03-4J9004 Construct Acceleration Lanes.pdf
PDF 781 KB Posted
- Attached to
- 03-4J9004 Construct Acceleration Lanes
- Solicitation number
- 03-4J9004, Fed #HSIM-0056(363)
- Issued by
- Sacramento County, San Francisco City, California
About this file
This is a Notice to Bidders and Special Provisions document issued by the California Department of Transportation (Caltrans) District 03 for construction work on State Highway 5 in Sacramento County near Thornton. The project involves constructing acceleration lanes from Lost Slough Bridge to Dierssen Road Overcrossing (Post Mile 1.2/3.1) under Contract No. 03-4J9004, a federal-aid project designated as HSIM-0056(363). The work encompasses 74 bid items including earthwork, erosion control, asphalt concrete paving, traffic control systems, electrical systems, signage, pavement markings, and temporary construction elements. Bidders must submit electronically sealed bids by 2:00 p.m. on Tuesday, August 25, 2026, with work to be completed within a bid range of 65 to 90 working days on a cost-plus-time basis. The project requires either a Class A contractor license or a Class C-12 license constituting the majority of work, and an estimated project cost of $5,400,000 is provided for reference.
Bidders must submit security equal to at least 10 percent of their bid amount. Prevailing wages are required, and contractors must comply with both California Department of Industrial Relations wage rates and federal minimum wage determinations, applying whichever rate is higher. The contract includes extensive special provisions addressing traffic control during construction, with detailed lane closure restrictions by day and time for both mainline freeway and ramp operations. Key requirements include maintaining at least one through lane open in each direction, implementing portable radar speed feedback sign systems, and complying with construction work zone speed limit reductions. Additional compliance mandates cover Buy America requirements for manufactured products and construction materials, environmental product declarations for hot mix asphalt and concrete, stormwater pollution prevention, local material testing and certification, treated wood waste management, and professional project partnering. Liquidated damages are assessed for failure to open scheduled closures, limited to 5 percent of the total bid per occurrence, with damages calculated at $1,531 to $3,062 per 10-minute interval depending on facility type and time period.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bids open Tuesday, August 25, 2026
Dated July 20, 2026
STATE OF CALIFORNIA
DEPARTMENT OF TRANSPORTATION
NOTICE TO BIDDERS
AND
SPECIAL PROVISIONS
FOR CONSTRUCTION ON STATE HIGHWAY IN SACRAMENTO COUNTY
NEAR THORNTON FROM LOST SLOUGH BRIDGE TO DIERSSEN ROAD
OVERCROSSING
In District 03 On Route 5
Under
Bid book dated July 20, 2026 Standard Specifications dated 2025
Project plans approved May 18, 2026 Standard Plans dated 2025
Identified by
Contract No. 03-4J9004
03-Sac-5-1.2/3.1
Project ID 0323000287
Federal-Aid Project
HSIM-0056(363)
SPECIAL NOTICES
See sections 2 and 3 for contractors' registration requirements.
The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.
See section 2 for submittal requirements for DVBE quotes and Non–Small Business
Subcontractor Preference.
For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).
See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.
The flagging and temporary traffic control requirements have been revised. See sections 7-
1.03, 7-1.04, and 12.
See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.
See section 14-11.14 for changes to the management of treated wood waste.
See section 6-1.01 and 6-1.04 of these Special Provisions for the requirements of Buy
America/Build America for manufactured products.
See section 6-1.08 for the requirements for environmental product declarations for hot mix asphalt and concrete materials and products.
Contract No. 03-4J9004 i
TABLE OF CONTENTS
NOTICE TO BIDDERS
BID ITEM LIST
SPECIAL PROVISIONS
ORGANIZATION
DIVISION I GENERAL PROVISIONS
1 GENERAL
2 BIDDING
5 CONTROL OF WORK
6 CONTROL OF MATERIALS
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
8 PROSECUTION AND PROGRESS
9 PAYMENT
DIVISION II GENERAL CONSTRUCTION
12 TEMPORARY TRAFFIC CONTROL
13 WATER POLLUTION CONTROL
14 ENVIRONMENTAL STEWARDSHIP
15 EXISTING FACILITIES
DIVISION III EARTHWORK AND LANDSCAPE
19 EARTHWORK
21 EROSION CONTROL
DIVISION V SURFACINGS AND PAVEMENTS
36 GENERAL
39 ASPHALT CONCRETE
DIVISION VI STRUCTURES
49 PILING
DIVISION IX TRAFFIC CONTROL DEVICES
84 MARKINGS
DIVISION X ELECTRICAL WORK
86 GENERAL
87 ELECTRICAL SYSTEMS
ii
STANDARD PLANS LIST
The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.
