This document is an Invitation to Bid (ITB 068-25) issued by the Ohio Department of Transportation (ODOT) for a multiple-award contract covering chain link fence, right-of-way fence, and snow fence materials and installation. The contract is structured as a multiple-award, meaning ODOT will accept all responsive bids and make awards to multiple vendors who meet the specified requirements.

The contract covers the procurement of fence components including chain link, right-of-way, and wooden/plastic snow fences, along with associated installation services. The contract duration is from November 1, 2024, through October 31, 2024, with specific detailed specifications for fence materials, including requirements for slat dimensions, wire gauge, post types, and material composition. Vendors are required to provide itemized pricing for materials and installation, with compensation structured to include mobilization fees, mileage reimbursement, and provisions for multiple project sites. Delivery is expected within 10 calendar days of order, with deliveries restricted to Monday through Friday between 7:00 a.m. and 4:30 p.m., and vendors must submit material specification data sheets for all bid items.

View the file

Other files

File Type Posted
ODOT_068-25_Affirmation__1_.pdf PDF
Signature.pdf PDF
ODOT_068-25_BID_ITEMS.xls XLS spreadsheet
ODOT_Co-Op_Program_Information.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB 068-25 Requirements/Specifications 9/3/24 Chain Link, Right of Way, and Snow Fence

Section 1: Intent

The purpose of this invitation is to establish prices for the purchase of Chain-Link fence components, Right-of-Way Fence components, Snow Fence components, and installation of fence.

Section 2: Multiple Award

Due to the nature of the items and services required or when a specific job is to be performed, the Department will accept all responsive bids submitted on or before the specified bid opening date and make an award to all responsive bidders. Therefore, this invitation constitutes a multiple award as set out in Section 5513.02 of the Ohio Revised Code.

An award does not guarantee that your company will receive a purchase order during the term of this contract, or that material will be released against an issued purchase order.

A vendor is not required to bid on every Section to be considered for award.

Vendors must submit their Bid Responses electronically in OhioBuys before the published deadline date & time, Columbus, Ohio local time on the Proposal due date. Vendors will not be able to submit Bid Responses, or unsolicited Proposal amendments after the deadline.

Vendors must allow adequate time for uploading a Bid Response prior to the due date and time.

ODOT recommends that vendors submit Bid Responses as early as possible. If a second round is issued for any reason, vendors must resubmit their bid if they had already submitted in a previous round, as the previously submitted Bid Responses do NOT carry over to the new round.

The Signature process takes place after the award now. The email will come from documents@esign.ohio.gov and will go to the signatory that was identified in the bid submission.

The subject line will be the bid # Signature Request, (example: 101G-25 Signature Request).

No contract can be issued to your company until we receive your signature to complete the process.

And you must have an OAKS Payor ID before a contract can be issued. To obtain that, you will need to go into https://ohiopays.ohio.gov.

Section 3: Contract Duration

The effective duration of this contract shall be from November 1, 2024 through October 31, 2024.

Section 4: Terms and Conditions

4.1 Description: The purpose of this contract is to provide Chain Link fence, Right of Way fence, and Snow Fence materials. Materials being requested for erecting the Chain Link fence or Right of Way fence will be listed on the pricing sheet.

4.2 Specifications:

4.2a Chain Link Fence:

Specifications for fence shall be in conformance with Item 607 of the current Construction and Materials Specifications at the time of bid.

Refer to Standard Construction Drawing F-1.1 for additional conformance requirements for Chain Link Fence materials.

https://www.dot.state.oh.us/SCDs/Roadway/F-1.1_2013-07-19.pdf mailto:documents@esign.ohio.gov https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fohiopays.ohio.gov%2F&data=05%7C02%7CTodd.VanKirk%40dot.ohio.gov%7C1ac0731aa3fa4f066d5408dc7b4d0c36%7C50f8fcc494d84f0784eb36ed57c7c8a2%7C0%7C0%7C638520818049379076%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=v8I%2Ba6H4M2smMVdNcvpoDrB2Dqsn4%2FJvMONLWyfwoxE%3D&reserved=0 https://www.dot.state.oh.us/SCDs/Roadway/F-1.1_2013-07-19.pdf

4.2b Refer to Standard Construction Drawing F-2.1 for additional conformance requirements for

Right of Way Fence materials.

https://www.dot.state.oh.us/SCDs/Roadway/F-2.1_2018-07-20.pdf

4.2c Refer to Standard Construction Drawing F-3.2 for additional conformance requirements for

Walk Gate materials.

https://www.dot.state.oh.us/SCDs/Roadway/F-3.2_2014-07-18.pdf

4.2d Wooden Snow Fence

Slats: Slats are to be made of No. 1 Aspen or Spruce measuring (3/8") three-eighths inches thick, one and one-half (1-1/2") inches wide and 48 inches long. Variation in width is not to exceed one sixteenth (1/16") inch nor one-quarter (1/4") inch in length. Thickness is to be a minimum of three-eighths (3/8") inches thick but not to exceed 9-sixteenths (9/16") inches.

Both ends are to be cut square. The slats are to be painted with good quality red iron oxide stain or equivalent.

Wire: Slats are woven with 5 double-strands of 12½ gauge galvanized wire.

Post: The post for erecting the snow fencing are to be made of hot rolled rail steel and formed into a “T”. Dimensions of “T” post section, approximately 1 7/16” X 1 5/16” x 1/8” x 6’ (six feet) long. Weight of post section without anchor is 1.25 pounds per foot. Area of anchor plates 23 square inches.

