- R2 Paving RFB - OR153 MP12. 6 Crash Paving
- Solicitation number
- S-73000-00017663
- Issued by
- Washington County, Oregon
About this file
This is a Request for Bid (RFB) and Work Order form issued by the Oregon Department of Transportation (ODOT) for on-call Region 2 paving services. The project, designated OR153 MP12.6 Crash Paving, involves 3-inch inlay paving on Oregon Route 153 at milepoint 12.60 to repair damaged asphalt concrete pavement resulting from a truck rollover. Work includes cold planing of existing pavement, placement of dense asphalt concrete mixture, application of longitudinal markings matching existing specifications, installation of rumble strips, and sawcutting vertical edges at inlay termination points. The project encompasses seven pay items with estimated quantities including mobilization (1 lump sum), temporary work zone traffic control (1 lump sum), pollution control plan (1 lump sum), cold plane pavement removal at 373 square yards, level 3 dense ACP mixture at 63 tons, hi-build paint for 445 linear feet, and continuous rumble strips for 0.027 miles. The bid submission deadline is August 20, 2026, at 2:00 p.m., with required project completion by October 30, 2026. The work will be performed in Yamhill County.
This procurement is restricted to holders of the existing On-Call Region 2 Paving Price Agreement, meaning only pre-qualified contractors may submit bids. The project requires compliance with domestic preference requirements under ORS 279C.303 and State Buy America Provisions as outlined in Price Agreement Exhibit A. If the total bid price exceeds $50,000, contractors must comply with prevailing wage rates established by Oregon's Bureau of Labor and Industries as of July 5, 2026. Traffic control restrictions prohibit holiday and weekend closures and lane closures during commute periods (6:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. Monday through Thursday), with work required to be off-highway by noon on Fridays. Portable changeable message signs must be placed a minimum of five days in advance of any lane closures. ODOT Project Manager Cody Stone (503-953-6334, Cody.Stone@ODOT.Oregon.gov) is the designated point of contact for this work order.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00017663_bid tab.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Work Order
| REQUEST FOR BID AND RESULTING WORK ORDER |
| On-Call Region 2 Paving |
| INSTRUCTIONS: ODOT will fill in all information below except Contractor Information, Work Order Number (to be added upon award of Work Order), and pricing. ODOT will provide a list of bid items and their estimated quantities. Contractor must complete the Contractor Information section, including a signature, and insert unit and total prices for all bid items. Contractor must submit its bid by uploading the completed Request for Bid/Work Order form to the Attachments tab for the project in OregonBuys and entering the total bid price on the Items tab. |
Request for Bid Number: S-73000-00017663 Work Order Number:
Issue Date: 8/7/2026 Bid due date and time: 8/20/2026 2:00 pm
Project Name: OR153 MP12.6 Crash Paving
Project description (include milepoint locations):
3" inlay paving on OR153 at MP12.60, full width edge of pavement to edge of pavement to repair damaged ACP from a truck rollover. Shoulder rock import is not required, but contractor shall rake the existing rock along the work zone up to grade with edge of ACP and compact it (work is incidential to paving). Longitudinal markings to match existing color, layout/location, and material as existing. Rumble strips to match existing. Sawcut/mill a vertical edge at ends of inlay paving per RD610.
| ODOT Project Manager Name and Phone number: Cody Stone 503-953-6334 |
| ODOT Project Manager Billing Address (may be an email): Cody.Stone@ODOT.Oregon.gov |
ODOT Site Representative (if different than ODOT Project Manager):
Required Completion Date: October 30, 2026
CONTRACTOR INFORMATION
Contractor (COMPANY) Legal Name:
Address:
Contact Person: Email:
Phone: CCB #:
Contractor's On-Call Region 2 Paving Price Agreement Number: PO-73000-
Contractor’s signature below indicates its firm offer to provide the Services described in this Work Order in accordance with all terms, conditions, and specifications contained in the Price Agreement referenced above, and any additional specifications contained within this Work Order and its attachments. The Work Order is not effective until it is signed by ODOT's Procurement Authority, and ODOT issues a notice to proceed.
Contractor Signature: Date:
| ODOT Signature (Procurement Authority): | Date: |
| ANTICIPATED WORK ITEMS (PAY ITEMS) | |
| This Work Order indicates an estimate of services/quantities required. Payment to Contractor will be made based on actual quantities provided/performed: |
| Item | Description | Est. Qty. | Unit | Unit Price | Total Price |
| 1 | Mobilization | 1 | LS | $ - 0 | |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | $ - 0 | |
| 3 | Pollution Control Plan | 1 | LS | $ - 0 | |
| 4 | Cold Plane Pavement Removal, 3" Deep | 373 | SQ YD | $ - 0 | |
| 5 | Level 3, 1/2" Dense ACP Mixture (PG64-22) | 63 | TON | $ - 0 | |
| 6 | Hi-Build Paint, Extruded or Sprayed, Surface | 445 | FOOT | $ - 0 | |
| 7 | Continuous Rumble Strips | 0.027 | MILE | $ - 0 | |
| $ - 0 | |||||
| PROJECT SPECIFIC REQUIREMENTS |
This project requires compliance with the domestic preference requirements of ORS 279C.303. Contractor shall comply with Price Agreement Exhibit A - State Buy America Provisions.
X If the total price is over $50,000, this project requires payment of the following prevailing wage rates, which are available online at http://www.oregon.gov/boli/WHD/PWR/Pages/pwr_state.aspx:
The “PREVAILING WAGE RATES for Public Works Contracts in Oregon” dated July 5, 2026
| County where the work will be performed: Yamhill |
| The following attachments are incorporated into this Request for Bid and any resulting Work Order: |
X One or more traffic lanes may be closed when allowed, shown, or directed during the following periods of time:
No Holiday or weekend closures.
No lane closures during commute times (6AM-9AM and 4PM-6PM Monday-Thursday).
Off highway by noon on Friday. (9:00am-12:00pm)
X Portable Changeable Message Signs (PCMS) shall be placed a minimum of 5 days in advance of any ramp or lane closure to alert the public of the closure. The location of the PCMS and the message on the PCMS shall be submitted to the Project Manager as part of the Contractor’s proposed TCP.
Traffic will be allowed on the cold planed surface up to ____ calendar days after removing the existing surface. Sweep and clean the cold planed surface before opening to traffic.
COMMENTS & SPECIAL INSTRUCTIONS: