This is a Notice to Bidders and Special Provisions document issued by the California Department of Transportation (Caltrans) District 05 for a highway construction project in Santa Cruz County. The project, identified as Contract No. 05-1J9624, involves modifying existing drainage systems, replacing lighting systems, and installing a Traffic Management System (TMS) on State Highway Route 1, extending from 0.5 miles north of Larkin Valley Road Undercrossing to Laguna Road. Bids opened on Tuesday, November 17, 2026, with project plans approved on May 18, 2026. The contract is based on the Caltrans Standard Specifications and Plans dated 2025. The project encompasses multiple work locations with specific time constraints, including restrictions on work in culverts and drainage channels at designated locations between June 1 and October 31 only. Contractors must obtain authorization or acceptance of multiple submittals, including the CPM baseline schedule, Water Pollution Control Plan or Stormwater Pollution Prevention Plan, and notification of Disadvantaged Business Enterprise or Disabled Veteran Business Enterprise nominees before commencing job site activities within 55 days of contract approval.

The contract requires compliance with extensive environmental, safety, and regulatory requirements, including handling of unregulated earth material containing lead at multiple specified locations with concentrations up to 80 mg/kg total lead, management of fire hazards with mandatory fire prevention equipment and personnel, and environmental product declarations for hot mix asphalt and concrete materials from plants providing specified minimum quantities. Small Business Enterprise participation is required with goals outlined in sections 1-1.06, 1-1.07B, 2-1.23, 2-1.24, and 2-1.33B(3), and contractors must comply with certified payroll record submissions through LCPtracker Pro. The project includes funding from multiple agencies, specifically the City of San Jose and Valley Transportation Authority, as indicated by required C50B construction project funding identification signage. Performance failure withholding of $6,000 per missing environmental product declaration applies if declarations are not submitted within 30 days of initial material placement. The project establishes a completion year target of 2027 and requires adherence to stringent traffic control measures, including temporary barrier systems complying with MASH Test Level 3 specifications.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bids open Tuesday, November 17, 2026 Dated September 28, 2026

STATE OF CALIFORNIA

DEPARTMENT OF TRANSPORTATION

NOTICE TO BIDDERS

AND

SPECIAL PROVISIONS

FOR CONSTRUCTION ON STATE HIGHWAY IN SANTA CRUZ COUNTY FROM

0.5 MILE NORTH OF LARKIN VALLEY ROAD UNDERCROSSING TO LAGUNA

ROAD

In District 05 On Route 1

Under Bid book dated September 28, 2026 Standard Specifications dated 2025

Project plans approved May 18, 2026 Standard Plans dated 2025

Identified by Contract No. 05-1J9624

05-SCr-1-10.6/26.0 Project ID 0523000198

SPECIAL NOTICES

• See sections 2 and 3 for contractors' registration requirements.

• The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.

• See section 2 for submittal requirements for DVBE quotes and Non–Small Business

Subcontractor Preference.

See sections 1-1.06, 1-1.07B, 2-1.23, 2-1.24, 2-1.33B(3), 5-1.13D, and 5-1.13F for “Small

Business Enterprise Participation Goal Requirement” and “Small Business and Non-Small Business Subcontractor Preferences.”

• See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.

• For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).

• See section 6-1.08 for the requirements for environmental product declarations for hot mix asphalt and concrete materials and products.

• See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.

• The flagging and temporary traffic control requirements have been revised. See sections 7-

1.03, 7-1.04, and 12.

• See section 14-11.14 for changes to the management of treated wood waste.

Contract No. 05-1J9624 i

TABLE OF CONTENTS

NOTICE TO BIDDERS

BID ITEM LIST

SPECIAL PROVISIONS

ORGANIZATION

DIVISION I GENERAL PROVISIONS

1 GENERAL

2 BIDDING

5 CONTROL OF WORK

6 CONTROL OF MATERIALS

7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

8 PROSECUTION AND PROGRESS

9 PAYMENT

DIVISION II GENERAL CONSTRUCTION

10 GENERAL

12 TEMPORARY TRAFFIC CONTROL

13 WATER POLLUTION CONTROL

14 ENVIRONMENTAL STEWARDSHIP

15 EXISTING FACILITIES

DIVISION III EARTHWORK AND LANDSCAPE

17 GENERAL

19 EARTHWORK

20 LANDSCAPE

21 EROSION CONTROL

DIVISION V SURFACINGS AND PAVEMENTS

39 ASPHALT CONCRETE

49 PILING

55 STEEL STRUCTURES

DIVISION VII DRAINAGE FACILITIES

61 GENERAL

65 CONCRETE PIPE

71 EXISTING DRAINAGE FACILITIES

DIVISION VIII MISCELLANEOUS CONSTRUCTION

72 SLOPE PROTECTION

73 CONCRETE CURBS AND SIDEWALKS

DIVISION IX TRAFFIC CONTROL DEVICES

81 MISCELLANEOUS TRAFFIC CONTROL DEVICES

82 SIGNS AND MARKERS

ii

82-6 SIGN POST SUPPORT SYSTEM

83 RAILINGS AND BARRIERS

84 MARKINGS

DIVISION X ELECTRICAL WORK

86 GENERAL

87 ELECTRICAL SYSTEMS

iii

STANDARD PLANS LIST

The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.

RSP A3A Abbreviations (Sheet 1 of 3)

RSP A3B Abbreviations (Sheet 2 of 3)

RSP A3C Abbreviations (Sheet 3 of 3)

A10A Legend - Lines and Symbols (Sheet 1 of 5)

A10B Legend - Lines and Symbols (Sheet 2 of 5)

A10C Legend - Lines and Symbols (Sheet 3 of 5)

A10D Legend - Lines and Symbols (Sheet 4 of 5)

A10E Legend - Lines and Symbols (Sheet 5 of 5)

A62A Excavation and Backfill - Miscellaneous Details

A77L2 Midwest Guardrail System - Standard Railing Section (Steel Post with Notched Wood or Notched Recycled Plastic Block)

A77N2 Midwest Guardrail System - Steel Post and Block Details

A77N3 Midwest Guardrail System - Typical Line Post Embedment and Hinge Point Offset Details

A77N4 Midwest Guardrail System - Typical Height Measurement, Dike Positioning, and Delineation Details

A87A Curbs and Driveways

A87B Hot Mix Asphalt Dikes

P74 Pavement Edge Treatments

P76 Pavement Edge Treatments - New Construction

D71 Drainage Inlet Markers

D72B CIP Drainage Inlets - Types G1, G2, G3, G4, G5 and G6

D72C CIP Drainage Inlets - Types G1, G2, G3, G4, G5 and G6

D72E CIP Drainage Inlets - Types GO and GDO

D72F CIP Drainage Inlet Notes

D72G CIP Drainage Inlet Tables

D73B Precast Drainage Inlets - Types G1, G2, G3, G4, G5 and G6

D73C Precast Drainage Inlets - Types G1, G2, G3, G4, G5 and G6

D73E Precast Drainage Inlets - Types GO and GDO

D73F Precast Drainage Inlet Notes

D73G Precast Drainage Inlet Tables

D74 Drainage Inlet Details

D77A Grate Details No. 1 iv

D77B Grate Details No. 2

D87A Corrugated Metal Pipe Downdrain Details

D87C Cable Anchorage System

D90 Pipe Culvert Headwalls, Endwalls and Wingwalls - Types A, B and C

D94B Concrete Flared End Sections

H1 Landscape and Erosion Control Symbols

H2 Landscape Details

H6 Landscape Details

RSP H8 Landscape Details

H51 Erosion Control Details - Fiber Roll and Compost Sock

H52 Rolled Erosion Control Product

T1A Temporary Crash Cushion - Sand Filled (Unidirectional)

T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)

T1B Temporary Crash Cushion - Sand Filled (Bidirectional)

T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)

T3C Temporary Barrier System (Cross Bolt)

T3D Temporary Barrier System (Cross Bolt)

T3E Temporary Barrier System (Cross Bolt)

T3F Temporary Barrier System (Cal F-23)

T3F2 Temporary Barrier System (Cal F-23)

T3G Temporary Barrier System (Staking or Anchoring)

T3G2 Temporary Barrier System (Staking or Anchoring)

T9 Traffic Control System Tables for Lane and Ramp Closures

T10 Traffic Control System for Lane Closure on Freeways and Expressways

T10A Traffic Control System for Lane Closure on Freeways and Expressways

RSP T11 Traffic Control System for Lane Closure on Multilane Conventional Highways

RSP T13 Traffic Control System with Reversible Control on Two Lane Conventional Highways

RSP T13A Traffic Control System - Two Lane Conventional Highways

RSP T13B Traffic Control System - Two Lane Conventional Highways

RSP T13C Traffic Control System - Two Lane Conventional Highways

T14 Traffic Control System for Ramp Closure

T18 Traffic Control System - Construction Work Zone Speed Limit Reduction on Freeways and Expressways

T19 Traffic Control System - Construction Work Zone Speed Limit Reduction on Conventional Highways

T20 Traffic Control System - Construction Work Zone Speed Limit Reduction Details v

T22 Traffic Control System for Construction Work Zone Speed Limit Reduction on Two Lane Conventional Highways

T26 Temporary Automated End of Queue Warning System Type 1 (Queue <= 3.5 Miles)

T30 Temporary Pedestrian Access Routes - Typical Sidewalk Closure and Pedestrian Detour

T56 Temporary Water Pollution Control Details (Temporary Fiber Roll)

T59 Temporary Water Pollution Control Details (Temporary Concrete Washout Facility)

T61 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

T62 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

T63 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

T64 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

RS1 Roadside Signs - Typical Installation Details No. 1

RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2

RS4 Roadside Signs - Typical Installation Details No. 4

S89 Roadside Sign - Formed Single Sheet Aluminum Panel

S93 Framing Details for Framed Single Sheet Aluminum Signs, Rectangular Shape

S94 Roadside Framed Single Sheet Aluminum Signs, Rectangular Shape

S95 Roadside Single Sheet Aluminum Signs, Diamond Shape

ES-1A Electrical Systems (Legend)

ES-1B Electrical Systems (Legend)

ES-1C Electrical Systems (Legend)

ES-2A Electrical Systems (Service Equipment)

ES-2E Electrical Systems (Service Equipment Enclosure and Typical Wiring Diagram, Type III - B Series)

ES-3E Electrical Systems (Telephone Demarcation Cabinet, Type B)

ES-5A Electrical Systems (Loop Detectors)

ES-5B Electrical Systems (Detectors)

ES-5D Electrical Systems (Curb and Shoulder Termination, Trench, and Handhole Details)

ES-5E Electrical Systems (Trench in Pavement and Piezoelectric Axle Sensor Details)

ES-6A Electrical Systems (Lighting Standard, Types 15 and 21)

ES-6B Electrical Systems (Electrolier Anchorage and Grouting for Type 15 and Type 21, Barrier Rail Mounted)

ES-6E Electrical Systems (Lighting Standard, Types 30 and 31)

ES-6F Electrical Systems (Lighting Standard, Slip Base Plate)

ES-7M Electrical Systems (Signal and Lighting Standard, Details No. 1)

ES-7N Electrical Systems (Signal and Lighting Standard, Details No. 2)

RSP ES-7O Electrical Systems (Signal and Lighting Standard, Details No. 3)

ES-8A Electrical Systems (Non-Traffic Pull Box) vi

ES-8B Electrical Systems (Traffic Pull Box)

ES-11 Electrical Systems (Foundation Installations)

ES-13A Electrical Systems (Splice Insulation Methods Details)

ES-13B Electrical Systems (Kinking and Banding Detail)

CANCELED STANDARD PLANS LIST

The 2025 standard plan sheets listed below are canceled and not applicable to this contract.