The post shall be painted green or galvanized.

Fence Post Minimum of 12½ gauge galvanized wire ties or approved equivalent.

Tie Wire: A minimum of 8 inches in length is required.

4.2e Plastic Snow Fence

Fence Material: High Density Polyethylene Porosity: 50% +/-5% Tensile Strength: 100 lb/ft minimum Height: 48 inch Temperature Range: -50º F to 150º F Resistant: UV degradation resistant Posts: The post for erecting the snow fencing are to be made of hot rolled rail steel and formed into a “T”. Dimensions of “T” post section, approximately 1 7/16” X 1 5/16” x 1/8” x 6’ (six feet) long. Weight of post section without anchor is 1.25 pounds per foot. Area of anchor plates 23 square inches. The post shall be painted green or galvanized.

Fence Post Zip Tie: Plastic zip ties of sufficient tensile strength (minimum 120 lbs). A minimum of 8 inches in length is required.

The vendor shall be responsible for following the current Construction and Material Specifications (C&MS) and current Supplemental Specifications at the time of award.

Specifications: Vendor shall provide a copy of the material specifications data sheet (SDS) for any materials bid.

https://www.dot.state.oh.us/SCDs/Roadway/F-2.1_2018-07-20.pdf https://www.dot.state.oh.us/SCDs/Roadway/F-3.2_2014-07-18.pdf

4.4 Parts and Materials

A list of parts are materials are provided on the pricing page for the various types of fence.

Additional parts and materials relating to the fences, whether it is additional parts or materials that may be used for installation, should be added/included on the pricing page.

4.3 Installation & Mobilization:

From time to time, ODOT may request installation of fence. This could range from a section of fence being replaced to a complete run of fencing.

Installation: This shall include all work necessary to have a final in-place fence per the Standard Construction Drawings, C&MS and/or ODOT representative.

In order to accurately account for the cost of fence installation, the ODOT requests that the vendor provide an itemized list of work and pricing. When installation is requested, the ODOT will utilize the necessary items and associated pricing listed to properly determine an overall cost of installation. The vendor will have the opportunity to review the project site prior to providing the itemized list of work and pricing.

Mobilization to a Project: When a vendor is selected for a project, the vendor will be paid for mobilization to the single project. Within a single project, ODOT may select up to four sites to include.

Mobilization within a Project: Since one project may consist of up to four sites, ODOT will compensate the awarded vendor a lump sum plus mileage for the second, third, and fourth sites, if applicable.

Compensation will be a lump sum of $150.00 for each additional site plus mileage.

One vehicle for equipment and one vehicle for material will be paid at a rate of $0.67 per mile. If one vehicle is used for both equipment and material, then the mileage compensation will only apply to that vehicle. Example: An equipment vehicle and material vehicle traveled 15 miles from site one to site two. The awarded vendor would receive $150.00 + (15 miles) x $.67 + (15 miles) x $.67 = $170.10

• For any project with a total length of 500 linear feet or less, ODOT may include up to four sites within a county.

• For any project with a total length greater than 500 linear feet and less than 1000 linear feet, ODOT may include up to two sites in a county.

• For any project with a total length of 1000 linear feet or more, ODOT may include only one site.

Since the ODOT is unaware of site or project lengths in advance of this bid, the ODOT has provided a number of pricing columns for each vendor to specify ranges for each item.

ODOT has determined the low-end range to be from 1 to 100 linear feet. This will be determined by the distance between the first and last post within a run of fence.

Due to the location of the work being done, typically at the R/W boundary, ODOT does not foresee any need for Maintenance of Traffic Control that would require a lane or shoulder closure. In the event Traffic Control is needed for such a closure, the vendor shall be responsible for setting up the work zone in accordance with the current version of the OUMTCD. Line items have been provided on the pricing page to address Construction Work Zone (no lane/shoulder closure, Lane Closure, and Shoulder Closure).

Removal of existing fence: In the event ODOT requests fencing to be replaced, and the existing fence must be removed, costs to remove components of the existing fence should be considered.

Section 5: Delivery Provisions

5.1a Delivery of Purchased Materials only:

Delivery of placed orders shall be made within ten (10) calendar days after receipt of written or verbal notification against a valid State of Ohio purchase order or State payment card.

5.1b Installation request of Purchased Materials:

When a vendor is requested for installation of purchased materials, installation shall begin within ten (10) calendar days from the date of the request, unless ODOT and the awarded vendor mutually agree upon another date.

5.1 Delivery Hours

All deliveries shall be made between the hours of 7:00 a.m. and 4:30 p.m., Monday through Friday, excluding State holidays, unless special permission is granted by the Department to temporarily waive or adjust this requirement.

5.2 Freight Charges for Materials.

Delivery transport vehicle may vary based on the type, size, weight, and need of the material orders placed. On the excel pricing page, a separate tab will establish the various delivery options a vendor may have. A vendor shall provide the various transport types they have for orders placed. This can range from a small pickup truck (or similar size) to a semi-truck. Based on the order placed, a vendor shall estimate the most efficient vehicle to meet the order requirement.

When a vendor chooses to combine orders to be more efficient and effective, this may result in a different transport type for an individual order. See Notes on pricing page for combining orders.

5.3 Delivery Location

A single delivery location has been established for each District. Costs for additional locations (drop fee) and additional mileage are established on the pricing page for delivery costs.