RSP A3A Abbreviations (Sheet 1 of 3)
RSP A3B Abbreviations (Sheet 2 of 3)
RSP A3C Abbreviations (Sheet 3 of 3)
A10A Legend - Lines and Symbols (Sheet 1 of 5)
A10B Legend - Lines and Symbols (Sheet 2 of 5)
A10C Legend - Lines and Symbols (Sheet 3 of 5)
A10D Legend - Lines and Symbols (Sheet 4 of 5)
A10E Legend - Lines and Symbols (Sheet 5 of 5)
A20A Pavement Markers and Traffic Lines - Typical Details
A20B Pavement Markers and Traffic Lines - Typical Details
A20D Pavement Markers and Traffic Lines - Typical Details
A40B Shoulder Rumble Strip Details - Ground-In Indentations
P75 Pavement Edge Treatments - Overlays
P76 Pavement Edge Treatments - New Construction
H1 Landscape and Erosion Control Symbols
H51 Erosion Control Details - Fiber Roll and Compost Sock
T1A Temporary Crash Cushion - Sand Filled (Unidirectional)
T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)
T1B Temporary Crash Cushion - Sand Filled (Bidirectional)
T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)
T3C Temporary Barrier System (Cross Bolt)
T3D Temporary Barrier System (Cross Bolt)
T3E Temporary Barrier System (Cross Bolt)
T3F Temporary Barrier System (Cal F-23)
T3F2 Temporary Barrier System (Cal F-23)
T3G Temporary Barrier System (Staking or Anchoring)
T3G2 Temporary Barrier System (Staking or Anchoring)
T9 Traffic Control System Tables for Lane and Ramp Closures
T10 Traffic Control System for Lane Closure on Freeways and Expressways
RSP T13 Traffic Control System with Reversible Control on Two Lane Conventional Highways
T14 Traffic Control System for Ramp Closure iii
T15 Traffic Control System for Moving Lane Closure on Multilane Highways
T16 Traffic Control System for Moving Lane Closure on Multilane Highways
T18 Traffic Control System - Construction Work Zone Speed Limit Reduction on Freeways and Expressways
T21 Traffic Control System - Construction Work Zone Speed Limit Reduction Twenty- Four Hours a Day 7 Days a Week (24/7)
RS1 Roadside Signs - Typical Installation Details No. 1
RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2
RS4 Roadside Signs - Typical Installation Details No. 4
ES-1A Electrical Systems (Legend)
ES-1B Electrical Systems (Legend)
ES-1C Electrical Systems (Legend)
ES-2A Electrical Systems (Service Equipment)
ES-2D Electrical Systems (Service Equipment Enclosure and Typical Wiring Diagram, Type III - A Series)
ES-6B Electrical Systems (Electrolier Anchorage and Grouting for Type 15 and Type 21, Barrier Rail Mounted)
ES-6G Electrical Systems (Lighting Standard, Type 32)
ES-7B Electrical Systems (Signal and Lighting Standard, Type 1 and Equipment Identification Characters)
ES-7M Electrical Systems (Signal and Lighting Standard, Details No. 1)
ES-7N Electrical Systems (Signal and Lighting Standard, Details No. 2)
RSP ES-7O Electrical Systems (Signal and Lighting Standard, Details No. 3)
ES-8A Electrical Systems (Non-Traffic Pull Box)
ES-8B Electrical Systems (Traffic Pull Box)
ES-11 Electrical Systems (Foundation Installations)
ES-13A Electrical Systems (Splice Insulation Methods Details)
ES-15D Electrical Systems (Lighting and Sign Illumination Control)
CANCELED STANDARD PLANS LIST
The 2025 standard plan sheets listed below are canceled and not applicable to this contract.
Plan No.
Date
Canceled Plan No.
Date Canceled
Plan No.
Date
Canceled
P8 04-20-26
NOTICE TO BIDDERS
Bids open Tuesday, August 25, 2026
Dated July 20, 2026
General work description: Construct acceleration lanes.
The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON
STATE HIGHWAY IN SACRAMENTO COUNTY NEAR THORNTON FROM LOST SLOUGH BRIDGE TO
DIERSSEN ROAD OVERCROSSING.
District-County-Route-Post Mile: 03-Sac-5-1.2/3.1
Contract No. 03-4J9004
The Contractor must have either a Class A license or the following Class C license which constitutes a majority of the work: C-12.
Federal-aid project no.:
HSIM-0056(363)
Bids must be on a cost+time basis.
Complete the work within the number of working days bid.
Do not bid less than 65 working days and not more than 90 working days.
The estimated cost of the project is $5,400,000.
The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.
The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.
For bid results go to:
https://ppmoe.dot.ca.gov/cc
Select Electronic Bidding under the Bidding tab.
District office addresses are provided in the Standard Specifications.
Present bidders' inquiries to the Department and view the Department's responses at:
https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries
Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.
Submit your bid with bidder's security equal to at least 10 percent of the bid.
Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.
The federal minimum wage rates for this Contract as determined by the United States Secretary of Labor are available at https://sam.gov/content/home.
If the minimum wage rates as determined by the United States Secretary of Labor differs from the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors must not pay less than the higher wage rate. The Department does not accept lower State wage rates not specifically included in the federal minimum wage determinations. This includes helper, or other classifications based on hours of experience, or any other classification not appearing in the federal wage determinations. Where federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors must not pay less than the federal minimum wage rate that most closely approximates the duties of the employees in question.