Plan No. Date Canceled Plan No. Date

Canceled Plan No. Date Canceled

P8 04-20-26

NOTICE TO BIDDERS

Bids open Tuesday, November 17, 2026

Dated September 28, 2026

General work description: Modify existing drainage, replace lighting systems, and install TMS.

The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON

STATE HIGHWAY IN SANTA CRUZ COUNTY FROM 0.5 MILE NORTH OF LARKIN VALLEY ROAD

UNDERCROSSING TO LAGUNA ROAD.

District-County-Route-Post Mile: 05-SCr-1-10.6/26.0

Contract No. 05-1J9624

The Contractor must have either a Class A license or any combination of the following Class C licenses which constitutes a majority of the work: C-8, C-42, C-12.

The Department establishes no DVBE Contract goal but encourages bidders to obtain DVBE participation.

The SBE Contract goal is 5 percent.

Bids must be on a unit price basis.

Complete the work within 300 working days.

The estimated cost of the project is $6,800,000.

The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.

The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.

For bid results go to:

https://ppmoe.dot.ca.gov/cc

Select Electronic Bidding under the Bidding tab.

District office addresses are provided in the Standard Specifications.

Present bidders' inquiries to the Department and view the Department's responses at:

https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries

Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.

Submit your bid with bidder's security equal to at least 10 percent of the bid.

Under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq., the Department gives preference to certified small businesses and non–small businesses who commit to 25 percent certified small business participation.

Under Pub Cont Code § 6107, the Department gives preference to a “California company,” as defined, for bid comparison purposes over a nonresident contractor from any state that gives or requires a preference to be given to contractors from that state on its public entity construction contracts.

Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.

The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.

Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.

Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.

Department of Transportation

BID ITEM LIST

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM

0002 080060 LEVEL 2 CRITICAL PATH METHOD SCHEDULE LS LUMP SUM

0003 090100 TIME-RELATED OVERHEAD (WDAY) WDAY 300

0004 090200 DISPUTE RESOLUTION ADVISOR ON-SITE

MEETING

EA 7

0005 090207 HOURLY OFF-SITE DISPUTE-RESOLUTION-

ADVISOR-RELATED TASKS

HR 10

0006 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM

0007 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM

0008 120103 STATIONARY IMPACT ATTENUATOR VEHICLE DAY 102

0009 120149 TEMPORARY PAVEMENT MARKING (PAINT) SQFT 40

0010 120159 TEMPORARY TRAFFIC STRIPE (PAINT) LF 3,060

0011 120165 CHANNELIZER (SURFACE MOUNTED) EA 480

0012 120207 PORTABLE RADAR SPEED FEEDBACK SIGN

SYSTEM

DAY 220

0013 120300 TEMPORARY PAVEMENT MARKER EA 66

0014 120320 TEMPORARY BARRIER SYSTEM LF 5,150

0015 128651 PORTABLE CHANGEABLE MESSAGE SIGN (EA) EA 29

0016 128652 PORTABLE CHANGEABLE MESSAGE SIGN (LS) LS LUMP SUM

0017 129108 TEMPORARY CRASH CUSHION TL-3 EA 17

0018 129152 TEMPORARY RADAR SPEED FEEDBACK SIGN

SYSTEM

EA 2

0019 129161 AUTOMATED FLAGGER ASSISTANCE DEVICE

DAY

EA 282

0020 130100 JOB SITE MANAGEMENT LS LUMP SUM

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0021 130201 WATER POLLUTION CONTROL PROGRAM LS LUMP SUM

0022 130505 MOVE-IN/MOVE-OUT (TEMPORARY EROSION

CONTROL)

EA 2

0023 130530 TEMPORARY HYDRAULIC MULCH (BONDED

FIBER MATRIX)

SQYD 5,000

0024 130620 TEMPORARY DRAINAGE INLET PROTECTION EA 30

0025 130640 TEMPORARY FIBER ROLL LF 1,000

0026 130660 TEMPORARY LARGE SEDIMENT BARRIER LF 100

0027 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM

0028 141120 TREATED WOOD WASTE LB 2,270

0029 013893 (F) - BIOLOGICAL MITIGATION (ON-SITE) LS LUMP SUM

0030 160110 TEMPORARY HIGH-VISIBILITY FENCE LF 320

0031 170103 CLEARING AND GRUBBING (LS) LS LUMP SUM

0032 190101 ROADWAY EXCAVATION CY 97

0033 190105 ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY

DEPOSITED LEAD)

CY 651

0034 190159 ROADWAY EXCAVATION (TYPE COM) (AERIALLY

DEPOSITED LEAD)

CY 320

0035 192502 SAND BEDDING CY 1

0036 193006 (F) - STRUCTURE BACKFILL (SLURRY CEMENT) CY 130

0037 200002 ROADSIDE CLEARING LS LUMP SUM

0038 204008 PLANT (GROUP H) EA 50

0039 204099 PLANT ESTABLISHMENT WORK LS LUMP SUM

0040 206300 TEMPORARY IRRIGATION SYSTEM LS LUMP SUM

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0041 206400 CHECK AND TEST EXISTING IRRIGATION

FACILITIES

LS LUMP SUM

0042 210010 MOVE-IN/MOVE-OUT (EROSION CONTROL) EA 3

0043 210270 ROLLED EROSION CONTROL PRODUCT

(NETTING)

