Summary: Notice to Bidders and Special Provisions for Construction Contract 07-502204

This is a Notice to Bidders and Special Provisions document issued by the California Department of Transportation (Caltrans) District 07 for landscape visual and aesthetic improvement work on State Highways 5, 10, and 110 at various locations in Los Angeles County. The project encompasses roadway improvements including plant installation, irrigation systems, temporary traffic control, erosion control, and minor concrete work across multiple interchange locations. The bid item list contains 87 items including landscaping (51,700 plants in Group H, 12,700 plants in Group A, and 170 plants in Group U), irrigation infrastructure (plastic pipe ranging from 1" to 3" in various quantities totaling approximately 47,000 linear feet), temporary barrier systems, erosion control measures, and associated construction materials and services. Electronic sealed bids are due October 28, 2026, at 2:00 p.m. via the Bid Express website. The contract requires completion of all work excluding plant establishment within 250 working days, with plant establishment work to be completed within 500 working days and all work including plant establishment within 750 working days.

The estimated project cost is $7,800,000. Contractors must provide bidder's security equal to at least 10 percent of the bid and possess either a Class A contractor license or a Class C-27 license. The Department establishes no DVBE contract goal but encourages DVBE participation, with a 5 percent Small Business Enterprise (SBE) contract goal. Prevailing wages are required, with rates established by the California Director of Industrial Relations. The contract includes specific requirements for off-road diesel engine compliance (Tier 4 interim or Tier 4 final), environmental product declarations for certain materials, lead compliance planning, water pollution control measures, safety representative designation with specific certifications and qualifications, and prompt payment provisions requiring subcontractors be paid within 7 days of the contractor's receipt of progress payments. Additional provisions address temporary traffic control restrictions, closure liquidated damages on specific freeway segments, Olympic Games period work restrictions (June 1 to September 1, 2028), and specialized requirements for handling unregulated lead-containing materials on the job site.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bids open Wednesday, October 28, 2026 Dated September 21, 2026

STATE OF CALIFORNIA

DEPARTMENT OF TRANSPORTATION

NOTICE TO BIDDERS

AND

SPECIAL PROVISIONS

FOR CONSTRUCTION ON STATE HIGHWAY IN LOS ANGELES COUNTY ON

ROUTES 5, 10, AND 110 AT VARIOUS LOCATIONS

In District 07 On Route 5,10,110

Under Bid book dated September 21, 2026 Standard Specifications dated 2025

Project plans approved June 5, 2026 Standard Plans dated 2025

Identified by Contract No. 07-502204

07-LA-5,10,110-VAR

Project ID 0724000178

SPECIAL NOTICES

• See sections 2 and 3 for contractors' registration requirements.

• The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.

• See section 2 for submittal requirements for DVBE quotes and Non–Small Business

Subcontractor Preference.

• For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).

• See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.

• The flagging and temporary traffic control requirements have been revised. See sections 7-

1.03, 7-1.04, and 12.

• See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.

• See section 14-11.14 for changes to the management of treated wood waste.

• See section 12-3.20 for the requirements of MASH TL-3 compliant temporary barrier systems.

Contract No. 07-502204 i

TABLE OF CONTENTS

NOTICE TO BIDDERS

BID ITEM LIST

SPECIAL PROVISIONS

ORGANIZATION

DIVISION I GENERAL PROVISIONS

1 GENERAL

2 BIDDING

5 CONTROL OF WORK

6 CONTROL OF MATERIALS

7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

8 PROSECUTION AND PROGRESS

9 PAYMENT

12 TEMPORARY TRAFFIC CONTROL

13 WATER POLLUTION CONTROL

Dominguez Channel Los Angeles River Ballona Creek

14 ENVIRONMENTAL STEWARDSHIP

DIVISION III EARTHWORK AND LANDSCAPE

17 GENERAL

73 CONCRETE CURBS AND SIDEWALKS

80 FENCES

83 RAILINGS AND BARRIERS

DIVISION X ELECTRICAL WORK

86 GENERAL

87 ELECTRICAL SYSTEMS

96 GEOSYNTHETICS

ii

STANDARD PLANS LIST

The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.

RSP A3A Abbreviations (Sheet 1 of 3)

RSP A3B Abbreviations (Sheet 2 of 3)

RSP A3C Abbreviations (Sheet 3 of 3)

A10A Legend - Lines and Symbols (Sheet 1 of 5)

A10B Legend - Lines and Symbols (Sheet 2 of 5)

A10C Legend - Lines and Symbols (Sheet 3 of 5)

A10D Legend - Lines and Symbols (Sheet 4 of 5)

A10E Legend - Lines and Symbols (Sheet 5 of 5)

A77N5 Minor Concrete Vegetation Control - Guardrail System A77N5A Minor Concrete Vegetation Control - Guardrail System - Narrow Vegetation Control

Installation A77N6 Minor Concrete Vegetation Control - Guardrail System for Terminal System End

Treatments A77N7 Minor Concrete Vegetation Control - Guardrail System at Structure Approach A77N8 Minor Concrete Vegetation Control - Guardrail System at Fixed Object A77N9 Minor Concrete Vegetation Control - Guardrail System at Fixed Object A77N10 Minor Concrete Vegetation Control - Guardrail System at Fixed Object A77N11 Minor Concrete Vegetation Control - Guardrail System - Miscellaneous Details A85 Chain Link Fence A85A Chain Link Fence Details A85B Chain Link Fence Details H1 Landscape and Erosion Control Symbols H2 Landscape Details H3 Landscape Details H4 Landscape Details (Sprinkler Assembly) H5 Landscape Details (Swing Joint and Protector) H6 Landscape Details H7 Landscape Details RSP H8 Landscape Details H9 Landscape Details H10 Irrigation Controller Enclosure Cabinet H51 Erosion Control Details - Fiber Roll and Compost Sock T1A Temporary Crash Cushion - Sand Filled (Unidirectional) iii

