(1) Dimick Mold SOW Tech. Exhibit.docx
DOCX document 224 KB Posted
- Attached to
- MOLD REMEDIATION PROJECT IN DIMICK HALL
- Solicitation number
- 70Z039-22QCGA0001414
View the file
Other files
| File | Type | Posted |
|---|---|---|
| (3) DOL REV 19 for ref only.pdf | ||
| SF-1449.pdf | ||
| (2) Unique Entity Identifier (UEI) Reference.pdf | ||
| ADDENDUM.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
MOLD REMEDIATION
UNITED STATES COAST GUARD ACADEMY, DIMICK HALL
A. BACKGROUND
The US Coast Guard Academy (CGA) in New London CT has a mold remediation project that need to be completed. The area is the HVAC vents in the ceiling of Dimick Hall Auditorium (See exhibit A). There are 17 vents in the ceiling that are approximately 2 ½ feet in diameter (See exhibit B). These vents need to be cleaned and treated with an antimicrobial.
TASKS
Dimick Hall Auditorium -Dimick Hall cleaning of HVAC vents with HEPA vacuum then wiping down with Fiberlock Shockwave or industry equivalent. Only the vents around the outside of the auditorium are required to be wiped down. The vents over 12 feet require the mold to be effectively removed.
- Air scrubbers will be used for the duration of this project and must be able to move at least 12,000 cfm of air. The air scrubbers must have a HEPA filter and at least one pre filter on them.
REQUIREMENTS
The company conducting the requested services shall have experience in mold remediation and be mold remediation certified.
1. SUBMITTALS
The following shall be submitted to CGA prior to the start of work:
· Mold remediation certification.
E. SCHEDULE
- Bid Walk – 0900 on 6 June 2022 meet at the Sail Loft
- Bid submittals due- By COB 10 June 2022
- Contract awarded- 13 June 2022
- Period of Work Performance 20 June 2022- 20 July 2022
-A proposed schedule is required to be submitted with any bids. Work should be scheduled within normal business hours of 8:00 a.m. to 4:00 p.m. This can be adjusted but has to be approved by USCG Academy.
Exhibit A
Exhibit B image1.jpeg image2.jpeg
File details come from the government source that posted it. Updated .