SQFT 840

0044 210350 FIBER ROLLS LF 230

0045 210430 HYDROSEED SQFT 12,600

0046 210610 COMPOST (CY) CY 78

0047 260203 CLASS 2 AGGREGATE BASE (CY) CY 240

0048 390095 REPLACE ASPHALT CONCRETE SURFACING CY 120

0049 390132 HOT MIX ASPHALT (TYPE A) TON 261

0050 394076 PLACE HOT MIX ASPHALT DIKE (TYPE E) LF 1,670

0051 398000 REMOVE ASPHALT CONCRETE PAVEMENT (CY) CY 50

0052 398100 REMOVE ASPHALT CONCRETE DIKE LF 1,460

0053 418006 REMOVE CONCRETE PAVEMENT (CY) CY 120

0054 510092 (F) - STRUCTURAL CONCRETE, HEADWALL CY 17

0055 510094 (F) - STRUCTURAL CONCRETE, DRAINAGE

INLET

CY 25

0056 015420 (F) - CONCRETE COLLAR EA 5

0057 039555 STRESS REDUCING SLAB CY 14

0058 650014 18" REINFORCED CONCRETE PIPE LF 310

0059 650018 24" REINFORCED CONCRETE PIPE LF 540

0060 650022 30" REINFORCED CONCRETE PIPE LF 160

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0061 014906 30" REINFORCED CONCRETE PIPE

TRENCHLESS INSTALLATION METHOD

LF 91

0062 665016 18" CORRUGATED STEEL PIPE (.064" THICK) LF 22

0063 665025 24" CORRUGATED STEEL PIPE (.138" THICK) LF 110

0064 692209 24" DOWNDRAIN SLIP JOINT EA 1

0065 692309 24" ANCHOR ASSEMBLY EA 2

0066 700617 DRAINAGE INLET MARKER EA 12

0067 705208 30" CONCRETE FLARED END SECTION EA 1

0068 710102 ABANDON CULVERT (LF) LF 145

0069 710124 REMOVE GUTTER DRAIN CY 1

0070 710132 REMOVE CULVERT (LF) LF 1,050

0071 710150 REMOVE INLET EA 9

0072 710152 REMOVE HEADWALL EA 3

0073 710165 REMOVE CONCRETE FLARED END SECTION

(EA)

EA 1

0074 710260 REMOVE CONCRETE (CHANNEL) CY 7

0075 710262 CAP INLET EA 1

0076 710360 CLEANING, INSPECTING, AND PREPARING

CULVERT (LF)

LF 1,660

0077 710368 CULVERT SLURRY-CEMENT BACKFILL CY 4

0078 710380 18" CURED-IN-PLACE PIPELINER LF 330

0079 710384 24" CURED-IN-PLACE PIPELINER LF 120

0080 013729 GRAVEL FILTER CY 1

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0081 723080 ROCK SLOPE PROTECTION (60 LB, CLASS II,

METHOD B) (CY)

CY 2

0082 014305 FILTER FABRIC SQYD 6

0083 730020 MINOR CONCRETE (CURB) (CY) CY 31

0084 731508 MINOR CONCRETE (EXPOSED AGGREGATE

CONCRETE)

SQFT 6,900

0085 731519 MINOR CONCRETE (STAMPED CONCRETE) SQFT 25,100

0086 731710 REMOVE CONCRETE CURB (LF) LF 980

0087 731840 REMOVE CONCRETE (CURB AND GUTTER) LF 130

0088 750001 (F) - MISCELLANEOUS IRON AND STEEL LB 12,053

0089 810120 REMOVE PAVEMENT MARKER EA 66

0090 810170 DELINEATOR (CLASS 1) EA 84

0091 810230 PAVEMENT MARKER (RETROREFLECTIVE) EA 84

0092 820130 OBJECT MARKER EA 21

0093 820250 REMOVE ROADSIDE SIGN EA 20

0094 037843 (F) - REMOVE POST SLEEVE EA 15

0095 820750 FURNISH SINGLE SHEET ALUMINUM SIGN

(0.063"-UNFRAMED)

SQFT 36

0096 820760 FURNISH SINGLE SHEET ALUMINUM SIGN

(0.080"-UNFRAMED)

SQFT 350

0097 820780 FURNISH SINGLE SHEET ALUMINUM SIGN

(0.063"-FRAMED)

SQFT 59

0098 820840 ROADSIDE SIGN - ONE POST EA 15

0099 037844 (F) - POST SLEEVE EA 17

0100 820850 ROADSIDE SIGN - TWO POST EA 2

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0101 832006 MIDWEST GUARDRAIL SYSTEM (STEEL POST) LF 140

0102 839752 REMOVE GUARDRAIL LF 140

0103 839763 RECONSTRUCT THRIE BEAM BARRIER LF 12.5

0104 840516 THERMOPLASTIC PAVEMENT MARKING

(ENHANCED WET NIGHT VISIBILITY)

SQFT 1,460

0105 840623 6" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY) (BROKEN

36-12)

LF 80

0106 846007 6" THERMOPLASTIC TRAFFIC STRIPE

(ENHANCED WET NIGHT VISIBILITY)

LF 3,360

0107 846030 REMOVE THERMOPLASTIC TRAFFIC STRIPE LF 3,000

0108 846035 REMOVE THERMOPLASTIC PAVEMENT

MARKING

SQFT 40

0109 870009 MAINTAINING EXISTING TRAFFIC MANAGEMENT

SYSTEM ELEMENTS DURING CONSTRUCTION

LS LUMP SUM

0110 870600 TRAFFIC MONITORING STATION SYSTEM LS LUMP SUM

0111 872131 MODIFYING LIGHTING SYSTEMS LS LUMP SUM

0112 999990 MOBILIZATION LS LUMP SUM

SPECIAL PROVISIONS

ORGANIZATION

Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.

Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.

Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.