The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.
Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.
Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.
Department of Transportation
BID ITEM LIST
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM
0002 090105 TIME-RELATED OVERHEAD (LS) LS LUMP SUM
0003 090200 DISPUTE RESOLUTION ADVISOR ON-SITE
MEETING
EA 4
0004 090207 HOURLY OFF-SITE DISPUTE-RESOLUTION-
ADVISOR-RELATED TASKS
HR 10
0005 100100 DEVELOP WATER SUPPLY LS LUMP SUM
0006 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM
0007 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM
0008 120120 TYPE III BARRICADE EA 23
0009 120159 TEMPORARY TRAFFIC STRIPE (PAINT) LF 14,400
0010 120195 TRAFFIC DRUM EA 14
0011 120207 PORTABLE RADAR SPEED FEEDBACK SIGN
SYSTEM
DAY 180
0012 120320 TEMPORARY BARRIER SYSTEM LF 6,440
0013 128652 PORTABLE CHANGEABLE MESSAGE SIGN (LS) LS LUMP SUM
0014 129108 TEMPORARY CRASH CUSHION TL-3 EA 2
0015 129161 AUTOMATED FLAGGER ASSISTANCE DEVICE
DAY
EA 20
0016 130100 JOB SITE MANAGEMENT LS LUMP SUM
0017 130301 STORMWATER POLLUTION PREVENTION PLAN LS LUMP SUM
0018 130312 PRE-STORM EVENT INSPECTION REPORT EA 3
0019 130323 DURING-AND POST-STORM EVENT INSPECTION
REPORT
DAY 4
0020 130331 STORMWATER ANNUAL REPORT EA 2
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0021 130505 MOVE-IN/MOVE-OUT (TEMPORARY EROSION
CONTROL)
EA 6
0022 130530 TEMPORARY HYDRAULIC MULCH (BONDED
FIBER MATRIX)
SQYD 2,040
0023 130610 TEMPORARY CHECK DAM LF 120
0024 130620 TEMPORARY DRAINAGE INLET PROTECTION EA 9
0025 130640 TEMPORARY FIBER ROLL LF 2,000
0026 130680 TEMPORARY SILT FENCE LF 5,390
0027 130710 TEMPORARY CONSTRUCTION ENTRANCE EA 6
0028 130730 STREET SWEEPING LS LUMP SUM
0029 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM
0030 141120 TREATED WOOD WASTE LB 1,500
0031 160110 TEMPORARY HIGH-VISIBILITY FENCE LF 1,120
0032 170103 CLEARING AND GRUBBING (LS) LS LUMP SUM
0033 190101 ROADWAY EXCAVATION CY 8,310
0034 190185 SHOULDER BACKING TON 630
0035 198215 SUBGRADE ENHANCEMENT GEOGRID SQYD 3,140
0036 210252 BONDED FIBER MATRIX (SQFT) SQFT 119,000
0037 210350 FIBER ROLLS LF 5,720
0038 210360 COMPOST SOCK LF 1,090
0039 210610 COMPOST (CY) CY 360
0040 260203 CLASS 2 AGGREGATE BASE (CY) CY 2,100
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0041 390132 HOT MIX ASPHALT (TYPE A) TON 11,300
0042 390137 RUBBERIZED HOT MIX ASPHALT (GAP GRADED) TON 1,680
0043 390402 RUBBERIZED HOT MIX ASPHALT-OPEN GRADED
(OPEN GRADED FRICTION COURSE)
TON 840
0044 397005 TACK COAT TON 5
0045 398200 COLD PLANE ASPHALT CONCRETE PAVEMENT SQYD 3,800
0046 568042 REMOVE SIGN STRUCTURE WALKWAY (EA) EA 2
0047 568060 MODIFY SIGN STRUCTURE EA 2
0048 750500 (F) - MISCELLANEOUS METAL LB 610
0049 810170 DELINEATOR (CLASS 1) EA 50
0050 810230 PAVEMENT MARKER (RETROREFLECTIVE) EA 600
0051 820113 TREATMENT BEST MANAGEMENT PRACTICE
MARKER
EA 2
0052 820250 REMOVE ROADSIDE SIGN EA 29
0053 820300 REMOVE ROADSIDE SIGN (STRAP AND SADDLE
BRACKET METHOD)
EA 7
0054 820360 REMOVE SIGN PANEL EA 2
0055 820710 FURNISH LAMINATED PANEL SIGN (1"-TYPE A) SQFT 320
0056 820750 FURNISH SINGLE SHEET ALUMINUM SIGN
(0.063"-UNFRAMED)
SQFT 250
0057 820760 FURNISH SINGLE SHEET ALUMINUM SIGN
(0.080"-UNFRAMED)
SQFT 220
0058 820790 FURNISH SINGLE SHEET ALUMINUM SIGN
(0.080"-FRAMED)
SQFT 200
0059 820840 ROADSIDE SIGN - ONE POST EA 31
0060 820850 ROADSIDE SIGN - TWO POST EA 7
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0061 820860 INSTALL SIGN (STRAP AND SADDLE BRACKET
METHOD)
EA 3
0062 820890 INSTALL SIGN PANEL ON EXISTING FRAME SQFT 320
0063 840516 THERMOPLASTIC PAVEMENT MARKING
(ENHANCED WET NIGHT VISIBILITY)
SQFT 550
0064 840623 6" THERMOPLASTIC TRAFFIC STRIPE
(ENHANCED WET NIGHT VISIBILITY) (BROKEN
36-12)
LF 7,160
0065 846007 6" THERMOPLASTIC TRAFFIC STRIPE
(ENHANCED WET NIGHT VISIBILITY)
LF 14,100
0066 846009 8" THERMOPLASTIC TRAFFIC STRIPE
(ENHANCED WET NIGHT VISIBILITY)
LF 270
0067 846010 8" THERMOPLASTIC TRAFFIC STRIPE
(ENHANCED WET NIGHT VISIBILITY) (BROKEN
12-3)
LF 3,220
0068 846013 12" THERMOPLASTIC TRAFFIC STRIPE
(ENHANCED WET NIGHT VISIBILITY)
LF 2,380
0069 846034 REMOVE TRAFFIC STRIPE (HIGH-PRESSURE
WATER BLASTING)
LF 21,900
0070 846051 12" RUMBLE STRIP (ASPHALT CONCRETE
PAVEMENT)
STA 130
0071 870009 MAINTAINING EXISTING TRAFFIC MANAGEMENT
SYSTEM ELEMENTS DURING CONSTRUCTION
LS LUMP SUM
0072 872131 MODIFYING LIGHTING SYSTEMS LS LUMP SUM
0073 872142 REMOVING SIGN ILLUMINATION SYSTEMS LS LUMP SUM
0074 999990 MOBILIZATION LS LUMP SUM
SPECIAL PROVISIONS
ORGANIZATION
Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.
Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.
Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.
DIVISION I GENERAL PROVISIONS
1 GENERAL
Add to section 1-1.01:
Bid Items and Applicable Sections
Item code
Item description Applicable section
090200 DISPUTE RESOLUTION ADVISOR ON-SITE MEETING 5
090207 HOURLY OFF-SITE DISPUTE-RESOLUTION-ADVISOR-RELATED
TASKS
2 BIDDING
Add between the 1st and 2nd paragraphs of section 2-1.06B:
The Department makes the following supplemental project information available:
Supplemental Project Information
Means Description Included in the Information Handout 1. TMS Element Operational Status Certified List
Available as specified in the Standard Specifications
1. Digital terrain model LandXML format
2. Alignments in LandXML format
3. Cross sections in 2D DGN and PDF format
4. Digital design model in LandXML format
5. NB & SB Targetlines in LandXML format
Delete section 2-1.20.
Delete section 2-1.33B(2)(b).