T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)

T1B Temporary Crash Cushion - Sand Filled (Bidirectional)

T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)

RSP T3A Temporary Railing (Type K)

T3C Temporary Barrier System (Cross Bolt)

T3D Temporary Barrier System (Cross Bolt)

T3E Temporary Barrier System (Cross Bolt)

T3F Temporary Barrier System (Cal F-23)

T3F2 Temporary Barrier System (Cal F-23)

T3G Temporary Barrier System (Staking or Anchoring)

T3G2 Temporary Barrier System (Staking or Anchoring)

T9 Traffic Control System Tables for Lane and Ramp Closures T10 Traffic Control System for Lane Closure on Freeways and Expressways T10A Traffic Control System for Lane Closure on Freeways and Expressways RSP T11 Traffic Control System for Lane Closure on Multilane Conventional Highways T11A Traffic Control System for Changeable Lane Closure on Multilane Conventional

Highways and Expressways T14 Traffic Control System for Ramp Closure T15 Traffic Control System for Moving Lane Closure on Multilane Highways T18 Traffic Control System - Construction Work Zone Speed Limit Reduction on

Freeways and Expressways T20 Traffic Control System - Construction Work Zone Speed Limit Reduction Details T22 Traffic Control System for Construction Work Zone Speed Limit Reduction on Two

Lane Conventional Highways T30 Temporary Pedestrian Access Routes - Typical Sidewalk Closure and Pedestrian

Detour T32 Temporary Pedestrian Access Routes - Typical Sidewalk/Crosswalk Closure and

Pedestrian Detour T53 Temporary Water Pollution Control Details (Temporary Cover) T56 Temporary Water Pollution Control Details (Temporary Fiber Roll) T58 Temporary Water Pollution Control Details (Temporary Construction Entrance) T59 Temporary Water Pollution Control Details (Temporary Concrete Washout Facility) T61 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection) T62 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection) T63 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection) T64 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection) RS1 Roadside Signs - Typical Installation Details No. 1

RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2

RS4 Roadside Signs - Typical Installation Details No. 4 iv

ES-1A Electrical Systems (Legend) ES-1B Electrical Systems (Legend) ES-1C Electrical Systems (Legend) ES-2A Electrical Systems (Service Equipment) ES-2B Electrical Systems (Service Equipment) ES-2D Electrical Systems (Service Equipment Enclosure and Typical Wiring Diagram, Type III - A Series) ES-2E Electrical Systems (Service Equipment Enclosure and Typical Wiring Diagram, Type III - B Series) ES-2F Electrical Systems (Service Equipment Enclosure and Typical Wiring Diagram, Type III - C Series) ES-2G Electrical Systems (Service Equipment Enclosure and Typical Wiring Diagram, Type III - D Series) ES-3H Electrical Systems (Irrigation Controller Enclosure Cabinet) ES-8A Electrical Systems (Non-Traffic Pull Box) ES-8B Electrical Systems (Traffic Pull Box)

CANCELED STANDARD PLANS LIST

The 2025 standard plan sheets listed below are canceled and not applicable to this contract.

Plan No. Date Canceled Plan No. Date

Canceled Plan No. Date Canceled

P8 04-20-26

NOTICE TO BIDDERS

Bids open Wednesday, October 28, 2026

Dated September 21, 2026

General work description: Landscape visual and aesthetic improvement.

The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON

STATE HIGHWAY IN LOS ANGELES COUNTY ON ROUTES 5, 10, AND 110 AT VARIOUS

LOCATIONS.

District-County-Route-Post Mile: 07-LA-5,10,110-VAR

Contract No. 07-502204

The Contractor must have either a Class A license or the following Class C license which constitutes a majority of the work: C-27.

The Department establishes no DVBE Contract goal but encourages bidders to obtain DVBE participation.

The SBE Contract goal is 5 percent.

Bids must be on a unit price basis.

Complete the work, excluding plant establishment work, within 250 working days.

Complete the work, including plant establishment work, within 750 working days.

Complete the plant establishment work within 500 working days.

The estimated cost of the project is $7,800,000.

The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.

The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.

For bid results go to:

https://ppmoe.dot.ca.gov/cc

Select Electronic Bidding under the Bidding tab.

District office addresses are provided in the Standard Specifications.

Present bidders' inquiries to the Department and view the Department's responses at:

https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries

Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.

Submit your bid with bidder's security equal to at least 10 percent of the bid.

Under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq., the Department gives preference to certified small businesses and non–small businesses who commit to 25 percent certified small business participation.

Under Pub Cont Code § 6107, the Department gives preference to a "California company," as defined, for bid comparison purposes over a nonresident contractor from any state that gives or requires a preference to be given to contractors from that state on its public entity construction contracts.

Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.

The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.

Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.

Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.

Department of Transportation

BID ITEM LIST

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM

0002 090100 TIME-RELATED OVERHEAD (WDAY) WDAY 250

0003 090200 DISPUTE RESOLUTION ADVISOR ON-SITE

MEETING

EA 3

0004 090207 HOURLY OFF-SITE DISPUTE-RESOLUTION-

ADVISOR-RELATED TASKS

HR 16

0005 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM

0006 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM

0007 120165 CHANNELIZER (SURFACE MOUNTED) EA 8

0008 120207 PORTABLE RADAR SPEED FEEDBACK SIGN

SYSTEM

DAY 250

0009 017460 TEMPORARY BARRIER SYSTEM (MASH TL-3) LF 160

0010 129100 TEMPORARY CRASH CUSHION MODULE EA 14

0011 130100 JOB SITE MANAGEMENT LS LUMP SUM

0012 130301 STORMWATER POLLUTION PREVENTION PLAN LS LUMP SUM

0013 130312 PRE-STORM EVENT INSPECTION REPORT EA 20

0014 130323 DURING-AND POST-STORM EVENT INSPECTION

REPORT

DAY 20

0015 130570 TEMPORARY COVER SQYD 1,000

0016 130620 TEMPORARY DRAINAGE INLET PROTECTION EA 30

0017 130640 TEMPORARY FIBER ROLL LF 1,000

0018 130710 TEMPORARY CONSTRUCTION ENTRANCE EA 10

0019 130730 STREET SWEEPING LS LUMP SUM

0020 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0021 170103 CLEARING AND GRUBBING (LS) LS LUMP SUM

0022 190101 ROADWAY EXCAVATION CY 120

0023 190105 ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY

DEPOSITED LEAD)

CY 260

0024 190159 ROADWAY EXCAVATION (TYPE COM) (AERIALLY

DEPOSITED LEAD)

CY 90

0025 200002 ROADSIDE CLEARING LS LUMP SUM

0026 202039 SLOW-RELEASE FERTILIZER LB 4,440

0027 204008 PLANT (GROUP H) EA 51,700

0028 204035 PLANT (GROUP A) EA 12,700

0029 204038 PLANT (GROUP U) EA 170

0030 204096 MAINTAIN EXISTING PLANTED AREAS LS LUMP SUM

0031 204099 PLANT ESTABLISHMENT WORK LS LUMP SUM

0032 205035 WOOD MULCH CY 4,190

0033 206400 CHECK AND TEST EXISTING IRRIGATION

FACILITIES

LS LUMP SUM

0034 206402 OPERATE EXISTING IRRIGATION FACILITIES LS LUMP SUM

0035 206405 REMOVE IRRIGATION FACILITY LS LUMP SUM

0036 206560 CONTROL AND NEUTRAL CONDUCTORS LS LUMP SUM

0037 206562 1" REMOTE CONTROL VALVE EA 23

0038 206564 1 1/2" REMOTE CONTROL VALVE EA 79

0039 206565 2" REMOTE CONTROL VALVE EA 1

0040 206566 2 1/2" REMOTE CONTROL VALVE EA 1

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0041 206567 3" REMOTE CONTROL VALVE EA 1

0042 015027 LOCKJAW VALVE BOX EA 150

0043 206761 24-32 STATION IRRIGATION CONTROLLER

(PEDESTAL MOUNTED)

EA 6

0044 206762 30-42 STATION IRRIGATION CONTROLLER

(PEDESTAL MOUNTED)

EA 1

0045 208301 IRRIGATION CONTROLLER ENCLOSURE

CABINET

EA 6

0046 208426 2" BACKFLOW PREVENTER ASSEMBLY EA 1

0047 208427 2 1/2" BACKFLOW PREVENTER ASSEMBLY EA 1

0048 208428 3" BACKFLOW PREVENTER ASSEMBLY EA 3

0049 208442 FLOW SENSOR EA 6

0050 208445 TREE WELL SPRINKLER ASSEMBLY EA 290

0051 208446 RISER SPRINKLER ASSEMBLY (GEAR DRIVEN) EA 83

0052 208447 POP-UP SPRINKLER ASSEMBLY (GEAR DRIVEN) EA 530

0053 208448 RISER SPRINKLER ASSEMBLY EA 860

0054 208562 CAM COUPLER ASSEMBLY EA 1

0055 208588 3" GATE VALVE EA 8

0056 208595 (F) - 1" PLASTIC PIPE (SCHEDULE 40) (SUPPLY

LINE)

LF 28,325

0057 208597 (F) - 1 1/2" PLASTIC PIPE (SCHEDULE 40)

(SUPPLY LINE)

LF 11,410

0058 208598 (F) - 2" PLASTIC PIPE (SCHEDULE 40) (SUPPLY

LINE)

LF 7,790

0059 208599 (F) - 2 1/2" PLASTIC PIPE (SCHEDULE 40)

(SUPPLY LINE)

LF 20

0060 208605 (F) - 2" PLASTIC PIPE (CLASS 315) (SUPPLY

LINE)

LF 1,880

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0061 208606 (F) - 2 1/2" PLASTIC PIPE (CLASS 315) (SUPPLY

LINE)

LF 1,520

0062 208607 (F) - 3" PLASTIC PIPE (CLASS 315) (SUPPLY

LINE)

LF 5,855

0063 208610 HIGH DENSITY POLYETHYLENE PIPE CONDUIT LF 200

0064 208684 1" BALL VALVE EA 2

0065 208685 1 1/2" BALL VALVE EA 14

0066 208686 2" BALL VALVE EA 10

0067 208690 (F) - PVC PIPE CONDUIT (SLEEVE) LF 160

0068 208818 6" WELDED STEEL PIPE CONDUIT LF 250

0069 208819 8" WELDED STEEL PIPE CONDUIT LF 100

0070 210010 MOVE-IN/MOVE-OUT (EROSION CONTROL) EA 3

0071 210350 FIBER ROLLS LF 19,700

0072 210430 HYDROSEED SQFT 106,000

0073 210610 COMPOST (CY) CY 330

0074 721810 SLOPE PAVING (CONCRETE) CY 240

0075 723050 ROCK SLOPE PROTECTION (1/4 T, CLASS V,

METHOD B) (CY)

CY 160

0076 731519 MINOR CONCRETE (STAMPED CONCRETE) SQFT 22,500

0077 018345 CHAIN LINK FENCE (TYPE CL-6, MODIFIED,

VINYL-CLAD)

LF 400

0078 015034 CHAIN LINK FENCE (TYPE CL-8, MODIFIED,

VINYL-CLAD)

LF 620

0079 015032 4' CHAIN LINK GATE (TYPE CL-8, MODIFIED,

VINYL-CLAD)

EA 5

0080 803050 REMOVE CHAIN LINK FENCE LF 1,020

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0081 803060 REMOVE GATE EA 5

0082 820840 ROADSIDE SIGN - ONE POST EA 1

0083 832070 VEGETATION CONTROL (MINOR CONCRETE) SQYD 190

0084 870009 MAINTAINING EXISTING TRAFFIC MANAGEMENT

SYSTEM ELEMENTS DURING CONSTRUCTION

LS LUMP SUM

0085 014862 MODIFYING ELECTRIC SERVICE FOR

IRRIGATION

LS LUMP SUM

0086 995100 WATER METER CHARGES LS LUMP SUM

0087 999990 MOBILIZATION LS LUMP SUM

SPECIAL PROVISIONS

ORGANIZATION

Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.

Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.

Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.

DIVISION I GENERAL PROVISIONS

1 GENERAL

Add to section 1-1.01:

Bid Items and Applicable Sections Item code

Item description Applicable section

014862 MODIFYING ELECTRIC SERVICE FOR IRRIGATION 87

015027 LOCKJAW VALVE BOX 20

015034 CHAIN LINK FENCE (TYPE CL-8, MODIFIED, VINYL-CLAD) 80

015032 4' CHAIN LINK GATE (TYPE CL-8, MODIFIED, VINYL-CLAD) 80

017460 TEMPORARY BARRIER SYSTEM (MASH TL-3) 12

018345 CHAIN LINK FENCE (TYPE CL-6, MODIFIED, VINYL-CLAD) 80

2 BIDDING

Add between the 1st and 2nd paragraphs of section 2-1.06B:

The Department makes the following supplemental project information available:

Supplemental Project Information Means Description

Included in the Information Handout 1. Site Investigation report.

2. Metro Electrical As-builts

3. Landscape As-builts

Add to section 2-1.09:

The item total for plant establishment work must be at least $250,000.00.

5 CONTROL OF WORK

Replace section 5-1.13E with:

5-1.13E Prompt Payment Section 5-1.13E applies to all contracts.

Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.

Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:

1. Subcontractor’s or entity’s business name

2. Description of work performed

2.1. Bid item numbers or change order numbers

2.2. Written narrative of work performed

3. Value of work performed

4. Amount paid to subcontractor or entity

5. Withhold amount, if applicable

6. Explanation of withhold reasoning, if applicable

Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.

If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:

1. Value of the disputed work

2. Amount of the withhold being taken

3. Bid item numbers or change order numbers associated with the disputed work

4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated

5. Corrective actions to be taken for release of withheld amount

The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.

The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:

1. Withhold was not applied in good faith

2. Requested additional withhold documentation records were not provided

3. Payment information was not submitted through the prompt payment monitoring system

4. Required withhold notification was not provided

The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.

Replace section 5-1.15 with:

5-1.15 SAFETY REPRESENTATIVE

5-1.15A General Designate an on-site safety representative to superintend project safety for the duration of this Contract.

The safety representative may perform other non-safety related work if safety responsibilities are fulfilled.

The safety representative must be available after work hours as needed. The safety representative is not required to be on-site during plant establishment period, erosion control establishment period, or temporary suspensions when no other Contract work is being performed.

Develop a written site-specific safety program (SSSP) that incorporates known hazards associated with the project.

5-1.15A(1) Submittals Submit a resume of the safety representative before starting work on the project, including education, completed safety training, and safety experience in heavy construction, heavy industrial, or oil and energy industry.

Submit a copy of the safety representative's certificate for the Cal/OSHA 30-hour – Cal/OSHA Standards for the Construction Industry or OSHA 510 - OSHA Standards for the Construction Industry training course as an informational submittal. The certificate must include:

1. Name of the entity providing certification

2. Name of the individual receiving certification

3. Date when the certification was provided

4. Expiration date, if applicable

Submit a copy of the SSSP as an informational submittal:

1. At least 15 days before starting work

2. At least 48 hours before starting work whenever a revision is made to the SSSP

5-1.15A(2) Quality Assurance 5-1.15A(2)(a) General Not Used

5-1.15A(2)(b) Certifications The safety representative must have completed training and received a certificate of completion for the Cal/OSHA 30-hour - Cal/OSHA Standards for the Construction Industry or OSHA 510 – OSHA Standards for the Construction Industry training course.

The safety representative must have one of the following certifications:

1. Certified Safety Professional from the Board of Certified Safety Professionals

2. Construction Health and Safety Technician from the Board of Certified Safety Professionals

3. Occupational Hygiene and Safety Technician from the Board of Certified Safety Professionals

4. Safety Trained Supervisor from the Board of Certified Safety Professionals

5. Safety Trained Supervisor Construction from the Board of Certified Safety Professionals

6. Associate Safety Professional from the Board of Certified Safety Professionals

7. Master Safety Professional from the National Association of Safety Professionals

8. Certified Safety Director from the National Association of Safety Professionals

5-1.15A(2)(c) Qualifications The safety representative must be a competent and qualified person, as defined by Cal/OSHA, and must provide safety oversight on the project. The safety representative must have:

1. At least 3 years of safety experience in heavy construction, heavy industrial, or oil and energy industry

2. Knowledge in the area of safety procedure for all types of work being performed on this project

3. Knowledge of Department specifications and plans, Cal/OSHA policy and procedures, and 8 CA

Code of Regs safety requirements

The safety representative must have completed safety training and maintain valid certifications for:

1. First aid

2. Cardiopulmonary resuscitation

5-1.15B Materials Not Used

5-1.15C Construction The safety representative must be available by:

1. Cellular telephone

2. Two-way radio

3. Mobile internet access

The safety representative must:

1. Develop the SSSP

2. Conduct the on-site new project orientation for each worker assigned to the project

3. Review the construction work plans for each subcontractor before starting work

4. Conduct or attend pre-planning sessions for high hazard work such as excavations, demolition, confined space entry, falsework, crane hoisting, high-risk utilities such as high-pressure pipelines with fuel or natural gas, and tunneling or boring

5. Conduct weekly job site safety meetings

6. Review work schedules, including subcontractors' work schedules, to ensure adequacy of job hazard analyses and address all safety concerns and issues

7. Ensure safety data sheets are available on-site for all materials and have a hazard communication program for informing workers of material hazards

8. Verify compliance with hazardous waste requirements under section 14-11, including spill prevention and control measures

9. Conduct daily safety inspections of the job site for hazards and compliance with safety requirements in the specifications and 8 CA Code of Regs

10. Report all incidents to the Engineer immediately, including the investigation of any close calls

When monitoring the job site, including work zones with certified flaggers or traffic control technicians, take immediate corrective action and notify the Engineer if an imminent danger is identified.

If the Engineer determines the safety representative is not meeting the intended duties and responsibilities, you must replace the safety representative within 30 days of written notice from the Engineer. If you need to replace the safety representative, notify the Engineer and provide replacement safety representative resume and required certifications at least 15 days before the replacement.

You may submit a secondary safety representative to act on behalf of the designated safety representative during extended shifts, continuous operations, or short-term absences that will not exceed 14 days in duration. The secondary safety representative must meet the same required qualifications and certifications as the designated safety representative.

5-1.15D Payment Not Used

Add to the end of section 5-1.20A:

During the progress of the work under this Contract, work under the following contracts may be in progress at or near the job site of this Contract:

Coincident or Adjacent Contracts

Contract no. County–Route–Post Mile Location Type of work 0721000250

EA 07-38040

LA-110-9.6/17.8 RTE 110 BETWEEN

WEST 182ND ST

AND SLAUSON AVE

IMPLEMENT PERMANENT

STORMWATER TREATMENT

BMP

0722000171

EA 07-38630

LA-110-14/21 RTE 110 CLEAN CA BEUTIFICATION

0715000122

EA 07-31450

LA-105-0.6R/18.1R RTE 105 CONSTRUCTION OF DOUBLE

HIGH OCCUPANCY TOLL

LANES (EXPRESSLANES)

Coordinate lane closures and traffic handling with the Engineer and with contractors of coincident or adjacent projects. Potential conflicts may not be limited to the contracts listed above.

Replace section 5-1.20E with:

5-1.20E Water Meter Charges Section 5-1.20E applies if a bid item for water meter charges is shown on the Bid Item List.

The local water authority is (A) Los Angeles Department of Water and Power & (B) City of Monterey Park.

The local water authority will install the water meters.

The charges are as shown in the following table:

Water Meter Charges

Meter size Quantity Charge per meter

(A) 2” 1 $30,000.00

(B) 2” 1 $30,000.00

The charges by the local water authority include:

1. Furnishing and installing each water meter

2. Connecting to the local water authority's main water line, including any required hot tap or tee

3. Furnishing and installing an extension pipe from the main water line to the water meter

4. Sterilizing the extension pipe

Make arrangements and pay the charges for installation of the water meters.

If the charge is changed at the time of installation, the Department adjusts the lump sum price based on the difference between the specified charges and the changed charges.

Add to the end of section 5-1.33:

You must use tier 4 interim or tier 4 final engines for off-road diesel-fueled vehicles subject to 13 CA Code of Regs § 2449 instead of the use of lowered tiered engines. However, the requirement to use tier 4 interim or tier 4 final engines does not apply to vehicles registered to operate on public roads when those vehicles are used solely to deliver materials or supplies to the job site.

For off-road diesel-fueled vehicles subject to 13 CA Code of Regs§ 2449:

1. At least 15 days before use of vehicles submit an inventory list to the Engineer and tier4@dot.ca.gov for authorization. The list must include the following information for each vehicle:

1.1. Diesel off-road on-line reporting system (DOORS) identification number issued to the vehicle owner by the California Air Resources Board

1.2. Company or agency name associated with the DOORS identification number

1.3. California Air Resources Board issued equipment identification number for the vehicle

1.4. Vehicle product identification number as listed in DOORS

1.5. Corresponding identifying number required in this section

1.6. Serial number

1.7. Vehicle type

1.8. Vehicle manufacturer, model number and model year

1.9. Number of engines as indicated in DOORS

1.10. For each engine:

1.10.1. Serial number

1.10.2. Manufacturer name, model, and model year

1.10.3. Maximum horsepower

1.10.4. EPA issued engine family name

1.10.5. Engine displacement in liters

1.10.6. California Air Resources Board issue executive order for the engine family from the off-road certification database. For the database go to the California Air Resources Board website: https://www.arb.ca.gov/msprog/offroad/cert/cert.php

1.10.7. Emission standard category for the engine family, such as tier 4 interim or tier 4 final

1.10.8. Photograph of the engine label

2. Submit an updated inventory list at least 5 business days before using a vehicle not on the list or replacing a vehicle on the list for authorization. Allow 5 business days for review.

Flexibility engines certified under the California Air Resources Board’s flexibility program provisions are noncompliant engines unless a previously issued executive order for that engine family indicates the emission standard category is tier 4 interim. You may access these executive orders at the California Air Resources Board website: https://www.arb.ca.gov/msprog/offroad/cert/cert.php For example:

Executive Order U-R-002-0747 was issued on March 16, 2020, for Flexibility Program Engine Family Name “DCEXL15.0AAK,” a Cummins Inc. 2020 model engine. Executive Order U-R-002-0592-2 issued On December 30, 2013, for Engine Family DCEXL15.0AAK indicates the “Emission Standard Category” is tier 4 interim. Use of Engine Family “DCEXL 15.0AAK is compliant.

If you operate a vehicle that is noncompliant with these requirements, the Department deducts a $2000 penalty for each noncompliant engine for each day of operation.

6 CONTROL OF MATERIALS

Replace section 6-1.03B with:

6-1.03B Submittals 6-1.03B(1) General Not Used

6-1.03B(2) Work Plan For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:

1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:

I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under section 6-1.03B(3) for other constituents of concern based on the land use history. I am aware that local material sources must not contain ADL at concentrations greater than 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II. I am aware that a maximum quantity of material may be excavated at the site based on the minimum number of samples taken before excavating at the site under section 6-1.03B(3).

2. Land use history of the local material location and surrounding property

3. Sampling protocol

4. Number of samples per volume of local material

5. QA and QC requirements and procedures

6. Qualifications of sampling personnel

7. Stockpile history

8. Name and address of the analytical laboratory that will perform the chemical analyses

9. Analyses that will be performed for lead and pH

10. Other analyses that will be performed for possible hazardous constituents based on:

10.1. Source property history

10.2. Land use adjacent to source property

10.3. Constituents of concern in the ground water basin where the job site is located

The plan must be sealed and signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State.

If the plan requires revisions, the Engineer provides comments. Submit a revised plan within 7 days of receiving comments. Allow 7 days for the review.

6-1.03B(3) Analytical Test Results At least 15 days before placing local material, submit analytical test results for each local material obtained from a noncommercial source or a source not regulated under CA jurisdiction. The analytical test results must include:

1. Certification signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:

The analytical testing described in the local material plan has been performed. I performed a statistical analysis of the test results using the US EPA's ProUCL software with the applicable 95 percent upper confidence limit. I certify that the material from the local material source is suitable for unrestricted use at the job site, it has a pH above 5.0, does not contain soluble lead in concentrations equal to or greater than 5mg/l as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II, does not contain lead in concentrations above 80 mg/kg total lead, is free from all other contaminants identified in the local material plan, and will comply with the job site's basin plan and water quality objectives of the RWQCB.

2. Chain of custody of samples

3. Analytical results no older than 1 year

4. Statistical analysis of the data using US EPA’s ProUCL software with a 95 percent upper confidence limit

5. Comparison of sample results to hazardous waste concentration thresholds and the RWQCB's basin plan requirements and water quality objectives for the job site location

6-1.03B(4) Sample and Analysis Sample and analyze local material from a (1) noncommercial source or (2) a source not regulated under CA jurisdiction:

1. Before bringing the local material to the job site

2. As described in the local material plan

3. Under US EPA Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846)

The sample collection must be designed to generate a data set representative of the entire volume of proposed local material.

Before excavating at the (1) noncommercial material source or (2) a source not regulated under CA jurisdiction, collect the minimum number of samples and perform the minimum number of analytical tests for the corresponding maximum volume of local material as shown in the following table:

Minimum Number of Samples and Analytical Tests for Local Material Maximum volume of imported borrow

(cu yd) Minimum number of samples and analytical tests

< 5,000 8

5,000–10,000 12 for the first 5,000 cu yd plus 1 for each additional 1,000 cu yd or portion thereof

10,000–20,000 17 for the first 10,000 cu yd plus 1 for each additional 2,500 cu yd or portion thereof

20,000-40,000 21 for the first 20,000 cu yd plus 1 for each additional 5,000 cu yd or portion thereof

40,000–80,000 25 for the first 40,000 cu yd plus 1 for each additional 10,000 cu yd or portion thereof

> 80,000 29 for the first 80,000 cu yd plus 1 for each additional 20,000 cu yd or portion thereof

Do not collect composite samples or mix individual samples to form a composite sample.

Analyze the samples using the US EPA's ProUCL software with a 95 percent upper confidence limit. All chemical analysis must be performed by a laboratory certified by the SWRCB's Environmental Laboratory Accreditation Program (ELAP).

The analytical test results must demonstrate that the local material:

1. Is not a hazardous waste

2. Has a pH above 5.0

3. Has an average total lead concentration, based upon the 95 percent upper confidence limit, at or below 80 mg/kg

4. Is free of possible contaminants identified in the local material plan

5. Complies with the RWQCB's basin plan for the job site location 6 Complies with the RWQCB's water quality objectives for the job site location

6-1.03C Local Material Management Do not place local material until authorized.

If the Engineer determines the appearance, odor, or texture of any delivered local material suggests possible contamination, sample and analyze the material. The sampling and analysis is change order work unless (1) hazardous waste is discovered or (2) the analytical test results indicate the material does not comply with section 6-1.03B(3).

Dispose of noncompliant local material at an appropriately permitted CA Class I, CA Class II or CA Class III facility. You are the generator of noncompliant local materials.

Add to section 6-1:

6-1.08 ENVIRONMENTAL PRODUCT DECLARATIONS FOR HOT MIX ASPHALT AND CONCRETE

Section 6-1.08 includes specifications for environmental product declarations for hot mix asphalt and concrete materials and products.

See section 6-1.06B for definitions.

For projects with bid opening dates after February 1, 2025, with a total bid over $1 million and 175 or more original working days, materials or products specified in the following table require facility-specific, product stage, environmental product declarations as informational submittals:

Material or product Material specifications Hot mix asphalta Section 39-2, "Hot Mix Asphalt"

Excludes RHMA, OGFC, and BWC materials.