DIVISION I GENERAL PROVISIONS

1 GENERAL

Add to section 1-1.01:

Bid Items and Applicable Sections Item code

Item description Applicable section

090200 DISPUTE RESOLUTION ADVISOR ON-SITE MEETING 5

090207 HOURLY OFF-SITE DISPUTE-RESOLUTION-ADVISOR-RELATED

TASKS

014305 BIOLOGICAL MITIGATION (ON-SITE) 14

015420 CONCRETE COLLAR 61

039555 STRESS REDUCING SLAB 61

014906

30" REINFORCED CONCRETE PIPE TRENCHLESS NSTALLATION

METHOD 65

013729 GRAVEL FILTER 72

014305 FILTER FABRIC 72

037843 REMOVE POST SLEEVE 82

037844 POST SLEEVE 82

Add to the table in the 1st paragraph of section 1-1.06:

SBE Small Business Enterprise

Add to section 1-1.07B:

small business enterprise: Small business or small business for the purpose of public works, as certified by the Department of General Services, Office of Small Business and DVBE Services, and as defined in Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq.

2 BIDDING

Add between the 1st and 2nd paragraphs of section 2-1.06B:

The Department makes the following supplemental project information available:

Supplemental Project Information Means Description

Included in the Information Handout 1. U.S. Fish and Wildlife Service Programmatic Biological Opinion for Projects Funded or Approved under the Federal Highway Administration’s Federal Aid Program (8-8-10-F-58) for California red-legged frog

2. U.S. Fish and Wildlife Service Programmatic Biological Opinion on the Santa Cruz Roadside Safety Project, Santa Cruz County, California, dated October 03, 2022

3. Coastal Development Permit

4. US Fish and Wildlife 1602 Permit

5. 404 Permit

6. Central Regional Water Quality Control Board, Central Coast, Clean Water Act Section 401 Water Quality Certification No 34425WQ10, dated April 21,

7. Railroad Right of Entry

8. Geotechnical Design Report for SR-1 Drainage and Erosion Control Improvements, dated February 25,

9. Department of Industrial Relations Division of Occupational Safety and Health Mining and Tunneling Unit, dated

10. 1J9624 Staging Areas with Coastal Access

11. List of Existing TMS Elements

Available as specified in the Standard Specifications

Original ground in DWG Alignment in XML

Replace section 2-1.23 with:

2-1.23 SMALL BUSINESS ENTERPRISE PARTICIPATION GOAL REQUIREMENT

2-1.23A General Section 2-1.23 applies if an SBE participation goal requirement is shown on the Notice to Bidders.

The SBE participation goal requirement is in addition to any DVBE goal shown on the Notice to Bidders and the DVBE requirements in section 2-1.22.

Make work available to SBEs and select work parts consistent with the available SBEs, including subcontractors, suppliers, service providers, and truckers.

Meet the SBE participation goal requirement shown on the Notice to Bidders. A bid that demonstrates an SBE participation commitment less than the SBE participation goal requirement is nonresponsive.

Each listed SBE must be certified as a small business or small business for the purpose of public works by 5:00 p.m. on the bid opening date. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.

The Department of General Services determines whether an SBE was certified on the bid opening date.

The Department of Transportation confirms an SBE’s certification status.

2-1.23B SBE Submittals Submit SBE information under section 2-1.33.

For the SBE participation goal requirement, submit the following:

1. Completed Small Business Enterprise – Commitment form. Failure to submit the completed form by 4 p.m. on the 4th business day after bid opening may result in a nonresponsive bid.

2. Copy of the quote for each SBE shown on the Small Business Enterprise – Commitment form that describes the type and dollar amount of work shown on the form. Quotes are not required for work that will be completed by SBE prime bidders. Failure to submit a copy of the quote for each SBE listed on the Commitment form by 4 p.m. on the 4th business day after bid opening may result in disallowance of the SBE’s participation.

3. Completed Small Business Enterprise – Confirmation form from each SBE listed on the Commitment form. The form for each SBE is required to establish that the SBE will be participating in the Contract for the type and dollar amount of work shown on the form. Failure to submit completed Confirmation forms for each SBE listed on the Commitment form by 4 p.m. on the 4th business day after bid opening may result in disallowance of the SBE’s participation.

4. If an SBE is participating as a joint venture partner, submit a copy of the joint venture agreement.

The Department may contact you and SBEs to clarify quotes and supporting documentation.

If you elect, at time of bid, to pursue the optional small business or non-small business preference, see section 2-1.24 for the requirements arising from your request for the preference. SBE participation listed to meet the SBE participation goal requirement should not be listed for the preference.

Replace section 2-1.24 with:

2-1.24 SMALL BUSINESS AND NON–SMALL BUSINESS SUBCONTRACTOR PREFERENCES

2-1.24A General Section 2-1.24 applies to a non-federal-aid contract.

The Department applies small business preferences and non–small business preferences under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq.

Any contractor, subcontractor, supplier, or service provider who qualifies as a small business or small business for the purpose of public works is encouraged to apply for certification as an SBE by submitting its application to the Department of General Services, Office of Small Business and DVBE Services.

The Department of General Services determines whether an SBE was certified on the bid opening date.

The Department of Transportation confirms an SBE’s certification status before applying the small business or non-small business preference.

Contract award is based on the total bid, not the reduced bid.

Pursuant to Govt Code § 14838, SBE participation listed on the Small Business Enterprise – Commitment form used to meet the SBE participation goal requirement should not be listed on the Certified Small Business Listing for the Non-Small Business Preference form. Listing the same SBE participation on both the Small Business Enterprise – Commitment form and on the Certified Small Business Listing for the Non-Small Business Preference form may result in disallowance of the SBE’s participation toward the small business or non-small business preference.

2-1.24B Small Business Preference The Department allows a bidder certified as an SBE by the Department of General Services, Office of Small Business and DVBE Services, a preference if:

1. Bidder submitted a completed Request for Small Business Preference or Non–Small Business Preference form with its bid

2. Low bidder did not request the preference or is not certified as a small business

The Bidder's signature on the Request for Small Business Preference or Non–Small Business Preference form certifies that the Bidder is certified as an SBE at the date and time of bid or has submitted a complete application to the Department of General Services. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.

