07-367604 Construct Treatment BMPs for Stormwater Mitigation.pdf
PDF 857 KB Posted
- Solicitation number
- 07-367604, Fed #NH-Q101(464)
- Issued by
- Ventura County, California
About this file
This is a Notice to Bidders and Special Provisions document issued by the California Department of Transportation (Caltrans) District 07 for construction work in Ventura County. The project involves constructing treatment best management practices (BMPs) for stormwater mitigation on State Highway 101 between Central Avenue and 0.6 miles north of Victoria Avenue in and near Oxnard and Ventura. Bids open electronically on Thursday, November 19, 2026, at 2:00 p.m. via the Bid Express website. The contractor must complete all work excluding plant establishment within 200 working days, complete work including plant establishment within 450 working days, and complete plant establishment work within 250 working days. The bid item list includes 70 line items encompassing traffic control systems, stormwater pollution prevention, roadway excavation, landscaping, irrigation infrastructure, asphalt work, concrete pavement, infiltration areas, and gross solids removal devices. Key quantities include 240 cubic yards of aerially deposited lead excavation, 20,500 plants in Group H, 780 cubic yards of wood mulch, and various irrigation components.
The estimated project cost is $2,700,000, and bids must be submitted on a unit price basis with bidder's security equal to at least 10 percent of the bid amount. The contractor must possess either a Class A license or a combination of Class C licenses (C-27, C-12, C-42) constituting a majority of the work. This is a federal-aid project (NH-Q101(464)) and requires prevailing wages as determined by the California Department of Industrial Relations, with contractors obligated to pay the higher rate if federal minimum wage rates exceed state prevailing wage rates. The project incorporates standard 2025 specifications and plans approved on June 19, 2026, and includes comprehensive requirements for temporary traffic control, water pollution control, environmental stewardship, and treated wood waste management.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bids open Thursday, November 19, 2026 Dated October 12, 2026
STATE OF CALIFORNIA
DEPARTMENT OF TRANSPORTATION
NOTICE TO BIDDERS
AND
SPECIAL PROVISIONS
FOR CONSTRUCTION ON STATE HIGHWAY IN VENTURA COUNTY IN AND
NEAR OXNARD AND VENTURA FROM CENTRAL AVENUE TO 0.6 MILE
NORTH OF VICTORIA AVENUE
In District 07 On Route 101 Under
Bid book dated October 12, 2026 Standard Specifications dated 2025
Project plans approved June 19, 2026 Standard Plans dated 2025
Identified by Contract No. 07-367604 07-Ven-101-17.7/R24.7 Project ID 0719000358
Federal-Aid Project
NH-Q101(464)
SPECIAL NOTICES
• See sections 2 and 3 for contractors' registration requirements.
• The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.
• See section 2 for submittal requirements for DVBE quotes and Non–Small Business
Subcontractor Preference.
• For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).
• See section 6-1.01 and 6-1.04 of these Special Provisions for the requirements of Buy
America/Build America for manufactured products.
• See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.
• The flagging and temporary traffic control requirements have been revised. See sections 7-
1.03, 7-1.04, and 12.
• See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.
• See section 14-11.14 for changes to the management of treated wood waste.
Contract No. 07-367604 i
TABLE OF CONTENTS
NOTICE TO BIDDERS
BID ITEM LIST
SPECIAL PROVISIONS
ORGANIZATION
DIVISION I GENERAL PROVISIONS
1 GENERAL
2 BIDDING
5 CONTROL OF WORK
6 CONTROL OF MATERIALS
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
8 PROSECUTION AND PROGRESS
9 PAYMENT
DIVISION II GENERAL CONSTRUCTION
12 TEMPORARY TRAFFIC CONTROL
13 WATER POLLUTION CONTROL
14 ENVIRONMENTAL STEWARDSHIP
DIVISION III EARTHWORK AND LANDSCAPE
17 GENERAL
20 LANDSCAPE
DIVISION V SURFACINGS AND PAVEMENTS
39 ASPHALT CONCRETE
DIVISION VII DRAINAGE FACILITIES
62 STORMWATER TREATMENT
DIVISION VIII MISCELLANEOUS CONSTRUCTION
73 CONCRETE CURBS AND SIDEWALKS
DIVISION IX TRAFFIC CONTROL DEVICES
83 RAILINGS AND BARRIERS
ii
STANDARD PLANS LIST
The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.
