08_Rework_and_Repair_ES7034 (AS Attach.docx
DOCX document 18 KB Posted
- Attached to
- F-15 SMDC Lines Federal contract opportunity
- Solicitation number
- FA8213-23-R-0069
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 03_ADC SOW Jan 2018.docx | DOCX document | |
| 6-Combined_Special Packaging_Instructions.pdf | ||
| 11-CDRLs_1423.pdf | ||
| 1-Air_Munition_SpecificationsAir_SPEC.pdf | ||
| 5-Special_Packaging_Instructions_Retreival_SOW.pdf | ||
| 06_SPI_Combined_50083.pdf | ||
| 10_JFQR 1377-01-Various (F-15 SMDC) signed.pdf | ||
| 05_Packaging_SOW_50082.pdf | ||
| 11_Item Description_combined_50082.pdf | ||
| 12_EDL_combined_50082.pdf | ||
| 12_EDL_combined_50083.pdf | ||
| 01_AIR SPEC 23-50082(USAF).docx | DOCX document | |
| 3-Ammunition_Data_Cards.pdf | ||
| 10-Engineering_Data_Lists.pdf | ||
| 7-Rework_and_Repair_of_Nonconforming_Material.pdf | ||
| 05_Packaging_SOW_50083.pdf | ||
| 4-CADPAD_Item_Marking_Instruction.pdf | ||
| 06_SPI_Combined_50082.pdf | ||
| 13_CDRLs_FD2020-23-50082 -23-50083 CDRLs rev.pdf | ||
| 11_ID_combined_50083.pdf | ||
| 02_REPSHIP 11 Mar 14.docx | DOCX document | |
| 8-JFQR_1377_01_Various(F_15_SMDC)signed.pdf | ||
| 9-SMDC_Item_Descriptions.pdf | ||
| 2-RESHIP.pdf |
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.
(End of clause)
(ES7034)
File details come from the government source that posted it. Updated .