00013217 Preliminary Bid Results.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- I-5: Rice Hill Bridge Deck Repairs
- Solicitation number
- S-73000-00013217
- Issued by
- Deschutes County, Oregon
About this file
The file is a Preliminary Bid Results spreadsheet from the Oregon Department of Transportation (ODOT) for the I-5 Rice Hill Bridge Deck Repairs project, involving bridge deck reconstruction at Interstate 5 Milepost 148.10 in Douglas County. The bid solicitation was issued on 4/8/25 with a bid closing date of 4/8/2025 at 2:00 pm, and three contractors submitted bids: Oregon State Bridge Construction, Inc., HP Civil, Inc., and Legacy Contracting, Inc. The project encompasses comprehensive bridge deck removal and reconstruction, with 27 distinct bid line items covering mobilization, temporary traffic protection, signage, flagging, barricades, temporary barriers, erosion control, concrete work, and pavement marking.
The bid results show significant price variation among bidders, with total bids ranging from $492,557 to $697,505. Oregon State Bridge Construction, Inc. submitted the lowest bid at $492,557, while Legacy Contracting, Inc. submitted the highest at $697,505. The project requires substantial completion by May 23, 2025, and final completion by June 23, 2025, with liquidated damages of $700 per calendar day for missed deadlines. Funding appears to be state-based, with strict Buy America provisions mandating that steel, iron, coatings, and manufactured products be produced in the United States. Contractors must be registered in OregonBuys, comply with state prevailing wage rates, and submit comprehensive documentation including bid pricing forms and subcontractor disclosures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATT D ODOT Existing Plans.pdf | ||
| ATT E ODOT Standard Drawings~2.pdf | ||
| 00013217 Invitation to Bid.docx | DOCX document | |
| ATT A Specifications~3.pdf | ||
| ATT B Plans~21.pdf | ||
| HVAC Fan Maintenance for 3 DAS Buildings - Site Visit Sign in Sheet.pdf | ||
| ATT C Bid Pricing Form~1.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 4/8/25 | ||||||
| ITB No. | S-73000-00013217 | BIDDER | |||||
| NAME: | Oregon State Bridge Construction, Inc. | HP Civil, Inc. | Legacy Contracting, Inc. | ||||
| Bid Closing: | 4/8/2025 at 2:00 pm | CITY/STATE: | Stayton, OR | Salem, OR | Stayton, OR | ||
| Description: | I-5: Rice Hill Bridge Deck Repairs | CCB#: | 180779 | 202060 | 185342 | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $47,500.00 | $ 47,500.00 | $61,607.25 | $ 61,607.25 | $82,000.00 | $ 82,000.00 |
| 2 | Temporary Protection & Direction of Traffic | 1 | LS | $30,000.00 | $ 30,000.00 | $83,250.00 | $ 83,250.00 | $65,000.00 | $ 65,000.00 |
| 3 | Temporary Signs | 520.0 | SQFT | $23.00 | $ 11,960.00 | $25.00 | $ 13,000.00 | $36.00 | $ 18,720.00 |
| 4 | Sequential Arrow Signs | 1 | EACH | $7,500.00 | $ 7,500.00 | $600.00 | $ 600.00 | $2,450.00 | $ 2,450.00 |
| 5 | Portable Changeable Message Signs | 2 | EACH | $17,500.00 | $ 35,000.00 | $1,600.00 | $ 3,200.00 | $3,950.00 | $ 7,900.00 |
| 6 | Radar Speed Trailer | 2 | EACH | $3,000.00 | $ 6,000.00 | $250.00 | $ 500.00 | $8,650.00 | $ 17,300.00 |
| 7 | Flaggers | 160.0 | HOUR | $75.00 | $ 12,000.00 | $72.00 | $ 11,520.00 | $71.00 | $ 11,360.00 |
| 8 | Temporary Barricades, Type III | 2 | EACH | $150.00 | $ 300.00 | $200.00 | $ 400.00 | $280.00 | $ 560.00 |
| 9 | Temporary Plastic Drums | 102 | EACH | $45.00 | $ 4,590.00 | $45.00 | $ 4,590.00 | $82.00 | $ 8,364.00 |
| 10 | Temporary Striping | 300.0 | FT | $15.00 | $ 4,500.00 | $15.00 | $ 4,500.00 | $15.50 | $ 4,650.00 |
| 11 | Stripe Removal | 230.0 | FT | $15.00 | $ 3,450.00 | $15.00 | $ 3,450.00 | $15.50 | $ 3,565.00 |
| 12 | Temporary Barrier | 525.0 | FT | $35.00 | $ 18,375.00 | $33.00 | $ 17,325.00 | $34.00 | $ 17,850.00 |
| 13 | Temporary Impact Attenuator, Sand Barrel System | 1 | EACH | $4,150.00 | $ 4,150.00 | $4,150.00 | $ 4,150.00 | $5,400.00 | $ 5,400.00 |
| 14 | Moving Temporary Impact Attenuator, Sand Barrel System | 1 | EACH | $1,750.00 | $ 1,750.00 | $1,750.00 | $ 1,750.00 | $1,850.00 | $ 1,850.00 |
| 15 | Temporary Impact Attenuator, Truck Mounted | 1 | EACH | $4,200.00 | $ 4,200.00 | $5,000.00 | $ 5,000.00 | $6,500.00 | $ 6,500.00 |
| 16 | Reflective Barrier Panels | 62 | EACH | $20.00 | $ 1,240.00 | $20.00 | $ 1,240.00 | $22.00 | $ 1,364.00 |
| 17 | Repair Temporary Impact Attenuator, Truck Mounted | 2 | EACH | $1.00 | $ 2.00 | $1.00 | $ 2.00 | $150.00 | $ 300.00 |
| 18 | Repair Temporary Impact Attenuator, Sand Module | 16 | EACH | $1.00 | $ 16.00 | $1.00 | $ 16.00 | $110.00 | $ 1,760.00 |
| 19 | Minimum Deflection Bridge Temporary Barrier | 150.0 | FOOT | $80.00 | $ 12,000.00 | $75.25 | $ 11,287.50 | $125.00 | $ 18,750.00 |
| 20 | Temporary Work Access and Containment | 1.0 | LS | $80,000.00 | $ 80,000.00 | $35,000.00 | $ 35,000.00 | $88,235.00 | $ 88,235.00 |
| 21 | Erosion Control | 1 | LS | $5,000.00 | $ 5,000.00 | $2,000.00 | $ 2,000.00 | $2,200.00 | $ 2,200.00 |
| 22 | Pollution Control Plan | 1 | LS | $1,000.00 | $ 1,000.00 | $500.00 | $ 500.00 | $1,350.00 | $ 1,350.00 |
| 23 | Bridge Removal Work | 1 | LS | $80,000.00 | $ 80,000.00 | $75,000.00 | $ 75,000.00 | $108,395.00 | $ 108,395.00 |
| 24 | Reinforcement, Grade 60 | 1 | LS | $35,000.00 | $ 35,000.00 | $35,000.00 | $ 35,000.00 | $63,255.00 | $ 63,255.00 |
| 25 | Surface Texturing | 182.0 | SQYD | $7.00 | $ 1,274.00 | $33.90 | $ 6,169.80 | $56.00 | $ 10,192.00 |
| 26 | Deck Concrete, Class HPC(IC) 4500 -or- HESC | 1.0 | LS | $80,000.00 | $ 80,000.00 | $228,000.00 | $ 228,000.00 | $142,255.00 | $ 142,255.00 |
| 27 | Pavement Marking Tape, Grooved, Patterned, Wet Weather | 230.0 | FOOT | $25.00 | $ 5,750.00 | $30.50 | $ 7,015.00 | $26.00 | $ 5,980.00 |
| TOTAL | $ 492,557.00 | $ 616,072.55 | $ 697,505.00 |
*Apparent Low bid adjusted for correct quantity
File details come from the government source that posted it. Updated .