03 13-1005 Ktor Construction Cost Estimate Breakdown BLANK.xlsx

XLSX spreadsheet 24 KB Posted

Attached to
Replace Panelboard and Transformer shelter, Bldg 180 Federal contract opportunity
Solicitation number
FA557521B0005
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

View the file

Other files for this federal contract opportunity

Other files attached to Replace Panelboard and Transformer shelter, Bldg 180, newest first.
File Type Posted
18 13-1005 Especificaciones tecnicas.pdf PDF
06 13-1005 Specifications English.pdf PDF
07 13-1005 Drawings.pdf PDF
Solicitation - FA557521B0005.pdf PDF
12 13-1005 Schedule of Material Submittals.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IGE

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
MORÓN AIR BASE, SPAIN
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
RPL PANELBOARD AND TRANSFORMER SHELTER, Bldg #180
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 13-1005MORÓN AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
DEMOLITION WORKS
TRABAJOS DE DEMOLICIÓN
1Remove and dispose off pre-fabricated vault, Bldg #180
Eliminar y transportar a vertedero edificio prefabricado #180JOB
2Electrical demolition and disposal to authorized dump site
Demolición eléctrica y transporte a vertedero autorizadoJOB
STANDARD DEMOLITION WORKS TOTAL
TOTAL TRABAJOS DE DEMOLICIÓN ESTÁNDAR0.000.000.000.00
CIVIL WORKS
TRABAJOS DE CIVIL
3Levelling of the area
Nivelación de la zonaCM
4Excavation for new utility vault, inc. sand bed
Excavaciónm para nuevo centro de transformación, con lecho de arenaCM
5Excavation for generator concrete slab
Excavaciónm para losa de hormigón de grupo electrógenoCM
6Backfill and compaction
Relleno y compactaciónCM
7Install pre-manufactured building 6.44 x 2.50 m
Instalación edificio prefabricado 6.44 x 2.50 mEa
8Turf seeding
Siembra de céspedSm
CIVIL WORKS TOTAL
TOTAL TRABAJOS DE CIVIL0.000.000.000.00
ELECTRICAL WORKS
TRABAJOS DE ELECTRICIDAD
New Transformer Vault, Bldg #180 and UG lines
Nuevo Centro de Transformación, Edif #180 y líneas enterradas
9High Voltage Cable Terminals Indoors/Outdoors
Terminales Cable Alta Tensión Uso Interior/ExteriorEa
10Line Cabinet SM6-IM
Celda de Línea SM6-IMEa
11Re-install transformer Protection Cabinet SM6-QM
Re-instalar celda de Proteccion Transformador SM6-QMEa
12Re-instal transformer 12470/205V, 500 KVA 60 Hz
Re-instalar transformador 12470/208V, 500 KVA 60 HzEa
13Copper cable 1x185 mm2 RZ1-K (AS) 0.6/1 kV
Cable de cobre 1x185 mm2 RZ1-K (AS) 0.6/1 kVLm
14Copper cable 1x4 mm2 H07V-K (AS) 450/750V
Cable de cobre 1x4 mm2 H07V-K (AS) 450/750VLm
153/4" RMC including couplings & accessories
Conducto rígido acero galv. 3/4", incluso manguitos y accesoriosLm
16Capacitor Bank 98 KVAr and acc.
Batería de Condensadores 98 KVAr y acc.Ea
17Main distribution panelboard MDP
Cuadro de distribución principal MDPEa
18Weatherproof lighting fixture (Type A) 32W (+10% spares)
Luminaria estanca (Tipo A)32 W (+10% recambio)Ls
19LED floodlighting fixture (Type B) (+10% spares)
Proyectores LED (Tipo B) (+10% recambio)Ea
20Life Saving Kit
Kit de SeguridadEa
21Grounding system
Sistema de puesta a tierraLs
22Receptacle & toggle switch with conduit and wiring
Enchufe e interruptor con cableado y conductoEa
23Busbar Enclosure 1200x600x300 mm, IP66
Caja Repartidora 1200x600x300 mm, IP66Ea
New Transformer Vault, Bldg #180 and UG lines Total
Total Nuevo Centro de Transformación, Edif #180 y líneas enterradas0.000.000.000.00
New UG lines
Nuevas líneas enterradas
24High voltage RHZ1 OL 12/20 kV 1x35 mm² Cu
Cable alta tensión RHZ1 OL 12/20 kV 1x35 mm² CobreLm
25Galv. Rigid Metal Conduit 3" diammeter
Conducto Rígido Metálico Galvanizado 3" diam.Lm
26New HV underground line and accessories concrete encased
Nueva línea enterrada de alta tensión y accesorios en hormigónLm
27High voltage A1 type prefabricated manhole with cover
Arqueta prefabricada tipo A1 alta tension con tapaEa
28New LV underground line and accessorires
Nueva línea enterrada de baja tensión y accesoriosLm
29Low voltage A1 type prefabricated manhole with cover
Arqueta prefabricada tipo A1 baka tension con tapaEa
30Copper cable 1x150 mm2 RV-K 0.6/1 kV
Cable de cobre 1x150 mm2 RV-K 0.6/1 kVLm
New UG lines Total
Total Nuevas líneas enterradas0.000.000.000.00
ELECTRICAL WORKS TOTAL
TOTAL TRABAJOS DE ELECTRICIDAD0.000.000.000.00
WORK SUMMARY
RESUMEN TRABAJOS
DEMOLITION WORKS
TRABAJOS DE DEMOLICIÓN0.000.000.000.00
CIVIL WORKS
TRABAJOS DE CIVIL0.000.000.000.00
ELECTRICAL WORKS
TRABAJOS DE ELECTRICIDAD0.000.000.000.00
GRAND TOTAL
GRAN TOTAL0.000.000.000.00

TOTAL MATERIAL COSTS 0.00

TOTAL LABOR COSTS 0.00

TOTAL OTHER DIRECT COSTS 0.00

TOTAL DIRECT COSTS 0.00

OVERHEAD 0.00% 0.00

SUBTOTAL 0.00

PROFIT 0.00% 0.00

TOTAL PROJECT EUROS 0.00

DATE: FIRM NAME:

TITLE: BY:

These costs and overhead and profit percentages will be applied in any possible future modifications

&"Times New Roman,Regular"CONTRACTOR'S COST ESTIMATE BREAKDOWN&"Times New Roman,Bold"