFPA 252 for doors and NFPA 257 for window assemblies; both labeled and listed by UL or another testing and inspecting agency acceptable to authorities having jurisdiction.
C. Safety Glass: Category II materials complying with testing requirements in 16 CFR 1201 and ANSI Z97.1.
D. Comply with written instruction of glass product manufactures; GANA’s “Glazing
Manual;” and publications of GANA, AAMA, and SIGMA as applicable to products indicated, unless more stringent requirements are indicated.
E. Insulating-Glass Units: Permanently mark with appropriate certification label of one of the inspecting and testing agencies indicated below:
1. Insulating Glass Certification Council.
2. Associated Laboratories, Inc.
3. National Accreditation and Management Institute
E. Provide glass and glazing that has been produced, fabricated, and installed to withstand normal thermal movement, wind loading and impact loading (where applicable), without failure including loss or breakage of glass, failure of sealants or gaskets to remain watertight and airtight, deterioration of glass and glazing materials and other defects in the work.
1. Normal thermal movement is defined as that resulting from an ambient temperature range of 120 deg. F (67 deg. C) and from a consequent temperature range within glass and glass framing members of 180 deg. F (100 deg. C)
2. Deterioration of insulating glass is defined as failure of hermetic seal due to other causes than breakage which results in intrusion of dirt or moisture, internal condensation or fogging, deterioration of protected internal glass coating, if any, resulting from seal failure, and any other visual evidence of seal failure or performance.
PART 2 – PRODUCTS
2.01 GLASS
A. Float Glass: ASTM C 1036, Type 1, Class 1 (clear) and Quality q3.
2.02 FABRICATED GLASS PRODUCTS
A. Type I Sealed Insulating-Glass Units: Pre-assembled units complying with ASTM E 774 for Class CBA units, with two 1/4-inch clear thick sheets of glass separated by a ½-inch dehydrated space filled with air (hermetically sealed).
1. System: Manufacturer’s standard dual seam system compatible with glazing system, and including spacers, desiccant, and standard corner construction.
2. Glass: ASTM C 1036, select glazing quality of clear float glass at windows, unless otherwise noted or specified.
3. Safety Glass: ASTM C1048, Kind FT, fully tempered select glazing quality clear float safety glass at windows or doors and where required by codes and regulations.
4. Total Unit Thickness: 3/4" inch.
PART 3 – EXECUTION
3.01 INSTALLATION
A. Comply with combined recommendations of manufacturers of glass, sealants, gaskets, and other glazing materials, unless more stringent requirements are contained in GANA’s
“Glazing Manual”.
B. Set glass lites in each series with uniform pattern, draw, bow, and similar characteristics.
END OF SECTION 08800