RSP A3A Abbreviations (Sheet 1 of 3)
RSP A3B Abbreviations (Sheet 2 of 3)
RSP A3C Abbreviations (Sheet 3 of 3)
A10A Legend - Lines and Symbols (Sheet 1 of 5)
A10B Legend - Lines and Symbols (Sheet 2 of 5)
A10C Legend - Lines and Symbols (Sheet 3 of 5)
A10D Legend - Lines and Symbols (Sheet 4 of 5)
A10E Legend - Lines and Symbols (Sheet 5 of 5)
A20A Pavement Markers and Traffic Lines - Typical Details
A20B Pavement Markers and Traffic Lines - Typical Details
A20C Pavement Markers and Traffic Lines - Typical Details
A20D Pavement Markers and Traffic Lines - Typical Details
A20E Traffic Lines - Typical Details for Contrast Striping
A20F Pavement Markers and Traffic Lines - Typical Details
A20G Exit Ramp with Enhanced Pavement Markers for Wrong Way Details
A24A Pavement Markings - Arrows
A24B Pavement Markings - Arrows and Symbols
A24C Pavement Markings - Symbols and Numerals
A24D Pavement Markings - Words
A24E Pavement Markings - Words
A24F Pavement Markings - Crosswalks
A24G Pavement Markings - Yield Lines, Limit Lines, and Wrong Way Details
A24H Pavement Markings - Arrows
A62A Excavation and Backfill - Miscellaneous Details
A62F Excavation and Backfill - Metal and Plastic Culverts
A77L1 Midwest Guardrail System - Standard Railing Section (Wood Post with Wood Block)
A77M1 Midwest Guardrail System - Standard Hardware
A77N1 Midwest Guardrail System - Wood Post and Wood Block Details
A77N3 Midwest Guardrail System - Typical Line Post Embedment and Hinge Point Offset Details
A77N4 Midwest Guardrail System - Typical Height Measurement, Dike Positioning, and Delineation Details iii
A77N5 Minor Concrete Vegetation Control - Guardrail System
A77N6 Minor Concrete Vegetation Control - Guardrail System for Terminal System End Treatments
A77P1 Midwest Guardrail System - Typical Layouts for Embankments
RSP A77S1 Midwest Guardrail System - End Anchor Assembly (Type SFT - M)
A85 Chain Link Fence
A85A Chain Link Fence Details
A85B Chain Link Fence Details
A87A Curbs and Driveways
A87B Hot Mix Asphalt Dikes
D94A Metal and Plastic Flared End Sections
D97G Corrugated Metal Pipe Coupling Details No. 7 - Downdrain
D118 Ladder Details
D131 Infiltration Trench and Observation Well
D139A Gross Solids Removal Device - Inclined Screen Legend
D139B Gross Solids Removal Device - Inclined Screen Layout
RSP D139C Gross Solids Removal Device - Inclined Screen Details No. 1
D139D Gross Solids Removal Device - Inclined Screen Details No. 2
D139E Gross Solids Removal Device - Inclined Screen Details No. 3 - Wall Opening Details
RSP D139G1 Gross Solids Removal Device - Inclined Screen Details No. 6 - Pultruded FRP Screen
D139G2 Gross Solids Removal Device - Inclined Screen Details No. 7 - Pultruded FRP Screen
H1 Landscape and Erosion Control Symbols
H2 Landscape Details
H3 Landscape Details
H4 Landscape Details (Sprinkler Assembly)
H5 Landscape Details (Swing Joint and Protector)
H6 Landscape Details
H7 Landscape Details
RSP H8 Landscape Details
H9 Landscape Details
T1A Temporary Crash Cushion - Sand Filled (Unidirectional)
T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)
T1B Temporary Crash Cushion - Sand Filled (Bidirectional)
T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)
T3C Temporary Barrier System (Cross Bolt) iv
T3D Temporary Barrier System (Cross Bolt)
T3E Temporary Barrier System (Cross Bolt)
T3F Temporary Barrier System (Cal F-23)
T3F2 Temporary Barrier System (Cal F-23)
T3G Temporary Barrier System (Staking or Anchoring)
T3G2 Temporary Barrier System (Staking or Anchoring)
T9 Traffic Control System Tables for Lane and Ramp Closures
T10 Traffic Control System for Lane Closure on Freeways and Expressways
T10A Traffic Control System for Lane Closure on Freeways and Expressways
T51 Temporary Water Pollution Control Details (Temporary Silt Fence)
T53 Temporary Water Pollution Control Details (Temporary Cover)
T58 Temporary Water Pollution Control Details (Temporary Construction Entrance)
T59 Temporary Water Pollution Control Details (Temporary Concrete Washout Facility)
RS1 Roadside Signs - Typical Installation Details No. 1
RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2
RS4 Roadside Signs - Typical Installation Details No. 4
CANCELED STANDARD PLANS LIST
The 2025 standard plan sheets listed below are canceled and not applicable to this contract.
Plan No. Date Canceled Plan No. Date
Canceled Plan No. Date Canceled
P8 04-20-26
NOTICE TO BIDDERS
Bids open Thursday, November 19, 2026
Dated October 12, 2026
General work description: Construct treatment BMPs for stormwater mitigation.
The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON
STATE HIGHWAY IN VENTURA COUNTY IN AND NEAR OXNARD AND VENTURA FROM CENTRAL
AVENUE TO 0.6 MILE NORTH OF VICTORIA AVENUE.
District-County-Route-Post Mile: 07-Ven-101-17.7/R24.7
Contract No. 07-367604
The Contractor must have either a Class A license or any combination of the following Class C licenses which constitutes a majority of the work: C-27, C-12, C-42.
Federal-aid project no.:
NH-Q101(464)
Bids must be on a unit price basis.
Complete the work, excluding plant establishment work, within 200 working days.
Complete the work, including plant establishment work, within 450 working days.
Complete the plant establishment work within 250 working days.
The estimated cost of the project is $2,700,000.
The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.
The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.
For bid results go to:
https://ppmoe.dot.ca.gov/cc
Select Electronic Bidding under the Bidding tab.
District office addresses are provided in the Standard Specifications.
Present bidders' inquiries to the Department and view the Department's responses at:
https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries
Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.
Submit your bid with bidder's security equal to at least 10 percent of the bid.
Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.
The federal minimum wage rates for this Contract as determined by the United States Secretary of Labor are available at https://sam.gov/content/home.
If the minimum wage rates as determined by the United States Secretary of Labor differs from the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors must not pay less than the higher wage rate. The Department does not accept lower State wage rates not specifically included in the federal minimum wage determinations. This includes helper, or other classifications based on hours of experience, or any other classification not appearing in the federal wage determinations. Where federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors must not pay less than the federal minimum wage rate that most closely approximates the duties of the employees in question.
The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.
Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.
Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.
Department of Transportation
BID ITEM LIST
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM
0002 090100 TIME-RELATED OVERHEAD (WDAY) WDAY 200
0003 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM
0004 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM
0005 120165 CHANNELIZER (SURFACE MOUNTED) EA 64
0006 120207 PORTABLE RADAR SPEED FEEDBACK SIGN
SYSTEM
DAY 100
0007 120320 TEMPORARY BARRIER SYSTEM LF 1,560
0008 129105 TEMPORARY CRASH CUSHION TL-2 EA 2
0009 129108 TEMPORARY CRASH CUSHION TL-3 EA 4
0010 129152 TEMPORARY RADAR SPEED FEEDBACK SIGN
SYSTEM
EA 2
0011 130100 JOB SITE MANAGEMENT LS LUMP SUM
0012 130301 STORMWATER POLLUTION PREVENTION PLAN LS LUMP SUM
0013 130331 STORMWATER ANNUAL REPORT EA 1
0014 130570 TEMPORARY COVER SQYD 500
0015 130620 TEMPORARY DRAINAGE INLET PROTECTION EA 1
0016 130680 TEMPORARY SILT FENCE LF 1,000
0017 130710 TEMPORARY CONSTRUCTION ENTRANCE EA 2
0018 130730 STREET SWEEPING LS LUMP SUM
0019 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM
0020 141120 TREATED WOOD WASTE LB 3,000
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0021 170103 CLEARING AND GRUBBING (LS) LS LUMP SUM
0022 190101 ROADWAY EXCAVATION CY 70
0023 190105 ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY
DEPOSITED LEAD)
CY 240
0024 190139 ROADWAY EXCAVATION (UNSUITABLE
MATERIAL)
CY 570
0025 198050 EMBANKMENT CY 30
0026 200002 ROADSIDE CLEARING LS LUMP SUM
0027 202038 PACKET FERTILIZER EA 920
0028 202039 SLOW-RELEASE FERTILIZER LB 410
0029 204008 PLANT (GROUP H) EA 20,500
0030 204011 PLANT (GROUP K) EA 8
0031 204035 PLANT (GROUP A) EA 1,280
0032 204096 MAINTAIN EXISTING PLANTED AREAS LS LUMP SUM
0033 204099 PLANT ESTABLISHMENT WORK LS LUMP SUM
0034 205035 WOOD MULCH CY 780
0035 206300 TEMPORARY IRRIGATION SYSTEM LS LUMP SUM
0036 206400 CHECK AND TEST EXISTING IRRIGATION
FACILITIES
LS LUMP SUM
0037 206402 OPERATE EXISTING IRRIGATION FACILITIES LS LUMP SUM
0038 206405 REMOVE IRRIGATION FACILITY LS LUMP SUM
0039 206560 CONTROL AND NEUTRAL CONDUCTORS LS LUMP SUM
0040 206562 1" REMOTE CONTROL VALVE EA 1
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0041 206564 1 1/2" REMOTE CONTROL VALVE EA 18
0042 206761 24-32 STATION IRRIGATION CONTROLLER
(PEDESTAL MOUNTED)
EA 3
0043 208301 IRRIGATION CONTROLLER ENCLOSURE
CABINET
EA 3
0044 208426 2" BACKFLOW PREVENTER ASSEMBLY EA 1
0045 208445 TREE WELL SPRINKLER ASSEMBLY EA 16
0046 208446 RISER SPRINKLER ASSEMBLY (GEAR DRIVEN) EA 70
0047 208447 POP-UP SPRINKLER ASSEMBLY (GEAR DRIVEN) EA 18
0048 208448 RISER SPRINKLER ASSEMBLY EA 8
0049 208562 CAM COUPLER ASSEMBLY EA 4
0050 208575 2" GATE VALVE EA 1
0051 208588 3" GATE VALVE EA 1
0052 208595 (F) - 1" PLASTIC PIPE (SCHEDULE 40) (SUPPLY
LINE)
LF 2,970
0053 208597 (F) - 1 1/2" PLASTIC PIPE (SCHEDULE 40)
(SUPPLY LINE)
LF 2,195
0054 208605 (F) - 2" PLASTIC PIPE (CLASS 315) (SUPPLY LINE) LF 1,490
0055 208607 (F) - 3" PLASTIC PIPE (CLASS 315) (SUPPLY LINE) LF 210
0056 208610 HIGH DENSITY POLYETHYLENE PIPE CONDUIT LF 90
0057 208685 1 1/2" BALL VALVE EA 10
0058 260303 CLASS 3 AGGREGATE BASE (CY) CY 600
0059 280000 LEAN CONCRETE BASE CY 320
0060 390132 HOT MIX ASPHALT (TYPE A) TON 510
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0061 394073 PLACE HOT MIX ASPHALT DIKE (TYPE A) LF 35
0062 394076 PLACE HOT MIX ASPHALT DIKE (TYPE E) LF 30
0063 394090 PLACE HOT MIX ASPHALT (MISCELLANEOUS
AREA)
SQYD 45
0064 398000 REMOVE ASPHALT CONCRETE PAVEMENT (CY) CY 16
0065 398100 REMOVE ASPHALT CONCRETE DIKE LF 760
0066 401050 JOINTED PLAIN CONCRETE PAVEMENT CY 60
0067 510502 (F) - MINOR CONCRETE (MINOR STRUCTURE) CY 21.3
0068 038422 DPP INFILTRATION AREA (ROCK)(CY) CY 200
0069 621208 GROSS SOLIDS REMOVAL DEVICE INCLINED
SCREEN TYPE A (FRP SCREEN)
EA 1
0070 018530 CAPTURE HOUSING TYPE B (M)(5<D<6) EA 1
0071 641104 15" PLASTIC PIPE LF 14
0072 650411 18" REINFORCED CONCRETE PIPE (CLASS IV) LF 59
0073 665017 18" CORRUGATED STEEL PIPE (.079" THICK) LF 120
0074 705011 18" STEEL FLARED END SECTION EA 2
0075 710126 REMOVE OVERSIDE DRAIN EA 5
0076 710136 REMOVE PIPE (LF) LF 52
0077 710150 REMOVE INLET EA 2
0078 710196 ADJUST INLET EA 1
0079 010892 REMOVE ROCK SLOPE PROTECTION CY 24
0080 723080 ROCK SLOPE PROTECTION (60 LB, CLASS II,
METHOD B) (CY)
CY 26
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0081 723095 ROCK SLOPE PROTECTION (20 LB, CLASS I,
METHOD B) (CY)
CY 90
0082 729011 ROCK SLOPE PROTECTION FABRIC (CLASS 8) SQYD 860
0083 730045 MINOR CONCRETE (GUTTER) (CY) CY 4
0084 731504 MINOR CONCRETE (CURB AND GUTTER) CY 4
0085 731840 REMOVE CONCRETE (CURB AND GUTTER) LF 150
0086 750001 (F) - MISCELLANEOUS IRON AND STEEL LB 2,284
0087 800360 CHAIN LINK FENCE (TYPE CL-6) LF 170
0088 802501 4' CHAIN LINK GATE (TYPE CL-6) EA 1
0089 802580 12' CHAIN LINK GATE (TYPE CL-6) EA 5
0090 803050 REMOVE CHAIN LINK FENCE LF 170
0091 820113 TREATMENT BEST MANAGEMENT PRACTICE
MARKER
EA 16
0092 820610 RELOCATE ROADSIDE SIGN EA 2
0093 832007 MIDWEST GUARDRAIL SYSTEM (WOOD POST) LF 150
0094 832070 VEGETATION CONTROL (MINOR CONCRETE) SQYD 79
0095 839580 END ANCHOR ASSEMBLY (TYPE SFT-M) EA 1
0096 015299 ALTERNATIVE IN-LINE TERMINAL TL-3 EA 1
0097 839752 REMOVE GUARDRAIL LF 76
0098 999990 MOBILIZATION LS LUMP SUM
SPECIAL PROVISIONS
ORGANIZATION
Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.
Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.
Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.
DIVISION I GENERAL PROVISIONS
1 GENERAL
Add to section 1-1.01:
Bid Items and Applicable Sections
Item code
Item description Applicable section
018530 CAPTURE HOUSING TYPE B (M)(5<D<6) 62
038422 DPP INFILTRATION AREA (ROCK) (CY) 62
010892 REMOVE ROCK SLOPE PROTECTION 72
015299 ALTERNATIVE IN-LINE TERMINAL TL-3 83
2 BIDDING
Add between the 1st and 2nd paragraphs of section 2-1.06B:
The Department makes the following supplemental project information available:
Supplemental Project Information Means Description
Included in the Information Handout -Landscape irrigation as-builts -City of San Buenaventura Encroaching Permits Insurance Matrix -City of Ventura Public Works Encroachment permit application -City of Ventura Public Works Encroachment Permit Procedures -Concentration Data and Sample Location Maps for Regulated Material
Delete section 2-1.20.
Delete section 2-1.33B(2)(b).
5 CONTROL OF WORK
Delete section 5-1.13B.
Replace section 5-1.13E with:
5-1.13E Prompt Payment Section 5-1.13E applies to all contracts.
Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.
Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:
1. Subcontractor’s or entity’s business name
2. Description of work performed
2.1. Bid item numbers or change order numbers
2.2. Written narrative of work performed
3. Value of work performed
4. Amount paid to subcontractor or entity
5. Withhold amount, if applicable
6. Explanation of withhold reasoning, if applicable
Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.
If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:
1. Value of the disputed work
2. Amount of the withhold being taken
3. Bid item numbers or change order numbers associated with the disputed work
4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated
5. Corrective actions to be taken for release of withheld amount
The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.
The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:
1. Withhold was not applied in good faith
2. Requested additional withhold documentation records were not provided
3. Payment information was not submitted through the prompt payment monitoring system
4. Required withhold notification was not provided
The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.
Add to the end of section 5-1.20C:
This project does not include work on the railroad property, but a railroad is shown on the general plan sheet within the project limits. Do not trespass on the railroad property at Route VEN-101 - PM R24.36 -
DOT#745833H - RMP 403.04 - Montalvo Subdivision - Ventura SCRRA and Route VEN-101 - PM R24.00 - DOT#745834P - RMP 403.13 - Montalvo Subdivision - Ventura - SCRRA.
Replace section 5-1.36C(2) with:
5-1.36C(2) Nonhighway Facility Protection The utilities shown in the following table may interfere with the work and must be exposed or protected in place. Make arrangements with the utility owner (1) to conduct or witness all exposures or (2) to request temporary deactivation of the utility.
Utilities to Be Exposed and/or Protected in Place During Construction Utility Location
City of Camarillo Storm Drain 72” Casing crossing Ven-101 @ Approx Sta 940+30
City of Ventura Sewer District Contact: Engineering Address: 501 Poli St, Ventura, CA 93001 Phone No: 805-654-7887
12” VCP sewer along Ventura Rd @ Approx Sta 1258+80 to Sta 1261+00 12” VCP sewer along Ventura Rd @ Approx Sta 1271+20 18” VCP sewer along Ventura Rd @ Approx Sta 1285+00 to Sta 1287+00
City of Ventura – Water District Contact: Amanda Deleon Address: 336 Sanjon Rd, Ventura, CA 93002 Phone No: 805-652-4591 E-mail: adeleon@cityofventura.ca.gov
18” water along Ventura Rd @ Approx Sta 1285+00 to Sta 1287+00
SCG
Contact: Jason Sum Address: 701 N Bullis Rd ML 9530, Compton, CA 90221 Phone No: 310-687-2011 E-mail: northwestdistributionutilityrequest@semprautilities.com
12” gas along Ventura Rd @ Approx Sta 1258+80 to Sta 1261+00 12” gas along Ventura Rd @ Approx Sta 1271+20 12” gas along Ventura Rd @ Approx Sta 1285+00 to Sta 1287+00
AT&T
Contact: Joseph Forkert Address: 22311 Brookhurst St Ste 203, Huntington Beach, CA 92646 Phone No: 714-963-7964 E-mail: joef@forkertengineering.com
Underground Telecomm Along Ven- 101 @ Approx Sta 1251+50 to Sta 1253+80
The utility information shown is incomplete. Utility location activities must be concurrent with construction activities. Make arrangements with the utility owners to coordinate activities. At least 48 hours before you disturb soil, request that the Department mark the location of Department-owned underground facilities.
Failure to submit the request prohibits soil disturbance.
The utility information is not shown. Utility location activities must be concurrent with construction activities. Make arrangements with the utility owners to coordinate activities. Do not use power-operated or power-driven excavation or boring equipment within 24 inches horizontally of the exterior surface of any subsurface facilities.
6 CONTROL OF MATERIALS
Add to end of section 6-1.01:
If you fail to submit the form for materials subject to Buy America, the Department may:
1. Withhold from the next progress payment
2. Reject your request for a De Minimis Costs waiver for non-compliant construction materials or manufactured products
Replace section 6-1.03B with:
6-1.03B Submittals 6-1.03B(1) General Not Used
6-1.03B(2) Work Plan For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:
1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under section 6-1.03B(3) for other constituents of concern based on the land use history. I am aware that local material sources must not contain ADL at concentrations greater than 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II. I am aware that a maximum quantity of material may be excavated at the site based on the minimum number of samples taken before excavating at the site under section 6-1.03B(3).
2. Land use history of the local material location and surrounding property
3. Sampling protocol
4. Number of samples per volume of local material
5. QA and QC requirements and procedures
6. Qualifications of sampling personnel
7. Stockpile history
8. Name and address of the analytical laboratory that will perform the chemical analyses
9. Analyses that will be performed for lead and pH
10. Other analyses that will be performed for possible hazardous constituents based on:
10.1. Source property history
10.2. Land use adjacent to source property
10.3. Constituents of concern in the ground water basin where the job site is located
The plan must be sealed and signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State.
If the plan requires revisions, the Engineer provides comments. Submit a revised plan within 7 days of receiving comments. Allow 7 days for the review.
6-1.03B(3) Analytical Test Results At least 15 days before placing local material, submit analytical test results for each local material obtained from a noncommercial source or a source not regulated under CA jurisdiction. The analytical test results must include:
1. Certification signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
The analytical testing described in the local material plan has been performed. I performed a statistical analysis of the test results using the US EPA's ProUCL software with the applicable 95 percent upper confidence limit. I certify that the material from the local material source is suitable for unrestricted use at the job site, it has a pH above 5.0, does not contain soluble lead in concentrations equal to or greater than 5mg/l as determined by the Waste Extraction Test
(WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II, does not contain lead in concentrations above 80 mg/kg total lead, is free from all other contaminants identified in the local material plan, and will comply with the job site's basin plan and water quality objectives of the RWQCB.
2. Chain of custody of samples
3. Analytical results no older than 1 year
4. Statistical analysis of the data using US EPA’s ProUCL software with a 95 percent upper confidence limit
5. Comparison of sample results to hazardous waste concentration thresholds and the RWQCB's basin plan requirements and water quality objectives for the job site location
6-1.03B(4) Sample and Analysis Sample and analyze local material from a (1) noncommercial source or (2) a source not regulated under CA jurisdiction:
1. Before bringing the local material to the job site
2. As described in the local material plan
3. Under US EPA Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846)
The sample collection must be designed to generate a data set representative of the entire volume of proposed local material.
Before excavating at the (1) noncommercial material source or (2) a source not regulated under CA jurisdiction, collect the minimum number of samples and perform the minimum number of analytical tests for the corresponding maximum volume of local material as shown in the following table:
Minimum Number of Samples and Analytical Tests for Local Material Maximum volume of imported borrow
(cu yd) Minimum number of samples and analytical tests
< 5,000 8
5,000–10,000 12 for the first 5,000 cu yd plus 1 for each additional 1,000 cu yd or portion thereof
10,000–20,000 17 for the first 10,000 cu yd plus 1 for each additional 2,500 cu yd or portion thereof
20,000-40,000 21 for the first 20,000 cu yd plus 1 for each additional 5,000 cu yd or portion thereof
40,000–80,000 25 for the first 40,000 cu yd plus 1 for each additional 10,000 cu yd or portion thereof
> 80,000 29 for the first 80,000 cu yd plus 1 for each additional 20,000 cu yd or portion thereof
Do not collect composite samples or mix individual samples to form a composite sample.
Analyze the samples using the US EPA's ProUCL software with a 95 percent upper confidence limit. All chemical analysis must be performed by a laboratory certified by the SWRCB's Environmental Laboratory Accreditation Program (ELAP).
The analytical test results must demonstrate that the local material:
1. Is not a hazardous waste
2. Has a pH above 5.0
3. Has an average total lead concentration, based upon the 95 percent upper confidence limit, at or below 80 mg/kg
4. Is free of possible contaminants identified in the local material plan
5. Complies with the RWQCB's basin plan for the job site location 6 Complies with the RWQCB's water quality objectives for the job site location
6-1.03C Local Material Management Do not place local material until authorized.
If the Engineer determines the appearance, odor, or texture of any delivered local material suggests possible contamination, sample and analyze the material. The sampling and analysis is change order work unless (1) hazardous waste is discovered or (2) the analytical test results indicate the material does not comply with section 6-1.03B(3).
Dispose of noncompliant local material at an appropriately permitted CA Class I, CA Class II or CA Class III facility. You are the generator of noncompliant local materials.
Replace section 6-1.04 with:
6-1.04 BUY AMERICA
6-1.04A General Buy America requirements do not apply to the following:
1. Tools and construction equipment used in performing the work.
2. Temporary work that is not incorporated into the finished project.
An article, material, or supply to be permanently incorporated in the project should only be classified into one of the following categories:
1. Iron or steel products
2. Manufactured products
3. Construction materials
4. Excluded materials
Excluded materials means cement and cementitious materials; aggregates such as stone, sand, or gravel; or aggregate binding agents or additives.
6-1.04B Crumb Rubber (Pub Res Code § 42703(d)) Furnish crumb rubber with a certificate of compliance. Crumb rubber must be:
1. Produced in the United States
2. Derived from waste tires taken from vehicles owned and operated in the United States
6-1.04C Iron or Steel Products Iron or steel products must be melted and manufactured in the United States except:
1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials
2. If the total combined cost of the materials produced outside the United States does not exceed the greater of 0.1 percent of the total bid or $2,500, the material may be used if authorized
Furnish iron or steel products to be incorporated into the work with certificates of compliance and certified mill test reports. Mill test reports must indicate where the steel and iron were melted and manufactured.
All melting and manufacturing processes for these materials, including an application of a coating, must occur in the United States. Coating includes all processes that protect or enhance the value of the material to which the coating is applied.
6-1.04D Manufactured Products Manufactured products mean articles, materials, or supplies that have been:
1. Processed into a specific form and shape; or
2. Combined with other articles, materials, or supplies to create a product with different properties than the individual articles, materials, or supplies
Per 23 CFR 635.410, these products must be manufactured in the United States.
Manufacturer, in the case of manufactured products, means the entity that performs the final manufacturing process by bringing individual elements together that produces a manufactured product.
If an item is classified as an iron or steel product, a construction material, or an excluded material under the definitions set forth under this Buy America section, then it is not a manufactured product. However, an article, material, or supply classified as a manufactured product under this Buy America section may include components that are construction materials, iron or steel products, or excluded materials.
Iron or steel used in precast concrete manufactured products or enclosures for Intelligent Transportation Systems (ITS) must meet the requirements of section 6-1.04C regardless of the amount used.
Iron or steel used in other manufactured products must meet the requirements of section 6-1.04C if the cost of steel and iron components is 50 percent or more of the total cost of the manufactured product.
Furnish manufactured products to be incorporated into the work with certificates of compliance with each project delivery. The manufacturer's certificate of compliance must identify where the manufacturing occurred and attest specifically to compliance with the 23 CFR 635.410 standard.
6-1.04E Construction Materials The following construction materials must be produced in the United States under standards in 2 CFR 184.6:
1. Non-ferrous metals
2. Plastic and polymer-based products such as:
2.1. Polyvinylchloride
2.2. Composite building materials
3. Glass
4. Fiber optic cable including drop cable
5. Optical fiber
6. Lumber
7. Engineered wood
8. Drywall
All manufacturing processes for these materials as defined in 2 CFR 184.6 must occur in the United States.
Furnish construction materials to be incorporated into the work with certificates of compliance with each project delivery. Manufacturer’s certificate of compliance must identify where the construction material was manufactured and attest specifically to compliance with the 2 CFR 184.6 standard.
Minor additions of articles, materials, supplies, or binding agents to these construction materials do not change the categorization of the construction material.
6-1.04F Buy America Waiver for the De Minimis Costs for Manufactured Products and Construction Materials A De Minimis Costs waiver can waive the application of FHWA's Buy America requirements for manufactured products and construction materials under a single project when the total cost of non-compliant manufactured products and construction materials is no more than the lesser of $1,000,000 or 5 percent of the total applicable costs for the project.
The percentage threshold is calculated based on the following formula:
X = NC / TA
where:
X = percent threshold NC = total cost of non-compliant construction materials and manufactured products TA = total applicable project costs (steel, iron, construction materials and manufactured products;
does not include excluded materials)
This threshold is based on the actual cost of the steel, iron, construction materials, and manufactured products, not the anticipated cost of those materials. The contractor must account for compliant and non-compliant Department-Furnished Materials for the project in the De Minimis Costs Waiver Worksheet calculation if provided by the Department as supplemental project information.
See further instructions for the De Minimis Costs waiver request in the Notice of Materials to be Used form.
Add to section 6-1:
6-1.08 ENVIRONMENTAL PRODUCT DECLARATIONS FOR HOT MIX ASPHALT AND CONCRETE
Section 6-1.08 includes specifications for environmental product declarations for hot mix asphalt and concrete materials and products.
See section 6-1.06B for definitions.
For projects with bid opening dates after February 1, 2025, with a total bid over $1 million and 175 or more original working days, materials or products specified in the following table require facility-specific, product stage, environmental product declarations as informational submittals:
Material or product Material specifications Hot mix asphalta Section 39-2, "Hot Mix Asphalt"
Excludes RHMA, OGFC, and BWC materials.
Concreteb Section 28-2, "Lean Concrete Bases," Section 28-3, "Rapid
Strength Concrete Base," Section 28-4, "Lean Concrete Base Rapid Setting," Section 28-5, "Concrete Base," Section 40, "Concrete Pavement," Section 47-5, "Type 6 Retaining Walls," Section 49-3, "Cast-In-Place Concrete Piling," Section 49-4, "Steel Soldier Piling," Section 51, "Concrete Structures," Section 58-2, "Masonry Block," Section 73, "Concrete Curbs and Sidewalks," Section 83, "Railings and Barriers," and Section 99, "Building Construction."
Excludes volumetric-proportioned rapid strength concrete and Section 90-4 PC concrete members.
aFor each hot mix asphalt plant providing 2,250 tons or more on the project by job mix formula.
bFor each concrete plant providing 250 cubic yards or more on the project by mix design.
The requirements in section 6-1.08 do not apply to seasonal plants operating fewer than 6 months per year.
The requirements in section 6-1.08 do not apply to informal-bid contracts.
For product category rules for hot mix asphalt or concrete, go to the METS website. Use the product category rule in effect on the date of bid opening unless otherwise authorized. An environmental product declaration for hot mix asphalt or concrete is not required for either of the following conditions:
1. Applicable product category rule has expired without replacement as of the bid opening date.
2. Applicable product category rule was issued less than 50 days before the bid opening date.
Immediately notify the Engineer if a program operator has determined their product category rule does not allow for development of a facility-specific environmental product declaration. Include written correspondence from the program operator with your notification to the Engineer. If the Engineer determines the development of a facility-specific environmental product declaration cannot be achieved, an environmental product declaration will not be required for that material or product.
You must register on the Department’s Data Interchange for Materials Engineering (DIME) at least 15 days before submitting environmental product declarations. Follow the registration process at:
https://dime.dot.ca.gov/
Within 30 days of initial placement of each applicable material or product, submit a facility-specific, product stage, environmental product declaration informational submittal to DIME and provide proof of submission in PDF file format to the Engineer. The DIME entry information must include intended use of materials and estimated quantities of materials to be used as represented by the environmental product declaration.
Failure to provide a required environmental product declaration informational submittal will result in a $6,000 performance failure withhold for each missing declaration. The Department returns the withhold within 30 days after receipt of the compliant declaration if submitted prior to Contract acceptance.
Withholds become permanent deductions if the declaration is not submitted before Contract acceptance.
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
Replace Section 7-1.02K(6)(j)(iii) with:
7-1.02K(6)(j)(iii) Unregulated Earth Material Containing Lead Section 7-1.02K(6)(j)(iii) includes specifications for handling, removing, and disposing of unregulated earth material containing lead. Management of this material exposes workers to health hazards that must be addressed in your lead compliance plan. This material contains average lead concentrations below 80 mg/kg total lead and below 5 mg/L soluble lead and is not regulated by DTSC as a hazardous substance or a hazardous waste. This material does not require disposal at a permitted landfill or solid waste disposal facility. The RWQCB has jurisdiction over reuse of this material at locations outside the job site limits.
Manage regulated earth material containing lead under sections 14-11.08 and 14-11.09.
Unregulated earth material containing lead is present on the job site at the following locations:
Location Element of work Depth Drainage System 1, NB, PM 17.7 DPPIA any Drainage System 2, SB, PM 17.8 DPPIA any Drainage System 3, NB, PM 18.2 DPPIA, MVP any Drainage System 4, NB, PM 18.6 DPPIA any
Drainage System 5, NB, PM R23.5 CHD any Drainage System 6, SB, PM R23.7 BST, MVP any Drainage System 9, NB, PM R24.4 GSRD any Drainage System 10, NB, PM R24.7 DPPIA any
Unregulated earth material exists throughout the job site.
Lead is typically found within the top 2 feet of material within the highway. Reuse all of the excavated material on the right-of-way. Haul and place the surplus excavated material on the right-of-way at planned fill area.
Unregulated earth material containing lead has been detected to a depth of 2 feet within the job site.
Unregulated levels of lead found range from 4.0 to 70 mg/kg total lead with an average concentration of
27.9 mg/kg total lead as analyzed by EPA test method 6010 or EPA test method 7000 series and based upon a 95 percent upper confidence limit. Unregulated levels of lead on the job site have a predicted average soluble concentration of 1.25 mg/L as analyzed by the California Waste Extraction Test and based upon a 95 percent upper confidence limit.
Handle the material under all applicable laws, rules, and regulations, including those of the following agencies:
1. Cal/OSHA
2. CA RWQCB, Region 4 - Los Angeles
3. Ventura County Air Pollution Control District
If unregulated material is disposed of:
1. Submit at least 15 days before disposal, the form titled "Agreement between a Contractor Working on State Facilities and a Real Property Owner for Disposing Construction-related Material Suitable for Use on Residential Zoned Property" which discloses the lead concentration of the material to the receiving property owner and obtains authorization for disposal on the property. Give a copy of the signed form to the property owner.
2. You are responsible for any additional sampling and analysis required by the receiving property owner.
If you choose to dispose of unregulated material at a commercial landfill:
1. Transport it to a Class III or Class II landfill appropriately permitted to receive the material
2. You are responsible for identifying the appropriately permitted landfill to receive the material and for all associated trucking and disposal costs, including any additional sampling and analysis required by the receiving landfill
8 PROSECUTION AND PROGRESS
Replace the row for DBE and DVBE in the table in the 2nd paragraph of section 8-1.03 with:
DVBE Final utilization reports
Replace the row for Schedule in the table in the 2nd paragraph of section 8-1.03 with:
Schedule Baseline schedule and weekly statement of working days report
Replace the 4th and 5th paragraphs of section 8-1.05 with:
The Engineer issues a weekly statement of working days report by the end of the following week. If you disagree with a weekly statement of working days report, submit an RFI within 5 business days of receipt of the report.
The weekly statement of working days report shows:
1. Working days and non–working days during the reporting week
2. Time adjustments
3. Calculations of work completion dates, including working days remaining
4. Controlling activities
Delete the 6th paragraph of section 8-1.05.
9 PAYMENT
Replace the 1st paragraph of section 9-1.11D with:
For progress payments, the total work completed for the TRO bid item is the number of working days shown for the pay period on the weekly statement of working days report.
Replace item 2 in the list in the paragraph of section 9-1.16C with:
2. Material cost exceeds either of the following:
2.1. $50,000
2.2. $25,000 if the requestor is certified as one or more of the following:
2.2.1. DVBE
2.2.2. Small business as certified by Department of General Services, Office of Small
Business and Disabled Veteran Business Enterprise Services
DIVISION II GENERAL CONSTRUCTION
12 TEMPORARY TRAFFIC CONTROL
Add to section 12-3.11B(5)(b):
Provide two C50D(CA) construction project funding identification signs.
Legend for the type of project must read as follows:
ROADSIDE WORK
Legend for the year of completion on project funding sign must read as follows:
YEAR OF COMPLETION: 2028
Replace section 12-3.20 with:
12-3.20 TEMPORARY BARRIER SYSTEMS
12-3.20A General 12-3.20A(1) Summary Section 12-3.20 includes specifications for temporary barrier systems.
Temporary barrier system consists of:
1. New or undamaged used interconnected barrier segments
2. Segment connection hardware
3. Stakes and anchor bolts
Value engineering change proposals for the use of Type K temporary railing are not allowed.
If a discrepancy exists, governing ranking in descending order is:
1. These specifications
2. Approved manufacturer's drawings
3. Approved manufacturer's installation instructions
Markers must comply with section 82.
12-3.20A(2) Definitions anchored: Method for attaching temporary barrier segments to concrete pavement.
approach zone: Area immediately upstream of the protected area.
clear area width: Minimum width throughout the length of the barrier system that must be maintained clear of obstructions, objects, and work resources during non-working hours. The width is measured perpendicular from the non-traffic side toe.
departure zone: Area immediately downstream of the protected area.
freestanding: Temporary barrier not attached to the pavement.
height differential: May be an excavation, a downward slope greater than 4:1, or a difference in elevation. The height differential is measured down from the top of pavement.
minimum system length: Sum of approach zone, protected area, and departure zone.
set back distance: Measured between the closest toe of temporary barrier and the edge of traveled way for each direction of traffic.
staked: Method for attaching temporary barrier segments to asphalt concrete pavement.
12-3.20A(3) Submittals Submit as informational submittal for each type of temporary barrier system:
1. Certificate of compliance.
2. Manufacturer's installation instructions and Department approved manufacturer’s drawings from the
Department’s Division of Safety Programs website, except for temporary concrete barriers Cross Bolt and CAL F-23.
3. Manufacturer's concrete QC test results and daily production log of precast concrete activities, under section 90-4. QC test results must include the concrete mix design number and barrier stamped ID.
Submit connection bolt test reports that certify compliance with the applicable ASTM requirements, for temporary barrier systems Cross Bolt. The test reports must be from a laboratory that is accredited to International Standards Organization/International Electrotechnical Commission 17025 by the American Association for Laboratory Accreditation (A2LA) or the ANSI-ASQ National Accreditation Board.
Submit a signed manufacturer's replacement evaluation report within 10 days of damage to a temporary steel barrier system.
12-3.20A(4) Quality Assurance 12-3.20A(4)(a) General QC sampling, testing, and inspection personnel must have an ACI Concrete Field-Testing Technician, Grade 1 certification.
Temporary concrete barrier segments must:
1. Comply with the requirements for tier 3 precast concrete in section 90-4
2. Be fabricated at a plant on the Authorized Facility Audit List
Concrete must be sampled and tested as shown in the following table.
Concrete QC Tests Quality characteristic Test method Minimum testing frequency
Compressive strength ASTM C172/C172M, ASTM C31/C31M, and
ASTM C39/C39M
Once per 300 cu yd of concrete cast, or every day of casting, whichever is more frequent
Slump ASTM C143/C143M Temperature at time of mixing ASTM C1064/C1064M Density ASTM C138 Once per 600 cu yd of concrete cast or every 7 days of batching, whichever is more frequent
Air content ASTM C231/C231M or
ASTM C173/C173M
If concrete is air entrained, once for each set of cylinders, and when conditions warrant
A daily production log of precast concrete activities must be maintained under section 90-4.01C(4).
12-3.20A(4)(b) Quality Control Not Used
12-3.20B Materials 12-3.20B(1) General Temporary barrier segment must:
1. Be a minimum 31-1/2 inches in height
2. Have at least two lifting holes
3. Be designed to be used with temporary traffic screen when required
Temporary barrier segment may have your name or logo on each barrier segment. The name or logo must be no more than 4 inches in height and must be located no more than 12 inches above the bottom of the barrier segment.
Temporary barrier systems must comply with a minimum MASH Test Level 3.
Except for Cross Bolt, and CAL F-23, temporary barrier systems must:
1. Be on the Authorized Materials List for highway safety features
2. Comply with the manufacturer's drawings shown on the Department's Division of Safety Programs website and the manufacturer's installation instructions
12-3.20B(2) Temporary Concrete Barriers 12-3.20B(2)(a) General Not Used
12-3.20B(2)(b) Temporary Concrete Barriers Type F 12-3.20B(2)(b)(i) General Temporary concrete barrier Type F segment must:
1. Be precast concrete with a minimum 5,000-psi compressive strength.
2 Have bar or welded wire reinforcement steel that complies with section 52.
3. Have a finished surface that complies with section 51-1.03F(2).
4. Include the manufacturer's name, lot number, and month and year of manufacture stamped on the top of each barrier segment. The stamped information must be:
4.1. No more than 6 inches in height
4.2. From 3/16 to 1/4 inch in depth
4.3. Centered on the top width of the barrier segment
5. Use one of the following segment connections:
5.1. Loop and pin
5.2. "J" hook
5.3. Cross Bolt
6. Comply with the tolerances shown in the following table:
Precast Barrier Tolerances Dimension Tolerance(±)
Length (in) 1 Insert placement (in) 1/2 Horizontal alignment (in) 1/8 per 10 feet of length Deviation of ends (in):
Horizontal skew Vertical batter
1/4 1/8 per foot of depth
Bar reinforcement steel must:
1. Comply with ASTM A615 or ASTM A706, Grade 60
2. Be galvanized under section 52-3, when shown
Welded wire reinforcement must comply with ASTM A1064.
Stake must:
1. Be steel and comply with ASTM A36/A36M-14 or ASTM A529-14, Grade 50
2. Be 1-1/2 inches in diameter and 36 inches long, except "J" Hook must be 48 inches long
3. Have a 1/2-by-3-1/2-by-3-1/2-inch plate welded 2 inches down from the upper end using a 3/8-inch fillet weld under AWS D1.1 or D1.4
Anchor bolt must:
1. Be a steel bolt or threaded rod 1-1/8 inches in diameter
2. Comply with ASTM A307
3. Include a 1/2-by-3-1/2-by-3-1/2-inch plate washer:
3.1. With a 1-3/8-inch-diameter hole in the center
3.2. Complying with ASTM A36/A36M
3.3. Galvanized post fabrication under section…