5 CONTROL OF WORK
Replace the 2nd and 3rd paragraphs of section 5-1.09A with:
Professionally facilitated project partnering is required.
Delete section 5-1.13B.
Replace section 5-1.13E with:
5-1.13E Prompt Payment
Section 5-1.13E applies to all contracts.
Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.
Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:
1. Subcontractor’s or entity’s business name
2. Description of work performed
2.1. Bid item numbers or change order numbers
2.2. Written narrative of work performed
3. Value of work performed
4. Amount paid to subcontractor or entity
5. Withhold amount, if applicable
6. Explanation of withhold reasoning, if applicable
Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.
If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:
1. Value of the disputed work
2. Amount of the withhold being taken
3. Bid item numbers or change order numbers associated with the disputed work
4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated
5. Corrective actions to be taken for release of withheld amount
The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.
The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:
1. Withhold was not applied in good faith
2. Requested additional withhold documentation records were not provided
3. Payment information was not submitted through the prompt payment monitoring system
4. Required withhold notification was not provided
The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.
Replace section 5-1.26 with:
5-1.26 GRADE QUALITY CONTROL
Use a global navigation satellite system (GNSS) rover, robotic total station equipment, or a level to check the grades at the frequencies shown in the following table:
Grade Checking Requirements
Type of work Area or distance represented by the grade checking Frequency
(number of grade points) Earthwork for cut and fill slopes ≤15 feet 200 feet 2 Earthwork for cut and fill slopes ˃15 feet 1,000 sq yd 1 Rough grading 1,000 sq yd 1 Trenching 100 feet 6 Subgrade 1 mi 30 Subbase layer 1 mi 50 Base layer 1 mi 100 Curb and gutter 100 feet 6 Concrete barrier 100 feet 5 Finishing roadway 1,000 sq yd 2
Increase the frequency of grade checking of a roadway:
1. Wherever its curve radius is 500 feet or less
2. In areas of a superelevation transition
3. At intersections
Notify the Engineer when an area is ready for line and grade inspection. Submit the grade checking results on a Grade Checking Report form as an informational submittal.
6 CONTROL OF MATERIALS
Add to end of section 6-1.01:
If you fail to submit the form for materials subject to Buy America, the Department may:
1. Withhold from the next progress payment
2. Reject your request for a De Minimis Costs waiver for non-compliant construction materials or manufactured products
Replace section 6-1.03B with:
6-1.03B Submittals
6-1.03B(1) General
Not Used
6-1.03B(2) Work Plan
For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:
1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under section 6-1.03B(3) for other constituents of concern based on the land use history. I am aware that local material sources must not contain ADL at concentrations greater than 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II. I am aware that a maximum quantity of material may be excavated at the site based on the minimum number of samples taken before excavating at the site under section 6-1.03B(3).
2. Land use history of the local material location and surrounding property
3. Sampling protocol
4. Number of samples per volume of local material
5. QA and QC requirements and procedures
6. Qualifications of sampling personnel
7. Stockpile history
8. Name and address of the analytical laboratory that will perform the chemical analyses
9. Analyses that will be performed for lead and pH
10. Other analyses that will be performed for possible hazardous constituents based on:
10.1. Source property history
10.2. Land use adjacent to source property
10.3. Constituents of concern in the ground water basin where the job site is located
The plan must be sealed and signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State.
If the plan requires revisions, the Engineer provides comments. Submit a revised plan within 7 days of receiving comments. Allow 7 days for the review.
6-1.03B(3) Analytical Test Results
At least 15 days before placing local material, submit analytical test results for each local material obtained from a noncommercial source or a source not regulated under CA jurisdiction. The analytical test results must include:
1. Certification signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
The analytical testing described in the local material plan has been performed. I performed a statistical analysis of the test results using the US EPA's ProUCL software with the applicable 95 percent upper confidence limit. I certify that the material from the local material source is suitable for unrestricted use at the job site, it has a pH above 5.0, does not contain soluble lead in concentrations equal to or greater than 5mg/l as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II, does not contain lead in concentrations above 80 mg/kg total lead, is free from all other contaminants identified in the local material plan, and will comply with the job site's basin plan and water quality objectives of the RWQCB.
2. Chain of custody of samples
3. Analytical results no older than 1 year
4. Statistical analysis of the data using US EPA’s ProUCL software with a 95 percent upper confidence limit
5. Comparison of sample results to hazardous waste concentration thresholds and the RWQCB's basin plan requirements and water quality objectives for the job site location
6-1.03B(4) Sample and Analysis
Sample and analyze local material from a (1) noncommercial source or (2) a source not regulated under CA jurisdiction:
1. Before bringing the local material to the job site
2. As described in the local material plan
3. Under US EPA Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846)
The sample collection must be designed to generate a data set representative of the entire volume of proposed local material.
Before excavating at the (1) noncommercial material source or (2) a source not regulated under CA jurisdiction, collect the minimum number of samples and perform the minimum number of analytical tests for the corresponding maximum volume of local material as shown in the following table:
Minimum Number of Samples and Analytical Tests for Local Material
Maximum volume of imported borrow (cu yd)
Minimum number of samples and analytical tests
< 5,000 8
5,000–10,000 12 for the first 5,000 cu yd plus 1 for each additional 1,000 cu yd or portion thereof
10,000–20,000 17 for the first 10,000 cu yd plus 1 for each additional 2,500 cu yd or portion thereof
20,000-40,000 21 for the first 20,000 cu yd plus 1 for each additional 5,000 cu yd or portion thereof
40,000–80,000 25 for the first 40,000 cu yd plus 1 for each additional 10,000 cu yd or portion thereof
> 80,000 29 for the first 80,000 cu yd plus 1 for each additional 20,000 cu yd or portion thereof
Do not collect composite samples or mix individual samples to form a composite sample.
Analyze the samples using the US EPA's ProUCL software with a 95 percent upper confidence limit. All chemical analysis must be performed by a laboratory certified by the SWRCB's Environmental Laboratory Accreditation Program (ELAP).