The small business preference is a reduction for bid comparison in the total bid submitted by the small business contractor by the lesser of the following amounts:

1. 5 percent of the verified total bid of the low bidder

2. $50,000

If the Department determines that a certified small business bidder is the low bidder after the application of the small business preference, the Department does not consider a request for non–small business preference.

2-1.24C Non–Small Business Subcontractor Preference At time of bid, the Department allows a bidder not certified as an SBE by the Department of General Services, Office of Small Business and DVBE Services, the option of requesting the non-small business subcontractor preference. If a bidder elects to pursue that option at the time of bid, the bidder is required to meet the corresponding commitment.

For the non-small business subcontractor preference, submit the following:

1. Completed Request for Small Business Preference or Non–Small Business Preference form with your bid

2. Completed Certified Small Business Listing for the Non–Small Business Preference form which shows you are subcontracting at least 25 percent to certified SBEs

Each listed SBE must be certified as a small business or small business for the purpose of public works by 5:00 p.m. on the bid opening date. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.

Failure to submit a completed Certified Small Business Listing for the Non–Small Business Preference form by 4 p.m. on the 4th business day after bid opening will result in a nonresponsive bid.

The non–small business subcontractor preference is a reduction for bid comparison in the total bid submitted by the non–small business contractor requesting the preference by the lesser of the following amounts:

1. 5 percent of the verified total bid of the low bidder

2. $50,000

Replace the table in the 1st paragraph of section 2-1.33B(3)(b)(ii) with:

Bid Form Submittal Schedule for a Non-Federal-Aid Contract with a DVBE Goal

Form Submittal deadline

Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract

For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number

10 days after bid opening

Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa Time of bid

Certified DVBE Summary No later than 4 p.m. on the 4th business day after bid opening

California Company Preference Time of bid

Small Business Enterprise – Commitment No later than 4 p.m. on the 4th business day after bid opening

Small Business Enterprise – Confirmation No later than 4 p.m. on the 4th business day after bid opening

Request for Small Business Preference or Non– Small Business Preferencea Time of bid

Certified Small Business Listing for the Non– Small Business Preferencea

No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.

Replace the table in the 1st paragraph of section 2-1.33B(3)(c)(ii) with:

Bid Form Submittal Schedule for a Non-Federal-Aid Contract without a DVBE Goal

Form Submittal deadline

Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract

For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number

10 days after bid opening

Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa Time of bid

California Company Preference Time of bid

Certified DVBE Summaryb No later than 4 p.m. on the 4th business day after bid opening

Small Business Enterprise – Commitment No later than 4 p.m. on the 4th business day after bid opening

Small Business Enterprise – Confirmation No later than 4 p.m. on the 4th business day after bid opening

Request for Small Business Preference or Non– Small Business Preferencea Time of bid

Certified Small Business Listing for the Non– Small Business Preferencea

No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.

bSubmit only if you obtain DVBE participation or you are the apparent low bidder, 2nd low bidder, or 3rd low bidder and you choose to receive the specified incentive.

5 CONTROL OF WORK

Replace section 5-1.13D with:

5-1.13D Non-Small Business Preference 5-1.13D(1) General Section 5-1.13D applies to a non-federal-aid contract when you have obtained a non-small business subcontractor preference under section 2-1.24.

Use each SBE as shown on the Certified Small Business Listing for the Non-Small Business Preference form unless you receive authorization for a substitution under section 5-1.13D(3).

Maintain records of subcontracts and agreements made with each SBE. Include in the records:

1. SBE subcontract or agreement

2. Name and business address of each business

3. Proof of each payment made to an SBE

Upon reasonable notice and during normal business hours, permit access to the SBE premises for the purpose of:

1. Interviewing employees.

2. Inspecting and copying books, records, accounts, and other material that may be relevant to a matter under investigation.

Upon work completion, complete a Final Report – Utilization of Small Business Enterprise form and submit within 10 days of Contract acceptance. The Department withholds the greater of 10 percent of the SBE work amount or $10,000 until the form is submitted. The Department releases the withhold upon submission of the completed form. If additional payments are made to an SBE after submittal of the completed form, submit an updated form to reflect such payments.

5-1.13D(2) Commercially Useful Function SBEs must perform a commercially useful function under 2 CA Code Regs § 1896.15 when performing tasks listed on the Certified Small Business Listing for the Non-Small Business Preference form and as a Department authorized substitute SBE. The SBE’s value of work will only count toward the non-small business preference if the SBE performs a commercially useful function under 2 CA Code Regs § 1896.15.

Provide written notification to the Engineer at least 15 days in advance of each SBE’s initial performance of work on the Contract. Include the SBE’s name, contract work to be performed, and the location, date, and time of where the SBE’s work will take place.

Monitor each SBE’s performance of a commercially useful function throughout their duration of work on the Contract. Maintain supporting documentation of commercially useful function related records. Provide copies of the following to the Department within 5 business days of a specific SBE request:

1. Subcontract or agreement with the SBE

2. Purchase orders

3. Bills of lading

4. Invoices

5. Proof of payment

You and your SBEs must submit any commercially useful function related records and documents within 5 business days of Department request such as:

1. Proof of ownership or lease and rental agreements for equipment

2. Tax records

3. Employee rosters

4. Certified payroll records

5. Inventory rosters

Notify the Engineer immediately if you believe an SBE may not be performing a commercially useful function.

Failure to submit requested records and documents, or failure of an SBE to perform a commercially useful function, will be a violation of these specifications. Such violations will result in referral to the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.

5-1.13D(3) Substitutions Substitution of an SBE may be requested for the reasons listed in Pub Cont Code § 4107. The Department will consider your SBE substitution request under 2 CA Code Regs § 1896.10. The substitute must be another SBE.

The requirement that an SBE be certified by the bid opening date does not apply to SBE substitutions after contract award.