Concreteb Section 28-2, "Lean Concrete Bases," Section 28-3, "Rapid

Strength Concrete Base," Section 28-4, "Lean Concrete Base Rapid Setting," Section 28-5, "Concrete Base," Section 40, "Concrete Pavement," Section 47-5, "Type 6 Retaining Walls," Section 49-3, "Cast-In-Place Concrete Piling," Section 49-4, "Steel Soldier Piling," Section 51, "Concrete Structures," Section 58-2, "Masonry Block," Section 73, "Concrete Curbs and Sidewalks," Section 83, "Railings and Barriers," and Section 99, "Building Construction."

Excludes volumetric-proportioned rapid strength concrete and Section 90-4 PC concrete members.

aFor each hot mix asphalt plant providing 2,250 tons or more on the project by job mix formula.

bFor each concrete plant providing 250 cubic yards or more on the project by mix design.

The requirements in section 6-1.08 do not apply to seasonal plants operating fewer than 6 months per year.

The requirements in section 6-1.08 do not apply to informal-bid contracts.

For product category rules for hot mix asphalt or concrete, go to the METS website. Use the product category rule in effect on the date of bid opening unless otherwise authorized. An environmental product declaration for hot mix asphalt or concrete is not required for either of the following conditions:

1. Applicable product category rule has expired without replacement as of the bid opening date.

2. Applicable product category rule was issued less than 50 days before the bid opening date.

Immediately notify the Engineer if a program operator has determined their product category rule does not allow for development of a facility-specific environmental product declaration. Include written correspondence from the program operator with your notification to the Engineer. If the Engineer determines the development of a facility-specific environmental product declaration cannot be achieved, an environmental product declaration will not be required for that material or product.

You must register on the Department’s Data Interchange for Materials Engineering (DIME) at least 15 days before submitting environmental product declarations. Follow the registration process at:

https://dime.dot.ca.gov/

Within 30 days of initial placement of each applicable material or product, submit a facility-specific, product stage, environmental product declaration informational submittal to DIME and provide proof of submission in PDF file format to the Engineer. The DIME entry information must include intended use of materials and estimated quantities of materials to be used as represented by the environmental product declaration.

Failure to provide a required environmental product declaration informational submittal will result in a $6,000 performance failure withhold for each missing declaration. The Department returns the withhold within 30 days after receipt of the compliant declaration if submitted prior to Contract acceptance.

Withholds become permanent deductions if the declaration is not submitted before Contract acceptance.

7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

Replace the paragraphs of section 7-1.02C with:

Submit to the Department the following certifications before performing the work:

I am aware of the emissions reduction regulations being mandated by the California Air Resources Board. I will comply with such regulations before commencing the performance of the work and maintain compliance throughout the duration of this Contract.

I am aware of the requirements to use tier 4 interim or tier 4 final engines under section 5-1.33 and I will comply with the requirements. I am aware that the Department deducts a $2,000 penalty for each noncompliant engine for each day of operation.

Contract signing constitutes submittal of these certifications.

Replace Section 7-1.02K(6)(j)(iii) with:

7-1.02K(6)(j)(iii) Unregulated Earth Material Containing Lead Section 7-1.02K(6)(j)(iii) includes specifications for handling, removing, and disposing of unregulated earth material containing lead. Management of this material exposes workers to health hazards that must be addressed in your lead compliance plan. This material contains average lead concentrations below 80 mg/kg total lead and below 5 mg/L soluble lead and is not regulated by DTSC as a hazardous substance or a hazardous waste. This material does not require disposal at a permitted landfill or solid waste disposal facility. The RWQCB has jurisdiction over reuse of this material at locations outside the job site limits.

Manage regulated earth material containing lead under sections 14-11.08 and 14-11.09.

Unregulated earth material containing lead is present on the job site at the following locations:

Location Element of work Depth Location 2

(I-110/105 Interchange) Minor Concrete 0.5 feet

Location 3 (I-110/Manchester)

Minor Concrete Rock Slope Protection

0.5 feet

Unregulated earth material containing lead has been detected to a depth of 0.5 feet within the job site.

Unregulated levels of lead found range from less than 6 to 25 mg/kg total lead with an average concentration of 19 mg/kg total lead as analyzed by EPA test method 6010 or EPA test method 7000 series and based upon a 95 percent upper confidence limit. Unregulated levels of lead on the job site have a predicted average soluble concentration of 2 mg/L as analyzed by the California Waste Extraction Test and based upon a 95 percent upper confidence limit.

Handle the material under all applicable laws, rules, and regulations, including those of the following agencies:

1. Cal/OSHA

2. CA RWQCB, Region 4-Los Angeles

If unregulated material is disposed of:

1. Submit at least 15 days before disposal, the form titled "Agreement between a Contractor Working on State Facilities and a Real Property Owner for Disposing Construction-related Material Suitable for Use on Residential Zoned Property" which discloses the lead concentration of the material to the receiving property owner and obtains authorization for disposal on the property. Give a copy of the signed form to the property owner.

2. You are responsible for any additional sampling and analysis required by the receiving property owner.

If you choose to dispose of unregulated material at a commercial landfill:

1. Transport it to a Class III or Class II landfill appropriately permitted to receive the material

2. You are responsible for identifying the appropriately permitted landfill to receive the material and for all associated trucking and disposal costs, including any additional sampling and analysis required by the receiving landfill

8 PROSECUTION AND PROGRESS

Replace the row for DBE and DVBE in the table in the 2nd paragraph of section 8-1.03 with:

DVBE Final utilization reports

Replace the row for Schedule in the table in the 2nd paragraph of section 8-1.03 with:

Schedule Baseline schedule and weekly statement of working days report

Replace the 4th and 5th paragraphs of section 8-1.05 with:

The Engineer issues a weekly statement of working days report by the end of the following week. If you disagree with a weekly statement of working days report, submit an RFI within 5 business days of receipt of the report.

The weekly statement of working days report shows:

1. Working days and non–working days during the reporting week

2. Time adjustments

3. Calculations of work completion dates, including working days remaining

4. Controlling activities

Delete the 6th paragraph of section 8-1.05.

9 PAYMENT

Replace the 1st paragraph of section 9-1.11D with:

For progress payments, the total work completed for the TRO bid item is the number of working days shown for the pay period on the weekly statement of working days report.

12 TEMPORARY TRAFFIC CONTROL

Add to section 12-3.11B(5)(b):

Provide four C51(CA) construction project funding identification signs.

Legend for the type of project must read as follows:

ROADSIDE WORK

Legend for the year of completion on project funding sign must read as follows:

YEAR OF COMPLETION: 2030

Add the following funding partner agency pictographs:

Partner funding agency Pictograph details The Los Angeles County Metropolitan Transportation Authority

The Los Angeles County Metropolitan Transportation Authority (M) logo including the tag line Metro

Replace section 12-3.20 with:

12-3.20 TEMPORARY BARRIER SYSTEMS

12-3.20A General 12-3.20A(1) Summary Section 12-3.20 includes specifications for placing, maintaining, repairing, and removing temporary barrier systems.

Temporary barrier system Type K temporary railing is not allowed. Value engineering change proposals for the use of Type K temporary railing are not allowed.

Temporary barrier system consists of:

1. New or undamaged used interconnected barrier segments

2. Segment connection hardware

3. Stakes and anchor bolts

12-3.20A(2) Definitions approach zone: The area immediately upstream of the work area and buffer space.

clear area width: Minimum width throughout the length of the barrier system that must be maintained clear of obstructions, objects, and work resources during non-working hours. The width is measured perpendicular from the non-traffic side toe.

departure zone: The area past the work area and the trailing end of the construction area.

set back distance: Space measured between the closest toe of temporary barrier and the edge of traveled way for each direction of traffic.

height differential: May be an excavation, a downward slope greater than 4:1, or a difference in elevation. The height differential is measured down from the top of pavement.

12-3.20A(3) Submittals Submit as informational submittal for each type of temporary barrier system:

1. Certificate of compliance.

2. Manufacturer's installation instructions except for temporary concrete barriers with loop and pin and temporary concrete barriers with cross bolt.

3. Manufacturer's concrete QC test results and daily production log of precast concrete activities, through the Data Interchange for Materials Engineering (DIME) website. For QC test results, use project identifier 88887 in the DIME sample record. QC test results must include the concrete mix design number, barrier stamped ID, and must be submitted within 3 business days of QC test completion.

Submit test reports for cross bolts that certify compliance with the applicable ASTM requirements. The test reports must be from a laboratory that is accredited to International Standards Organization/International Electrotechnical Commission 17025 by the American Association for Laboratory Accreditation (A2LA) or the ANSI-ASQ National Accreditation Board.

Submit a signed manufacturer's replacement evaluation report within 10 days of damage to a temporary steel barrier system.

12-3.20A(4) Quality Assurance 12-3.20A(4)(a) General Temporary barrier systems must comply with MASH Test Level 3.

Except for temporary concrete barriers with loop and pin and temporary concrete barriers with cross bolt, temporary barrier systems must:

1. Be on the Authorized Materials List for highway safety features

2. Comply with the manufacturer's drawings shown on the Department’s Division of Safety Programs website and the manufacturer's installation instructions

If a discrepancy exists, governing ranking in descending order is:

1. These specifications

2. Manufacturer's drawings

3. Manufacturer's installation instructions

QC sampling, testing, and inspection personnel must have an ACI Concrete Field-Testing Technician, Grade 1 certification.

Temporary concrete barrier segments must:

1. Comply with the requirements for tier 3 precast concrete in section 90-4

2. Be fabricated at a plant on the Authorized Facility Audit List

Concrete must be sampled and tested as shown in the following table.

Concrete QC Tests Quality characteristic Test method Minimum testing frequency

Compressive strength ASTM C172/C172M, ASTM C31/C31M, and

ASTM C39/C39M

Once per 300 cu yd of concrete cast, or every day of casting, whichever is more frequent Slump ASTM C143/C143M

Temperature at time of mixing ASTM C1064/C1064M Density ASTM C138 Once per 600 cu yd of concrete cast or every 7 days of batching, whichever is more frequent

Air content ASTM C231/C231M or

ASTM C173/C173M

If concrete is air entrained, once for each set of cylinders, and when conditions warrant

A daily production log of precast concrete activities must be maintained under section 90-4.01C(4).

12-3.20A(4)(b) Quality Control Replace damaged temporary concrete barrier segments with exposed reinforcing steel or concrete spalls 1-1/2 inches in depth and 4 inches in width or greater. Repair minor damage under section 51-1.03F(2), for temporary concrete barriers with loop and pin and temporary concrete barriers with cross bolt.

Replace damaged temporary steel barrier segments with permanent bends, tearing, or buckling as described in the signed manufacturer's replacement evaluation report.

Realign temporary barrier system within 2 days of impact or displacement when displaced more than 3 inches except when the temporary barrier system is displaced into a traveled lane realign immediately.

12-3.20B Materials 12-3.20B(1) General Temporary barrier segment must:

1. Be a minimum 31-1/2 inches in height

2. Have at least two lifting holes

3. Be designed to be used with temporary traffic screen when required

Temporary barrier segment may have your name or logo on each barrier segment. The name or logo must be no more than 4 inches in height and must be located no more than 12 inches above the bottom of the barrier segment.

12-3.20B(2) Temporary Concrete Barriers 12-3.20B(2)(a) General Temporary concrete barrier segment must:

1. Be precast concrete with a minimum 5,000-psi compressive strength.

2 Have reinforcement…