03 - Attachment 3 - Data Requirements List.pdf

PDF 137 KB Posted

Attached to
JPSS-2 Payload Processing Service Federal contract opportunity
Solicitation number
80KSC021R0037
Issued by
National Aeronautics and Space Administration Kennedy Space Center

About this file

This document contains an attachment to a solicitation for Joint Polar Satellite System-2 payload processing services. The attachment lists nine data requirement items due at various stages of the contract for which NASA requires insight or approval. These include facility documentation, safety manuals, transportation plans, orientation materials, and mishap reporting procedures. The solicitation seeks processing facilities and services for the JPSS-2 spacecraft to be launched on an Atlas V from the National Aeronautics and Space Administration Kennedy Space Center. Responses are due through the provided Box link by the dates specified. The work involves handling the spacecraft through processing and integration for launch.

View the file

Other files for this federal contract opportunity

Other files attached to JPSS-2 Payload Processing Service, newest first.
File Type Posted
JPSS-2 - RFP Questions and Responses 6.15.21.docx DOCX document
05 - Attachment 5 - Definitions.pdf PDF
01 - Attachment 1 - JPSS-2 Statement of Work.pdf PDF
04 - Attachment 4 - Acronyms and Abbreviations.pdf PDF
00 - SF 1449.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 3

DATA REQUIREMENTS LIST

Launch Services Program

Joint Polar Satellite System (JPSS) - 2

Payload Processing for the

National Aeronautics and Space Administration

JPSS-2 Payload Processing Attachment 3 - DRL 80KSC021R0037

1.0 Data Requirements List

The Data Requirements List (DRL) described in SOW 3.2.2 identifies critical elements of the contracted effort where aspects of payload processing insight are required by NASA and where NASA approval is required. The following DRL defines the scope of documentation required; however, NASA will utilize the Contractor’s existing documentation to the extent practicable if it meets compliance requirements. The submittal dates specified represent due dates to the Contracting Officer (CO). DRL approval may be assumed unless the Contractor is notified by NASA of disapproval within thirty (30) days, or as otherwise identified.

All DRLs shall be submitted electronically to the respective points of contact. All data requirements shall be delivered to the CO, with an informational copy to the Contracting Officer’s Representative (COR) and Launch Site Integration Manager (LSIM). The Contractor shall notify the CO in writing of DRL delivery.

DRL

Item Document Submittal Date Insight (I)

Approval (A) Subsequent Submittal/

Changes

1 Facility Manifest 10 Business Days After Contract Award I As Required

2 Facility Handbook 10 Business Days After Contract Award I As Required

3 Facility Safety Manual 10 Business Days After Contract Award A As Required

4 Certificate Of Facility Readiness (COFR)

See “Milestone Performance and Payment” Article

A As Required

5 Facility Environment History 10 Business Days After Contract Award I As Required

Off-loading and Transport Operation Procedures and Transportation route survey

20 Days Prior to facility occupancy date A As Required

7 Orientation Presentation No Later Than Ground Operations Review I As Required

8 Impound Plan 10 Business Days After Contract Award I As Required

9 Mishap Reporting and Investigation

No Later Than 5 Days after Type A, B, or C Occurrence. No Later Than 7 Days after all other Occurrence.

I As Required

DRL 1 Facility Occupancy Manifest

The latest facility manifest will be provided anytime changes have occurred that may have an impact on the NASA Spacecraft. The facility manifest shall include the known payload processing commitments in the facility, whether they are commercial or Government, including the initial facility occupancy and processing durations, the facility readiness schedule (cleaning time, stabilization time), and planned facility outages.

DRL 2 Facility Handbook

The facility handbook shall have a complete description of the facility and facility systems capabilities. As the facility or facilities systems are modified, the Contractor shall revise the Facility Handbooks and applicable safety documentation requirements to reflect the current facility and facility systems capabilities.

DRL 3 Facility Safety Manual

The Facility Safety Manual should provide detailed description of the hazardous and critical systems in a facility in accordance with AFSPCMAN 91-710. As standard operating safety requirements for organizations occupying the facility change, the Contractor shall revise the safety manual to reflect current safety policy and criteria applicable to ground support equipment (GSE) and to ground operations processing at the facility. The Contractor shall also make the appropriate revisions if there are any mission-unique safety systems for a mission that drives the control or mitigation for a potential safety hazard other than those already addressed in the current Manual.

DDRL 4 Certificate of Facility Readiness (COFR)

The Contractor shall generate a detailed report on the facility, facility systems and facility support equipment documenting that the square footage required is provided for, and that contamination and environmental control, electrical, communication and video systems comply with the requirements as stated in the SOW and associated Appendices. As a minimum, the COFR shall:

• Identify all systems by name

• Identify each system as critical/non-critical

• Provide a brief description of status and readiness of the facility and each facility system

• Provide a copy of the certification for each systems proofload, calibration, compliance or inspection

• List supporting documentation for each system

• Provide a summary of facility modifications implemented since last NASA usage

• Include an Open items, Issues, and Concerns Section with associated correction plan and date

• Include an Exceptions, Waivers, and Deviations Section

Provide a Safety Statement of Readiness

DRL 5 Facility Environment History

The latest facility environment history will be provided to include the latest radio frequency (RF) survey results, the latest magnetic survey results and the latest cleanroom cleanliness results.

DRL 6 Offloading and Transport Operation Procedures and Transportation Route Survey

The Contractor shall be notified of approval or disapproval within ten business days of submittal. For offloading Flight hardware and GSE, any operation procedures used shall be submitted by the Contractor. The survey will include but not be limited to: road conditions, overhead obstruction, bridge conditions and a map identifying the transportation route. Not earlier than one (1) business day prior to transportation, a final route survey shall be performed by driving the transport route.

DRL 7 Orientation Presentation

The presentation and hand-out material shall include: the Contractor’s key personnel contacts, facility layout, operation methodology, status of the processing facility and its associated systems, open deviation/waivers, anomalies currently open or under investigation, safety training information, delivery dates of commodities, and agreements for services. Also, the package shall address mission unique requirements, support and services. An overview of the processing facility and mission flow shall be provided.

DRL 8 Impound Plan

The Contractor’s Impound Plan shall identify the procedures/actions, roles and responsibilities that will be implemented by the Contractor after a mishap occurs.

The Impound Plan shall include:

a. Identification of the location or space where impounded data, records, and equipment shall be stored and secured during an investigation.

b. Procedures for release of impounded data, records, equipment, and facilities at the mishap site.

Data and records, regardless of format, to be impounded may include, but are not limited to:

a. Check-out logs, test and check-out record charts, launch records, weather information, telemetry tapes, video tapes, audio tapes, timecards, training records, work authorization documents, inspection records, analyses, and problem reports.

b. Historical data associated with the specific equipment, operations, and operating personnel including, environmental, operational, psychological, and other factors bearing on the situation.

DRL 9 Mishap Reporting and Investigation

For Type A, B, C, and D mishaps and close calls, as defined in NPR 8621.1, reports shall be generated per requirements in SOW paragraph 3.1. A copy of the report shall be forwarded to the COR within five days for Type A, B, and C mishaps and seven days for all others.

Attachment 3
DATA REQUIREMENTS LIST

File details come from the government source that posted it. Updated .