Include in your substitution request:

1. Copy of the written notice issued to the SBE with proof of delivery

2. Copy of the SBE response to the notice

3. Your explanation of the reason for the substitution request

4. Names and certification numbers of the listed SBE and the proposed substitute SBE

5. Description of the work to be performed including dollar amount or percentage of overall contract the proposed substitute SBE will perform

6. If an SBE substitution cannot occur, written justification and the steps that were taken to try to acquire a new SBE and how that non-small business preference portion of the Contract will be fulfilled

Upon receipt of the substitution request, the listed SBE will be notified by the Department of the substitution request. The listed SBE will have 5 business days to respond. Where the listed SBE objects to the substitution, the Department will schedule a hearing.

If the Department authorizes your SBE substitution request, it will do so in writing.

Work performed by a firm other than the listed SBE or authorized substitute will be a violation of these specifications. Such violations will result in notification of the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.

Replace section 5-1.13E with:

5-1.13E Prompt Payment Section 5-1.13E applies to all contracts.

Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.

Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:

1. Subcontractor’s or entity’s business name

2. Description of work performed

2.1. Bid item numbers or change order numbers

2.2. Written narrative of work performed

3. Value of work performed

4. Amount paid to subcontractor or entity

5. Withhold amount, if applicable

6. Explanation of withhold reasoning, if applicable

Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.

If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:

1. Value of the disputed work

2. Amount of the withhold being taken

3. Bid item numbers or change order numbers associated with the disputed work

4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated

5. Corrective actions to be taken for release of withheld amount

The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.

The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:

1. Withhold was not applied in good faith

2. Requested additional withhold documentation records were not provided

3. Payment information was not submitted through the prompt payment monitoring system

4. Required withhold notification was not provided

The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.

Replace section 5-1.13F with:

5-1.13F Small Business Enterprise Participation Goal Requirement 5-1.13F(1) General Section 5-1.13F applies to a non-federal-aid contract if an SBE participation goal requirement is shown on the Notice to Bidders.

Use each SBE as shown on the Small Business Enterprise – Commitment form unless you receive authorization for a substitution under section 5-1.13F(3).

Maintain records of subcontracts and agreements made with each SBE. Include in the records:

1. SBE subcontract or agreement

2. Name and business address of each business

3. Proof of each payment made to an SBE

Upon reasonable notice and during normal business hours, permit access to the SBE premises for the purpose of:

1. Interviewing employees.

2. Inspecting and copying books, records, accounts, and other material that may be relevant to a matter under investigation.

Upon work completion, complete a Final Report – Utilization of Small Business Enterprise form and submit within 10 days of Contract acceptance. The Department withholds the greater of 10 percent of the SBE work amount or $10,000 until the form is submitted. The Department releases the withhold upon submission of the completed form. If additional payments are made to an SBE after submittal of the completed form, submit an updated form to reflect such payments.

5-1.13F(2) Commercially Useful Function SBEs must perform a commercially useful function under 2 CA Code Regs § 1896.15 when performing tasks listed on the Small Business Enterprise – Commitment form and as a Department authorized substitute SBE. The SBE’s value of work will only count toward the SBE participation goal requirement if the SBE performs a commercially useful function under 2 CA Code Regs § 1896.15.

Provide written notification to the Engineer at least 15 days in advance of each SBE’s initial performance of work on the Contract. Include the SBE’s name, contract work to be performed, and the location, date, and time of where the SBE’s work will take place.

Monitor each SBE’s performance of a commercially useful function throughout their duration of work on the Contract. Maintain supporting documentation of commercially useful function related records. Provide copies of the following to the Department within 5 business days of a specific SBE request:

1. Subcontract or agreement with the SBE

2. Purchase orders

3. Bills of lading

4. Invoices

5. Proof of payment

You and your SBEs must submit any commercially useful function related records and documents within 5 business days of Department request such as:

1. Proof of ownership or lease and rental agreements for equipment

2. Tax records

3. Employee rosters

4. Certified payroll records

5. Inventory rosters

Notify the Engineer immediately if you believe an SBE may not be performing a commercially useful function.

Failure to submit requested records and documents, or failure of an SBE to perform a commercially useful function, will be a violation of these specifications. Such violations will result in referral to the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.

5-1.13F(3) Substitutions Substitution of an SBE may be requested for the reasons listed in Pub Cont Code § 4107. The Department will consider your SBE substitution request under 2 CA Code Regs § 1896.10. The substitute must be another SBE.

The requirement that an SBE be certified by the bid opening date does not apply to SBE substitutions after contract award.

Include in your substitution request:

1. Copy of the written notice issued to the SBE with proof of delivery

2. Copy of the SBE response to the notice

3. Your explanation of the reason for the substitution request

4. Names and certification numbers of the listed SBE and the proposed substitute SBE

5. Description of the work to be performed including dollar amount or percentage of overall contract the proposed substitute SBE will perform

6. If an SBE substitution cannot occur, written justification and the steps that were taken to try to acquire a new SBE and how that SBE participation goal requirement portion of the Contract will be fulfilled

Upon receipt of the substitution request, the listed SBE will be notified by the Department of the substitution request. The listed SBE will have 5 business days to respond. Where the listed SBE objects to the substitution, the Department will schedule a hearing.

If the Department authorizes your SBE substitution request, it will do so in writing.

Work performed by a firm other than the listed SBE or authorized substitute will be a violation of these specifications. Such violations will result in notification of the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.

Replace section 5-1.15 with:

5-1.15 SAFETY REPRESENTATIVE

5-1.15A General Designate an on-site safety representative to superintend project safety for the duration of this Contract.

The safety representative may perform other non-safety related work if safety responsibilities are fulfilled.

The safety representative must be available after work hours as needed. The safety representative is not required to be on-site during plant establishment period, erosion control establishment period, or temporary suspensions when no other Contract work is being performed.

Develop a written site-specific safety program (SSSP) that incorporates known hazards associated with the project.