The analytical test results must demonstrate that the local material:
1. Is not a hazardous waste
2. Has a pH above 5.0
3. Has an average total lead concentration, based upon the 95 percent upper confidence limit, at or below 80 mg/kg
4. Is free of possible contaminants identified in the local material plan
5. Complies with the RWQCB's basin plan for the job site location 6 Complies with the RWQCB's water quality objectives for the job site location
6-1.03C Local Material Management
Do not place local material until authorized.
If the Engineer determines the appearance, odor, or texture of any delivered local material suggests possible contamination, sample and analyze the material. The sampling and analysis is change order work unless (1) hazardous waste is discovered or (2) the analytical test results indicate the material does not comply with section 6-1.03B(3).
Dispose of noncompliant local material at an appropriately permitted CA Class I, CA Class II or CA Class III facility. You are the generator of noncompliant local materials.
Replace section 6-1.04 with:
6-1.04 BUY AMERICA
6-1.04A General
Buy America requirements do not apply to the following:
1. Tools and construction equipment used in performing the work.
2. Temporary work that is not incorporated into the finished project.
An article, material, or supply to be permanently incorporated in the project should only be classified into one of the following categories:
1. Iron or steel products
2. Manufactured products
3. Construction materials
4. Excluded materials
Excluded materials means cement and cementitious materials; aggregates such as stone, sand, or gravel; or aggregate binding agents or additives.
6-1.04B Crumb Rubber (Pub Res Code § 42703(d))
Furnish crumb rubber with a certificate of compliance. Crumb rubber must be:
1. Produced in the United States
2. Derived from waste tires taken from vehicles owned and operated in the United States
6-1.04C Iron or Steel Products
Iron or steel products must be melted and manufactured in the United States except:
1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials
2. If the total combined cost of the materials produced outside the United States does not exceed the greater of 0.1 percent of the total bid or $2,500, the material may be used if authorized
Furnish iron or steel products to be incorporated into the work with certificates of compliance and certified mill test reports. Mill test reports must indicate where the steel and iron were melted and manufactured.
All melting and manufacturing processes for these materials, including an application of a coating, must occur in the United States. Coating includes all processes that protect or enhance the value of the material to which the coating is applied.
6-1.04D Manufactured Products
Manufactured products mean articles, materials, or supplies that have been:
1. Processed into a specific form and shape; or
2. Combined with other articles, materials, or supplies to create a product with different properties than the individual articles, materials, or supplies
Per 23 CFR 635.410, these products must be manufactured in the United States.
Manufacturer, in the case of manufactured products, means the entity that performs the final manufacturing process by bringing individual elements together that produces a manufactured product.
If an item is classified as an iron or steel product, a construction material, or an excluded material under the definitions set forth under this Buy America section, then it is not a manufactured product. However, an article, material, or supply classified as a manufactured product under this Buy America section may include components that are construction materials, iron or steel products, or excluded materials.
Iron or steel used in precast concrete manufactured products or enclosures for Intelligent Transportation Systems (ITS) must meet the requirements of section 6-1.04C regardless of the amount used.
Iron or steel used in other manufactured products must meet the requirements of section 6-1.04C if the cost of steel and iron components is 50 percent or more of the total cost of the manufactured product.
Furnish manufactured products to be incorporated into the work with certificates of compliance with each project delivery. The manufacturer's certificate of compliance must identify where the manufacturing occurred and attest specifically to compliance with the 23 CFR 635.410 standard.
6-1.04E Construction Materials
The following construction materials must be produced in the United States under standards in 2 CFR 184.6:
1. Non-ferrous metals
2. Plastic and polymer-based products such as:
2.1. Polyvinylchloride
2.2. Composite building materials
3. Glass
4. Fiber optic cable including drop cable
5. Optical fiber
6. Lumber
7. Engineered wood
8. Drywall
All manufacturing processes for these materials as defined in 2 CFR 184.6 must occur in the United States.
Furnish construction materials to be incorporated into the work with certificates of compliance with each project delivery. Manufacturer’s certificate of compliance must identify where the construction material was manufactured and attest specifically to compliance with the 2 CFR 184.6 standard.
Minor additions of articles, materials, supplies, or binding agents to these construction materials do not change the categorization of the construction material.
6-1.04F Buy America Waiver for the De Minimis Costs for Manufactured Products and Construction Materials
A De Minimis Costs waiver can waive the application of FHWA's Buy America requirements for manufactured products and construction materials under a single project when the total cost of non-compliant manufactured products and construction materials is no more than the lesser of $1,000,000 or 5 percent of the total applicable costs for the project.
The percentage threshold is calculated based on the following formula:
X = NC / TA
where:
X = percent threshold NC = total cost of non-compliant construction materials and manufactured products
TA = total applicable project costs (steel, iron, construction materials and manufactured products;
does not include excluded materials)
This threshold is based on the actual cost of the steel, iron, construction materials, and manufactured products, not the anticipated cost of those materials. The contractor must account for compliant and non-compliant Department-Furnished Materials for the project in the De Minimis Costs Waiver Worksheet calculation if provided by the Department as supplemental project information.
See further instructions for the De Minimis Costs waiver request in the Notice of Materials to be Used form.
Add to section 6-1:
6-1.08 ENVIRONMENTAL PRODUCT DECLARATIONS FOR HOT MIX ASPHALT AND CONCRETE
Section 6-1.08 includes specifications for environmental product declarations for hot mix asphalt and concrete materials and products.
See section 6-1.06B for definitions.
For projects with bid opening dates after February 1, 2025, with a total bid over $1 million and 175 or more original working days, materials or products specified in the following table require facility-specific, product stage, environmental product declarations as informational submittals:
Material or product Material specifications
Hot mix asphalta Section 39-2, "Hot Mix Asphalt" Excludes RHMA, OGFC, and BWC materials.
Concreteb Section 28-2, "Lean Concrete Bases," Section 28-3, "Rapid Strength Concrete Base," Section 28-4, "Lean Concrete Base Rapid Setting," Section 28-5, "Concrete Base," Section 40, "Concrete Pavement," Section 47-5, "Type 6 Retaining Walls," Section 49-3, "Cast-In-Place Concrete Piling," Section 49-4, "Steel Soldier Piling," Section 51, "Concrete Structures," Section 58-2, "Masonry Block," Section 73, "Concrete Curbs and Sidewalks," Section 83, "Railings and Barriers," and Section 99, "Building Construction."
Excludes volumetric-proportioned rapid strength concrete and Section 90-4 PC concrete members.
aFor each hot mix asphalt plant providing 2,250 tons or more on the project by job mix formula.
bFor each concrete plant providing 250 cubic yards or more on the project by mix design.
The requirements in section 6-1.08 do not apply to seasonal plants operating fewer than 6 months per year.
The requirements in section 6-1.08 do not apply to informal-bid contracts.
For product category rules for hot mix asphalt or concrete, go to the METS website. Use the product category rule in effect on the date of bid opening unless otherwise authorized. An environmental product declaration for hot mix asphalt or concrete is not required for either of the following conditions:
1. Applicable product category rule has expired without replacement as of the bid opening date.
2. Applicable product category rule was issued less than 50 days before the bid opening date.
Immediately notify the Engineer if a program operator has determined their product category rule does not allow for development of a facility-specific environmental product declaration. Include written correspondence from the program operator with your notification to the Engineer. If the Engineer determines the development of a facility-specific environmental product declaration cannot be achieved, an environmental product declaration will not be required for that material or product.
You must register on the Department’s Data Interchange for Materials Engineering (DIME) at least 15 days before submitting environmental product declarations. Follow the registration process at:
https://dime.dot.ca.gov/
Within 30 days of initial placement of each applicable material or product, submit a facility-specific, product stage, environmental product declaration informational submittal to DIME and provide proof of submission in PDF file format to the Engineer. The DIME entry information must include intended use of materials and estimated quantities of materials to be used as represented by the environmental product declaration.
Failure to provide a required environmental product declaration informational submittal will result in a $6,000 performance failure withhold for each missing declaration. The Department returns the withhold within 30 days after receipt of the compliant declaration if submitted prior to Contract acceptance.
Withholds become permanent deductions if the declaration is not submitted before Contract acceptance.
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
Replace Section 7-1.02K(6)(j)(iii) with:
7-1.02K(6)(j)(iii) Unregulated Earth Material Containing Lead
Section 7-1.02K(6)(j)(iii) includes specifications for handling, removing, and disposing of unregulated earth material containing lead. Management of this material exposes workers to health hazards that must be addressed in your lead compliance plan. This material contains average lead concentrations below 80 mg/kg total lead and below 5 mg/L soluble lead and is not regulated by DTSC as a hazardous substance or a hazardous waste. This material does not require disposal at a permitted landfill or solid waste disposal facility. The RWQCB has jurisdiction over reuse of this material at locations outside the job site limits.
Unregulated earth material exists throughout the job site.
Lead is typically found within the top 2 feet of material within the highway. Reuse all of the excavated material on the right-of-way.
Handle the material under all applicable laws, rules, and regulations, including those of the following agencies:
1. Cal/OSHA
2. CA RWQCB, Region 5S – Central Valley
8 PROSECUTION AND PROGRESS
Replace the row for DBE and DVBE in the table in the 2nd paragraph of section 8-1.03 with:
DVBE Final utilization reports
Replace the row for Schedule in the table in the 2nd paragraph of section 8-1.03 with:
Schedule Baseline schedule and weekly statement of working days report
Replace section 8-1.04C with:
8-1.04C Delayed Start
Section 8-1.04B does not apply.
Start job site activities within 180 days after receiving notice that the Contract has been approved by the Attorney General or the attorney appointed and authorized to represent the Department.
Do not start job site activities until the Department authorizes or accepts your submittal for:
3. CPM baseline schedule
4. WPCP or SWPPP, whichever applies
5. Notification of DRA or DRB nominee and disclosure statement
7. Contingency plan for opening closures to traffic
You may enter the job site only to measure controlling field dimensions and locate utilities.
Do not start other job site activities until all the submittals from the above list are authorized or accepted and the following information is received by the Engineer:
1. Notice of Materials To Be Used form.
2. Written statement from the vendor that the order for sign panels has been received and accepted by the vendor. The statement must show the dates that the materials will be shipped.
3. Written statement from the vendor that the order for electrical material has been received and accepted by the vendor. The statement must show the dates that the materials will be shipped.
4.
You may start job site activities before the 180th day after Contract approval if you:
1. Obtain specified authorization or acceptance for each submittal before the 180th day
2. Receive authorization to start
Submit a notice 72 hours before starting job site activities. If the project has more than 1 location of work, submit a separate notice for each location.
Replace the 4th and 5th paragraphs of section 8-1.05 with:
The Engineer issues a weekly statement of working days report by the end of the following week. If you disagree with a weekly statement of working days report, submit an RFI within 5 business days of receipt of the report.
The weekly statement of working days report shows:
1. Working days and non–working days during the reporting week
2. Time adjustments
3. Calculations of work completion dates, including working days remaining
4. Controlling activities
Delete the 6th paragraph of section 8-1.05.
9 PAYMENT
Replace the 1st paragraph of section 9-1.11D with:
For progress payments, the total work completed for the TRO bid item is the number of working days shown for the pay period on the weekly statement of working days report.
Replace item 2 in the list in the paragraph of section 9-1.16C with:
2. Material cost exceeds either of the following:
2.1. $50,000
2.2. $25,000 if the requestor is certified as one or more of the following:
2.2.1. DVBE
2.2.2. Small business as certified by Department of General Services, Office of Small
Business and Disabled Veteran Business Enterprise Services
DIVISION II GENERAL CONSTRUCTION
12 TEMPORARY TRAFFIC CONTROL
Add to section 12-3.11B(5)(b):
Provide two C50D(CA) construction project funding identification signs.
Legend for the type of project must read as follows:
HIGHWAY CONSTRUCTION
Legend for the year of completion on project funding sign must read as follows:
YEAR OF COMPLETION: 2027
Replace section 12-3.20 with:
12-3.20 TEMPORARY BARRIER SYSTEMS
12-3.20A General
12-3.20A(1) Summary
Section 12-3.20 includes specifications for temporary barrier systems.
Temporary barrier system consists of:
1. New or undamaged used interconnected barrier segments
2. Segment connection hardware
3. Stakes and anchor bolts
Value engineering change proposals for the use of Type K temporary railing are not allowed.
If a discrepancy exists, governing ranking in descending order is:
1. These specifications
2. Approved manufacturer's drawings
3. Approved manufacturer's installation instructions
Markers must comply with section 82.
12-3.20A(2) Definitions anchored: Method for attaching temporary barrier segments to concrete pavement.
approach zone: Area immediately upstream of the protected area.
clear area width: Minimum width throughout the length of the barrier system that must be maintained clear of obstructions, objects, and work resources during non-working hours. The width is measured perpendicular from the non-traffic side toe.
departure zone: Area immediately downstream of the protected area.
freestanding: Temporary barrier not attached to the pavement.
height differential: May be an excavation, a downward slope greater than 4:1, or a difference in elevation. The height differential is measured down from the top of pavement.
minimum system length: Sum of approach zone, protected area, and departure zone.
set back distance: Measured between the closest toe of temporary barrier and the edge of traveled way for each direction of traffic.
staked: Method for attaching temporary barrier segments to asphalt concrete pavement.
12-3.20A(3) Submittals
Submit as informational submittal for each type of temporary barrier system:
1. Certificate of compliance.
2. Manufacturer's installation instructions except for temporary concrete barriers CrossBolt and CAL F-
23.
3. Manufacturer's concrete QC test results and daily production log of precast concrete activities, under section 90-4. QC test results must include the concrete mix design number and barrier stamped ID.
Submit connection bolt test reports that certify compliance with the applicable ASTM requirements, for temporary barrier systems CrossBolt. The test reports must be from a laboratory that is accredited to International Standards Organization/International Electrotechnical Commission 17025 by the American Association for Laboratory Accreditation (A2LA) or the ANSI-ASQ National Accreditation Board.
Submit a signed manufacturer's replacement evaluation report within 10 days of damage to a temporary steel barrier system.
12-3.20A(4) Quality Assurance
12-3.20A(4)(a) General
QC sampling, testing, and inspection personnel must have an ACI Concrete Field-Testing Technician, Grade 1 certification.
Temporary concrete barrier segments must:
1. Comply with the requirements for tier 3 precast concrete in section 90-4
2. Be fabricated at a plant on the Authorized Facility Audit List
Concrete must be sampled and tested as shown in the following table.
Concrete QC Tests Quality characteristic Test method Minimum testing frequency
Compressive strength ASTM C172/C172M, ASTM C31/C31M, and
ASTM C39/C39M
Once per 300 cu yd of concrete cast, or every day of casting, whichever is more frequent
Slump ASTM C143/C143M Temperature at time of mixing ASTM C1064/C1064M Density ASTM C138 Once per 600 cu yd of concrete cast or every 7 days of batching, whichever is more frequent
Air content ASTM C231/C231M or
ASTM C173/C173M
If concrete is air entrained, once for each set of cylinders, and when conditions warrant
A daily production log of precast concrete activities must be maintained under section 90-4.01C(4).
12-3.20A(4)(b) Quality Control
Not Used
12-3.20B Materials
12-3.20B(1) General
Temporary barrier segment must:
1. Be a minimum 31-1/2 inches in height
2. Have at least two lifting holes
3. Be designed to be used with temporary traffic screen when required
Temporary barrier segment may have your name or logo on each barrier segment. The name or logo must be no more than 4 inches in height and must be located no more than 12 inches above the bottom of the barrier segment.
Temporary barrier systems must comply with a minimum MASH Test Level 3.
Except for CrossBolt, and CAL F-23, temporary barrier systems must:
1. Be on the Authorized Materials List for highway safety features
2. Comply with the manufacturer's drawings shown on the Department's Division of Safety Programs website and the manufacturer's installation instructions
12-3.20B(2) Temporary Concrete Barriers
12-3.20B(2)(a) General
Not Used
12-3.20B(2)(b) Temporary Concrete Barriers Type F
12-3.20B(2)(b)(i) General
Temporary concrete barrier Type F segment must:
1. Be precast concrete with a minimum 5,000-psi compressive strength.
2 Have bar or welded wire reinforcement steel that complies with section 52.
3. Have a finished surface that complies with section 51-1.03F(2).
4. Include the manufacturer's name, lot number, and month and year of manufacture stamped on the top of each barrier segment. The stamped information must be:
4.1. No more than 6 inches in height
4.2. From 3/16 to 1/4 inch in depth
4.3. Centered on the top width of the barrier segment
5. Use one of the following segment connections:
5.1. Loop and pin
5.2. "J" hook
5.3. CrossBolt
6. Comply with the tolerances shown in the following table:
Precast Barrier Tolerances Dimension Tolerance(±)
Length (in) 1 Insert placement (in) 1/2 Horizontal alignment (in) 1/8 per 10 feet of length Deviation of ends (in):
Horizontal skew Vertical batter
1/4 1/8 per foot of depth
Bar reinforcement steel must:
1. Comply with ASTM A615 or ASTM A706, Grade 60
2. Be galvanized under section 52-3, when shown
Welded wire reinforcement must comply with ASTM A1064.
Stake must:
1. Be steel and comply with ASTM A36/A36M-14 or ASTM A529-14, Grade 50
2. Be 1-1/2 inches in diameter and 36 inches long, except "J" Hook must be 48 inches long
3. Have a 1/2-by-3-1/2-by-3-1/2-inch plate welded 2 inches down from the upper end using a 3/8-inch fillet weld under AWS D1.1 or D1.4
Anchor bolt must:
1. Be a steel bolt or threaded rod 1-1/8 inches in diameter
2. Comply with ASTM A307
3. Include a 1/2-by-3-1/2-by-3-1/2-inch plate washer:
3.1. With a 1-3/8-inch-diameter hole in the center
3.2. Complying with ASTM A36/A36M
3.3. Galvanized post fabrication under section 75-1.02B
Threaded rod must include a nut complying with ASTM A563.
Anchor steel plate must:
1. Be 1/2 inch thick
2. Comply with ASTM A572, Grade 50
3. Be galvanized post fabrication under section 75-1.02B
Chemical adhesive must be on the Authorized Materials List for chemical adhesives and must be for a threaded rod at least 1 inch in diameter.
12-3.20B(2)(b)(ii) Temporary Barrier Systems CrossBolt
CrossBolt hardware includes:
1. Connection bolt
2. Nut complying with ASTM A563
3. Hardened washer complying with ASTM F436, Type 1
4. Plate washer complying with ASTM A36/A36M and galvanized post fabrication under section 75-
1.02B
Connection bolt must:
1. Be a 7/8-inch bolt or threaded rod and comply with one of the following:
1.1. HS threaded rod ASTM A193, Grade B7
1.2. HS threaded rod ASTM A449, Type 1
1.3. HS nonheaded anchor bolt ASTM F1554, Grade 105, Class 2A
2. Have a permanent grade symbol and manufacturer's identifier
12-3.20B(2)(c)(iii) Temporary Barrier Systems CAL F-23
Connecting loop must:
1. Be a steel bar 3/4 inch in diameter
2. Comply with ASTM A36/A36M, cold roll
3. Be galvanized after fabrication
Connecting pin must:
1. Comply with ASTM A449
2. Be forged steel, no welds
3. Be 1 inch in diameter and a minimum 30-1/4 inches long
4. Be galvanized under ASTM F2329 and A153
12-3.20B(3) Temporary Steel Barriers
Temporary steel barrier segment must:
1. Be galvanized steel.
2. Have a joint connection.
3. Include permanent identification information with no more than 6 inches in height and 12 inches in length and centered on the top width of the segment. The identification information must include:
3.1. Manufacturer's name
3.2. Serial number
3.3. Lot number
3.4. Month and year of manufacture
Temporary steel barrier HV2 segment must be filled to a depth of 11-13/16 inches with concrete ballast.
12-3.20B(10) Temporary Terminal Sections
Not Used
12-3.20C Construction
12-3.20C(1) General
Clean temporary barrier segments at time of installation and at least every 6 months thereafter.
Install temporary barrier systems based on the requirements shown in the following tables:
Minimum Clear Area Width
Temporary barrier system
Configuration
Height differentials 3 feet or less
(ft)
Height differentials greater than 3 feet up to 8 feet
(ft)
Edge of deck or height differentials greater than
8 feet (ft)
Fixed objects, falsework members, or temporary supportsa
(ft) CrossBolt 10-foot & 30-foot
Freestanding 1 2 5 5 3 stakes or anchor bolts per segment traffic side
1 1 2 3
CrossBolt 20-foot
Freestanding 1 2 5 5 4 stakes or anchor bolts per segment traffic side
1 1 2 3
CAL F-23
12-foot
Freestanding 4 5 8 8 3 stakes or anchor bolts per segment traffic side
1 1 2 3
CAL F-23
20-foot
Freestanding 4 5 8 8 4 stakes or anchor bolts per segment traffic side
1 1 2 3
J-J hooks 12.5-foot
Freestanding 3 4 8 7 3 stakes per segment traffic side
1 1 2 3
2 anchor bolts per segment traffic side
1 1 2 3
J-J hooks 20-foot
Freestanding 3 4 8 7 4 stakes per segment traffic side
1 1 2 3
3 anchor bolts per segment traffic side
1 1 2 3
ProMASH 30-foot
Freestanding 1 2 4 4 3 stakes on traffic side
1 1 1 2
3 stakes each side (total 6)
1 1 1 2
ProMASH 20-foot
Freestanding 1 2 5 5 3 stakes on traffic side
1 1 2 3
3 stakes each side (total 6)
1 1 1 2
ProMASH 10-foot
Freestanding 2 3 6 6 2 stakes on traffic side
1 1 3 4
2 stakes each side (total 4)
1 1 2 3
REBLOC
39.33-foot
SDS
Freestanding
4 4 7 7
MDS
Staked or
Anchored every
6.5 feet
1 1 2 4
Zoneguard 50-foot
Freestanding Staked or anchored at both ends only
6 7 9 10
SDS
Staked or anchored every 250 feet
5 6 8 9
MDS
Staked or anchored every 33 feet
1 1 3 4
HV2
19-foot
Freestanding 4 5 7 8
Defender 12-3/4-foot
Staked every 30 feet
1 2 4 5
HighwayGuard 19.8-foot
SDS
Staked or
Anchored every 190 feet
4 5 7 8
LDS
Staked or
Anchored every 40 feet
1 2 5 5
MDS
Staked or
Anchored every
6.5 feet
1 1 1 2 aThe minimum clear area width to a falsework or temporary support footing can be 2 feet less than the clear area width shown. Measure clear area width to the footing edge closest to traffic.
Minimum System Length, Curve Radius, and Setback
Temporary barrier system
Barrier segment length
(ft)
Minimum system length
(ft) Minimum curve radius (ft)
Minimum setback
(ft) Posted speed greater than
45mph
Posted speed 45mph or less
CrossBolt 10
160 120
CAL F-23 12
160 120
J-J hooks 12.5
ProMASH 10
REBLOC
SDS
MDS 39.33
Zoneguard Freestanding
SDS
MDS
50 250 250 800 NAa NAa
HV2 19 323 323 262 5
Defender 12.75 260 260 755 2 HighwayGuard SDS 19.8 393 393 NAa 7 HighwayGuard LDS 19.8 200 200…