5-1.15B Submittals Submit a resume of the safety representative before starting work on the project, including education, completed safety training, and safety experience in heavy construction, heavy industrial, or oil and energy industry.

Submit a copy of the safety representative's certificate for the Cal/OSHA 30-hour – Cal/OSHA Standards for the Construction Industry or OSHA 510 - OSHA Standards for the Construction Industry training course as an informational submittal. The certificate must include:

1. Name of the entity providing certification

2. Name of the individual receiving certification

3. Date when the certification was provided

4. Expiration date, if applicable

Submit a copy of the SSSP as an informational submittal:

1. At least 15 days before starting work

2. At least 48 hours before starting work whenever a revision is made to the SSSP

5-1.15C Certifications The safety representative must have completed training and received a certificate of completion for the Cal/OSHA 30-hour - Cal/OSHA Standards for the Construction Industry or OSHA 510 – OSHA Standards for the Construction Industry training course.

The safety representative must have one of the following certifications:

1. Certified Safety Professional from the Board of Certified Safety Professionals

2. Construction Health and Safety Technician from the Board of Certified Safety Professionals

3. Occupational Hygiene and Safety Technician from the Board of Certified Safety Professionals

4. Safety Trained Supervisor from the Board of Certified Safety Professionals

5. Safety Trained Supervisor Construction from the Board of Certified Safety Professionals

6. Associate Safety Professional from the Board of Certified Safety Professionals

7. Master Safety Professional from the National Association of Safety Professionals

8. Certified Safety Director from the National Association of Safety Professionals

5-1.15D Qualifications The safety representative must be a competent and qualified person, as defined by Cal/OSHA, and must provide safety oversight on the project. The safety representative must have:

1. At least 3 years of safety experience in heavy construction, heavy industrial, or oil and energy industry

2. Knowledge in the area of safety procedure for all types of work being performed on this project

3. Knowledge of Department specifications and plans, Cal/OSHA policy and procedures, and 8 CA

Code of Regs safety requirements

The safety representative must have completed safety training and maintain valid certifications for:

1. First aid

2. Cardiopulmonary resuscitation

5-1.15E Duties and Responsibilities The safety representative must be available by:

1. Cellular telephone

2. Two-way radio

3. Mobile internet access

The safety representative must:

1. Develop the SSSP

2. Conduct the on-site new project orientation for each worker assigned to the project

3. Review the construction work plans for each subcontractor before starting work

4. Conduct or attend pre-planning sessions for high hazard work such as excavations, demolition, confined space entry, falsework, crane hoisting, high-risk utilities such as high-pressure pipelines with fuel or natural gas, and tunneling or boring

5. Conduct weekly job site safety meetings

6. Review work schedules, including subcontractors' work schedules, to ensure adequacy of job hazard analyses and address all safety concerns and issues

7. Ensure safety data sheets are available on-site for all materials and have a hazard communication program for informing workers of material hazards

8. Verify compliance with hazardous waste requirements under section 14-11, including spill prevention and control measures

9. Conduct daily safety inspections of the job site for hazards and compliance with safety requirements in the specifications and 8 CA Code of Regs

10. Report all incidents to the Engineer immediately, including the investigation of any close calls

When monitoring the job site, including work zones with certified flaggers or traffic control technicians, take immediate corrective action and notify the Engineer if an imminent danger is identified.

If the Engineer determines the safety representative is not meeting the intended duties and responsibilities, you must replace the safety representative within 30 days of written notice from the Engineer. If you need to replace the safety representative, notify the Engineer and provide replacement safety representative resume and required certifications at least 15 days before the replacement.

You may submit a secondary safety representative to act on behalf of the designated safety representative during extended shifts, continuous operations, or short-term absences that will not exceed 14 days in duration. The secondary safety representative must meet the same required qualifications and certifications as the designated safety representative.

Add to the end of section 5-1.20A:

During the progress of the work under this Contract, work under the following contracts may be in progress at or near the job site of this Contract:

Coincident or Adjacent Contracts

Contract no. County–Route–Post Mile Location Type of work 05-0C734 SCr-001-8.1/10.7 In Santa Cruz County in and near Aptos from Freedom Blvd to State Park Dr

Auxiliary lane widening, retaining wall/sound wall, railroad bridge construction

05-0C733 SCr-001-10.4/13.3 Near Capitola and Aptos, SR 1 from State Park Drive to Bay/Porter Interchanges

Construct Auxiliary lanes between interchanges. Include reconstruction of the Capitola Ave.

overcrossing to accommodate new lanes on SR 1.

05-1R450 SCr-017-0.15/0.55 In Santa Cruz County in Pasatiempo on SR

SR17

Install non-rubberized open grade friction coarse

05-1Q250 SCr-001-17.46/17.66 In Santa Cruz County on State Route 1 and State Route 9 Junction

Construct continuous lightings on highway segment

05-1M110 SCr-001-17.5/20.2 In Santa Cruz County in and near Santa Cruz from 0.1 Miles south of the junction of Route 1 and Route 9 to 0.1 Miles North of the Western Drive Intersection

Pave 8.293 LM of Class 2 pavement.

Other work will include replacement of 87 ADA ramps and Sign Panel Replacement as needed.

05-1S850 SCr-001-26.764/26.764 Highway 1 in Santa Cruz County near Yellow Bank, just south of Davenport

Provide dedicated bicycle and pedestrian access over Hwy 1

05-1N610 SCr-001-26.45-28.78 On State Route 1 near Davenport 0.6 miles south of Laguna Road and at Ocean Street

Parking Lot, Turnpocket, Driveway and Crosswalk

Coordinate lane closures and traffic handling with the Engineer and with contractors of coincident or adjacent projects. Potential conflicts may not be limited to the contracts listed above.

Add to the end of section 5-1.20B(3):

Portions of this project are located within the jurisdiction of the City of Santa Cruz…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .