This document is a Statement of Qualifications from Jacobs Engineering Group Inc. for an on-call consulting contract with the Arizona Department of Transportation (ADOT) for Multimodal Transportation Planning. The solicitation number is BPM004111, and the document was submitted on May 5, 2022, in Phoenix, Arizona. The contract covers multiple disciplines including Active Transportation Planning, Transportation Sustainability, Intelligent Transportation Systems, Freight and Goods Movement Planning, and Transportation and Safety Planning.
The contract is structured as an indefinite delivery vehicle with not-to-exceed, fully burdened hourly rates for various professional roles, including administrative support, analysts, consultants, engineers, planners, and project managers. The total estimated value across eight disciplines is $6,258,367.55, based on projected hours for each role. Rates range from $70 per hour for administrative support to $290 per hour for principal-level staff. The pricing is flexible, with project budgets to be quoted competitively within the established rate ceilings, and the method of award will be specified in individual task assignments, potentially as not-to-exceed prices or fixed prices by deliverable.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1501 West Fountainhead Parkway, Suite 401 Tempe, AZ 85282 P: 480.966.8188
DUNS: 809218089
Not a DBE
Statement of Qualifications to provide On-Call Consultant
Services for Multimodal Transportation Planning
(Solicitation No: BPM004111)
SUMMARY OF NEGOTIATIONS
SUPPLEMENTAL INFORMATION
BEST AND FINAL OFFER (BAFO)
May 5, 2022
Jacobs Engineering Group Inc.
1501 West Fountainhead Parkway Suite 401 Tempe, AZ 85282 P: 480.966.8188
May 5, 2022
Ms. Kelly Greene Senior Procurement Specialist MD100P, 1739 W Jackson St. STE B Phoenix, AZ 85007
Subject: BPM004111 Multimodal Transportation Planning On-Call Summary of Negotiations – Supplemental/Supporting Information Best and Final Offer (BAFO)
Dear Ms. Greene:
Thank you for providing us the opportunity to address the items requested by the evaluation panel and provide a ‘Best and Final Offer’ on the above referenced solicitation. We have addressed the evaluation panel’s requests for supplemental information for the disciplines identified below in our package sent April 27th.
Discipline 2 – Active Transportation Planning Discipline 3 – Transportation Sustainability Discipline 5 – Intelligent Transportation Systems Discipline 6 – Freight and Goods Movement Planning Discipline 8 – Transportation and Safety Planning Pricing – After reviewing our rates, we believe them to be consistent with industry standards. No changes have been made to our original rate sheet.
As, such, our BAFO includes no changes from our supplemental information package submitted on April 27th, 2022.
Thank you for your consideration. If you have any questions, or need any additional information, please do not hesitate to contact Shanthi Krishnan at (480) 707-2984 (cell) or via email at shanthi.krishnan@jacobs.com.
Respectfully submitted, JACOBS
Troy Sieglitz, PE Shanthi Krishnan, PE, PTOE, RSP1
Project Principal & Authorized Signatory Project Manager & Contract Manager
ADOT Transportation Planning On-Call | 1
DISCIPLINE 2. ACTIVE TRANSPORTATION PLANNING
I. PROJECT MANAGER
• Project Manager - Can you provide examples of the PM’s state experience related to the Discipline?
SHANTHI KRISHNAN, PE, PTOE, RSP1: As a Project Manager and Senior Traffic Engineer, Shanthi has worked on multiple aspects of Active Transportation Planning projects at the local, county, and state level.
The two project examples that Shanthi has worked for the State that include Active Transportation Planning elements are:
1. ADOT, US 60X, Sossaman Road to Meridian Road – Comprehensive Transportation Study, Mesa/Apache Junction, AZ The US60X corridor study stemmed directly from ADOT’s desire to improve safety and mobility along the corridor as there were a significantly number of pedestrian and bicycle crashes. The Comprehensive Transportation Study:
• Involved a thorough technical, collaborative process involving affected parties along the US60X corridor, including strategic communications and messaging to local jurisdictions, regional agencies, stakeholders, and the general public.
• Focused on developing context-sensitive solutions; addressed neighborhood access and circulation; analyzed active transportation facilities and designs for their economic, public health, and equity impacts; considered local government planning standards; and developed alternatives that promote safe bicycle and pedestrian activity along the corridor.
• Completed robust review, mapping, and analysis of 5-year historic pedestrian and bicycle related crashes and developed low-cost, short- and long-term safety countermeasures to address one of the highest pedestrian and bicycle-related crash corridors in the state. Stakeholder consensus building and field assessment and scoping reviews also occurred with team members from ADOT, Mesa, Apache Junction, MCDOT, and MAG.
• Included a draft and final report covering purpose and need, stakeholder outreach plan, current and future conditions, roadway conditions, evaluation of preliminary improvement concepts, environmental overview, stakeholder and public outreach and 15% design plans with cost estimates.
This study is guiding the pedestrian and bicycle safety investments along this corridor consistent with ADOT’s Active Transportation Program, Pedestrian and Bicycle Safety Action Plan.
Shanthi’s Role: Shanthi served as the Senior Traffic Engineer and also conducted QA/QC reviews. She guided the safety analysis, evaluated corridor traffic operations, worked on short-term/long-term countermeasures and alternatives development to promote active transportation, and contributed to various sections of the report. Shanthi also actively engaged in stakeholder outreach.
Relevant Project Elements
• 5-year Bicycle and Pedestrian
Crash Analysis and Evaluation
• Existing/Future Conditions
Analysis
• Traffic and Safety Analysis
• Bicycle and Pedestrian Facilities
Connectivity Evaluation
• Context-sensitive and Complete
Streets Implementation Strategies
• Neighborhood-scale access and circulation
• Stakeholder and Public Outreach
ADOT Transportation Planning On-Call | 2
2. ADOT, San Carlos Apache Tribe (SCAT) – Long Range Transportation Plan (LRTP), San Carlos Apache Tribe, AZ This LRTP is a joint effort between SCAT and ADOT to evaluate the effectiveness of the implemented recommendations from the previous LRTP and provide updates to meet current trends/standards. This 20-year plan will guide decisions and prioritize transportation investments through a programmatic approach to multimodal transportation improvements, including active transportation modes, in SCAT communities. The goals of the LRTP include enhancing sustainability, safety, accessibility, mobility, livability, and economic vitality, while maintaining environmental and cultural sensitivity. The LRTP:
• Conducted a thorough evaluation of the existing multimodal transportation systems conditions for the entire San Carlos Reservation.
• Evaluated the existing bicycle and pedestrian amenities and facilities, conducted a safety review, addressed neighborhood access and circulation, addressed special needs for senior and children (especially the High School and Hospital), focused on developing context-sensitive solutions, considered local government planning standards, and developed alternatives that promote safe bicycle and pedestrian activity for SCAT communities.
• Identified roadway, safety, intersection, bicycle, pedestrian and trail, and transit improvements in addition to maintenance activities and an implementation plan.
This LRTP will guide safety, accessibility, mobility, livability for the SCAT residents consistent with ADOT’s Active Transportation Program.
Shanthi’s Involvement: As the project manager, Shanthi managed/guided the data collection efforts, development of the long-range plan, and cost estimates for the maintenance activities; provided input into the implementation plan; and contributed to various sections of the report. She is currently leading the task to transfer all the data collected into the BIA Roads Inventory Field Database Systems (RIFDS).
Shanthi maintains ongoing and active coordination with the Tribe and BIA.
ADOT Transportation Planning On-Call | 3
II. TEAM
• Team - Can you provide examples of team experience in: safety engineering, active transportation?
SAFETY ENGINEERING: Our proposed team brings has extensive experience in safety planning, analysis, and safety engineering. This team has worked on small- and large-scale projects for ADOT and other agencies in finding solutions to improve public safety for all road users. Here are examples of the types of projects this team brings significant experience in:
• Safety evaluations and studies
• Historical/predictive-safety crash analysis
• Road Safety Assessments (RSA)
• Roadway feasibility studies
• Roadside safety studies
• Small Area Transportation Studies (SATS)
• Safe Routes to School (SRTS) and bike/ped safety studies
• ADA, bike/ped facilities assessment/analysis
• Lane departure and run-off-road crash safety studies
• Local Area Safety Studies (LASS)
• Bottleneck safety studies, ADOT
• Safety Engineering & Design (ADOT HSIP)
Our team is recognized for our exceptional work in the areas of safety analysis, evaluation of countermeasures, and improving safety through design. Three team members are certified Road Safety Professionals (Level 1) with experience analyzing crash data, identifying crash contributing factors, and developing short- and long-term countermeasures. We utilize crash data to develop ‘hot-spot’ maps using GIS to pinpoint areas of high crash frequency. These crash ‘hot-spot’ maps were used in three recent ADOT/LPA rural highway projects where the primary goal was to mitigate run-off-road crashes. Design solutions we develop include: 1) advanced signing to warn drivers of curves and their severity; 2) rumble-strips to alert drivers of impending roadway departure; 3) shoulder treatments to improve the chance of recovering control of the vehicle if it does leave the road; and 4) clear zones and crash barriers to reduce the severity of the outcome if a vehicle does leave the road. Jacobs is also advancing the state-of-practice in pedestrian safety through the analysis of near-misses using Drone footage at urban intersections.
Our team has experience in advancing the short- and long-term safety countermeasures developed from various types of safety studies into final design solutions that are implemented in the field. Some of the examples of the team in the area of safety engineering include:
1. ADOT, Safe Routes to School Improvements (SRTS) Improvements PA and Final Design, Gilbert, AZ
We developed a Project Assessment (PA), ADA Evaluation Report, and the Final Design (PS&E) package for three pedestrian crossings to improve safety for schools in Gilbert, AZ. This included the design of two pedestrian hybrid beacons (HAWKs) and a Rectangular Rapid Flashing Beacon (RRFB) in addition to ADA and sidewalk improvements. The design was developed in coordination with the Town of Gilbert and followed the ADOT Project Development process. Utility, right-of-way and environmental clearance were also completed prior to the development of the bid-ready package.
Project Team and Roles on the Project:
• Troy Sieglitz – Principal
• Shanthi Krishnan – Project Manager
• Allen Barakovic – Traffic/Project Engineer
• Judah Cain – Roadway Engineer
ADOT Transportation Planning On-Call | 4
2. ADOT, Stockton Hill Road from MP 6.75 to MP 21.75, Mohave County, AZ The 15 mile Stockton Hill Road corridor, from Fountain Hills Road to Cedar Canyon Drive, is located north of Kingman in Mohave County. It is experiencing several safety issues with a high number of run-off-the-road related fatal/serious crashes. The safety countermeasures identified included centerline and edgeline rumble strips along with speed feedback signs along the entire corridor. Jacobs team developed the final PS&E for the installation of the countermeasures in addition to obtaining the necessary clearances for environmental, right-of-way, and utilities.
Project Team and Roles on the Project:
• Troy Sieglitz – Principal
• Anil Mudigonda – Project Manager
• Shanthi Krishnan – QA/QC
• Allen Barakovic – Sr. Traffic Engineer
• Judah Cain – Roadway Engineer
• Zachary Allard – GIS Analyst
• Isaiah Rubin – Engineer
• Jordan Rae Aguirre - Engineer
3. ADOT/MAG/MCDOT/City of Phoenix, Road Safety Assessments (RSAs), Various Locations, AZ
Jacobs’ local staff have led and conducted numerous RSAs for ADOT, MAG, MCDOT, and other agencies as part of an independent multi-disciplinary team of experts including roadway engineers, traffic engineers, police, emergency medical services workers and a human factors expert. The RSA team evaluates the safety of all road users from 4 E’s of safety perspective: Engineering, Education, Enforcement and Emergency Medical Services; reports on potential road safety issues; develops short-and long term safety countermeasures; and identifies opportunities for safety improvements.
• ADOT’s RSA Program: Jacobs conducted the SR87/SR260 RSA, SR347 Corridor RSA, Bottleneck Studies Groups C & D
• MAG’s RSA Program: Jacobs led and conducted 15 multidisciplinary RSAs
• MCDOT’s Road Safety Evaluation Program: Jacobs led and conducted RSAs & developed PAs at
6 intersections
• City of Phoenix T2050 Program: Jacobs has conducted (3) PAs and (1) Safety Assessment
Project Team and Roles on the Project:
• Troy Sieglitz – Principal
• Shanthi Krishnan – Project Manager
4. ADOT, Bottleneck Safety Studies (I-17/I-10/US60/SR101 Corridors - Groups C & D), Maricopa County, AZ Our team conducted Bottleneck Safety Studies and Safety Assessments for 7 segments of valley freeways. The scope included reviewing traffic/crash data, conducting owner/stakeholder meetings, leading field reviews with safety experts, and developing short- and long-term safety countermeasures to mitigate crashes. The project scope included review of the operations on the mainline and at the interchanges during peak hours, crash data analysis, INRIX data analysis, stakeholder kick-off/debrief meetings, develop short- and long-term solutions, and prepare draft/final reports.
Project Team and Roles on the Project:
• Troy Sieglitz – Principal
• Shanthi Krishnan – Project Manager
• Anil Mudigonda – Sr. Traffic Engineer
• Allen Barakovic – Sr. Traffic Engineer
• Isaiah Rubin – Traffic Engineer
ADOT Transportation Planning On-Call | 5
5. MCDOT, MC 85 Corridor (Baseline Road to Cotton Lane) Safety Improvements, Maricopa County, AZ We developed the preliminary conceptual design, scoping and final design packages for this 9.2-mile corridor, identified as part of MCDOT’s Safety Assessment Program. Our team developed and tailored low-cost safety countermeasure solutions to mitigate the crashes patterns identified in the crash analysis to improve traffic operations and safety from Baseline Road to Cotton Lane. We developed a Corridor Project Prioritization Matrix and grouped the improvements into smaller stand-alone packages for implementation.
Project Team and Roles on the project:
• Troy Sieglitz – Principal
• Shanthi Krishnan – Project Manager
ACTIVE TRANSPORTATION: The following two examples demonstrate our team’s Arizona experience in Active Transportation (County and Local Agency).
1. MCDOT, Active Transportation Plan (ATP), Maricopa County, AZ
Jacobs managed Maricopa County’s first ATP. The Plan ultimately provided a blueprint for a complete and accessible active transportation network that connects people of all ages and abilities with destinations across the County while providing fun, healthy, and convenient transportation options. The plan included:
• Inventory and assessment of existing pedestrian and bicyclist facilities on MCDOT maintained roadways to identify deficiencies, travel patterns, and system gaps.
• Comprehensive safety analysis to identify areas with a high crash risk potential and locations with historically high pedestrian/bicyclist crash rates.
• Develop countywide improvement recommendations, including strategic communications, education and awareness programs, low-cost safety countermeasures, and policy modifications.
Project Team and Roles on the project:
• Alex Quintero – Planner
• Shanthi Krishnan – QA/QC
This study is guiding the active transportation investments throughout Maricopa County.
Relevant Project Elements
• Active Transportation Plan
• Bicycle and Pedestrian Plan and
Evaluation
• Existing and Future Conditions
Analysis
• Traffic and Safety Analysis
• Gap Analysis and Systems
Assessment
• ADA Evaluation
• Bicycle and Pedestrian Connectivity
Evaluation
• Implementation Strategies
• GIS Data Inventory and Analysis
ADOT Transportation Planning On-Call | 6
2. MAG/City of Glendale, Glendale ATP, Glendale, AZ As part of the FY2018 MAG Bicycle and Pedestrian Master Plans and First Time Updates On-Call, Jacobs assisted the City of Glendale in developing a city-wide blueprint for a complete and accessible active transportation network. The plan includes a complete inventory of the existing active transportation network, including facility locations, conditions, gaps. A system assessment was performed to identify areas with a high demand for walking and biking as well as those locations underserved by active transportation. A high-level safety analysis was also performed to identify areas of high pedestrian and bicycle crashes. After examining the existing conditions and identifying system needs, a prioritized list of improvements was developed to enhance and expand the city’s active transportation network.
Project Team and Roles on the project:
• Troy Sieglitz – Principal
• Alex Quintero – Planner
• Kim Engesath – Planner
• Shanthi Krishnan – QA/QC
• Active Transportation Plan
• Bicycle and Pedestrian Plan and
Evaluation
• Existing/Future Conditions Analysis
• Safety, Gap Analysis and Systems
Assessment
• ADA Evaluation
• Implementation Strategies
• GIS Data Analysis
ADOT Transportation Planning On-Call | 7
III. FIRM
• Can you provide an example of the Firm’s active transportation experience?
Please refer to the two examples provided under TEAM (section above). They represent Jacobs’ Active Transportation experience.
• Can you provide details of reporting in the examples provided?
1. MCDOT, Active Transportation Plan (ATP), Maricopa County, AZ
The link to access MCDOT’s Active Transportation Plan:
https://www.maricopa.gov/4355/Active-Transportation-Plan
The following pictures represent sample pages from the Final Report of MCDOT’s Active Transportation Plan:
• Cover Page of Report
• Table of Contents
• Project Prioritization Features
• Active Transportation Needs https://www.maricopa.gov/4355/Active-Transportation-Plan
ADOT Transportation Planning On-Call | 8
2. MAG/City of Glendale, Glendale ATP, Glendale, AZ
The link to access the City of Glendale’s Active Transportation Plan:
https://p1cdn4static.civiclive.com/UserFiles/Servers/Server_15209001/File/Departments/Transpor tation/GlendaleATP_FinalReport%20_06102019%20reduced.pdf
IV. ORG CHART
• Org Chart - Missing job titles, can you improve upon this?
The organizational chart for Discipline 2 has been revised as attached. It now reflects each individual’s corporate titles in addition to their contract role(s) per Exhibit 7 of ADOT’s solicitation requirements.
V. PRICING
• Pricing - Can you improve upon this?
After reviewing our rates, we believe them to be consistent with industry standards and adjusted for inflation. We have included our original pricing sheet for your convenience.
https://p1cdn4static.civiclive.com/UserFiles/Servers/Server_15209001/File/Departments/Transportation/GlendaleATP_FinalReport%20_06102019%20reduced.pdf https://p1cdn4static.civiclive.com/UserFiles/Servers/Server_15209001/File/Departments/Transportation/GlendaleATP_FinalReport%20_06102019%20reduced.pdf
QA/QC
Scott Richman, AICP, PMP
(Role: Technical Expert / Title: Sr. Planner/Project Manager)
MPD Project Managers Discipline 2: Active Transportation Planning DISCIPLINE TWO
Active Transportation Planning Team Organization*
Project Manager Shanthi Krishnan, PE, PTOE, RSP1
(Role: Project Manager / Title: SW Trans. Planning/Traffic/ITS Group Leader)
Additional Project Manager Carl Seifert, AICP
(Role: Project Manager / Title: Trans. Planner)
Principal-in-Charge Troy Sieglitz, PE
(Role: Principal / Title: Sr. Project Manager)
Bike & Pedestrian Facilities Public & Stakeholder
Outreach & Web Interface/Management
ATP Development, Policy & Analysis
Data Collection, GIS, Inventory & Analysis
Ximena Atterbury, LEED GA (Role: Graphic Designer /
Title: Senior Urban Designer/Planner)
Jordan Rae Aguirre, EIT (Role: Engineer / Title: Traffic Engr.)
Zachary Allard (Role: GIS / Title: GIS Analyst/
Trans. Planner)
Kim Engesath (Role: Analyst / Title: GIS Analyst/
Multimodal Trans. Planner)
Subconsultant Resources
Data Collection and Transportation Planning (Firm: United Civil Group)
Sarah Simpson, PhD, PE (Role: Project Manager / Title: Principal) Keith Winney, PE (Role: Engineer / Title: Sr. Project Manager)
Subconsultant Resources
*All staff identified by name in the organization chart that are not in the Subconsultant Resources box are Jacobs staff. Subconsultant firms and staff are noted within the Subconsultant Resources box. The accompanying discipline two evaluation questionnaire goes into further detail on each person shown above.
Administrative Support Brian Toloczko
(Role: Admin/Financial Support / Title: Project Controls)
Jaqueline Brown (Role: Admin/Financial Support /
Title: Admin. Support Prof.)
Amiee Sanchez (Role: Admin/Financial Support /
Title: Project Controls)
Stephanie Lind, AICP (Role: Planner /
Title: Sr. Trans Planner)
Alexandra Quintero (Role: Planner / Title: Trans. Planner)
Brett Ripkin, AICP (Role: Planner /
Title: Sr. Trans. Planner)
Travis Norton, AICP (Role: GIS / Title: Trans. Planner/
GIS Analyst)
Design, Design Guidelines, & Complete Streets
Judah Cain, PE (Role: Engineer / Title: Trans.
Engineer/Project Manager)
Mounica Vinayakamurthy, PE (Role: Engineer /
Title: Roadway Engineer)
Safety Action Plans, Analysis, Design & Countermeasures
Allen Barakovic, PE, PTOE (Role: Consultant/Engineer / Title: Trans./Traffic Engineer)
Isaiah Rubin, EIT (Role: Engineer / Title: Traffic Engr.)
Ravi Ambadipudi, PE (Role: Consultant / Title: Arizona
Planning Practice Lead)
Sabra Bushey (Role: Planner / Title: Env. Planner)
Nair Barrios, AICP (Role: Technical Expert /
Title: Trans. Planner/Public Involvement Specialist)
Role: Refers to the individual’s contract role per ADOT’s solicitation document.
Title: Refers to the individual’s job title within the firm.
DISCIPLINE 3. TRANSPORTATION SUSTAINABILITY
I. TEAM
• Team - Can you provide a couple additional examples of team members experience related to this discipline?
Some additional examples of the team related to Transportation Sustainability include:
1. MCDOT, Broadway Road Corridor Improvement Study (CIS), Maricopa County, AZ
Jacobs completed the Broadway Road CIS to identify the bicycle and pedestrian improvements as well as improvements for accessibility for Americans with Disabilities Act (ADA) compliance consistent with the goals of MCDOT’s Active Transportation Plan (ATP). The project corridor is a 3.2-mile, four-lane, minor arterial and extends from 90th Street to Meridian Road in eastern Maricopa County and the City of Mesa, serving multiple residential neighborhoods and subdivisions. The CIS outlined short- and long-term capacity, pedestrian and bicycle needs, and developed a prioritization matrix of recommended improvements. Our team:
• Conducted a detailed review of the existing and future features/conditions along the 3.2-mile corridor.
• Developed conceptual alternatives consistent with Complete Streets and Context-Sensitive Solutions (CSS) principles, addressed neighborhood access and circulation needs, evaluated the needs of seniors and children, considered local government planning, and developed three candidate alternatives with input from our public and stakeholder engagement activities.
• Conducted alternatives analysis with specific criteria/performance measures (including the three E’s of sustainability [social equity, economic efficiency, and environmental responsibility]) to illuminate the preferred alternative.
• Created a phased implementation plan along with planning-level cost estimates for future roll out of the improvements to promote livable communities along the corridor.
• Troy Sieglitz – Principal
• Shanthi Krishnan – Project Manager
• Alexandra Quintero – Planner
• Zachary Allard – GIS Analyst
• Allen Barakovic – Traffic Engineer
• Sabra Bushey - Planner
2. Yavapai County, Verde Connect Corridor Study, Yavapai County, AZ
Yavapai County, in cooperation and coordination with ADOT and the local communities and towns, had completed several studies and identified the need for a new north-south corridor between Cornville Road and SR 260. The proposed Verde Connect project is a planning and design effort that:
• Evaluated the feasibility of sustainable few alternatives to improve safety, access, circulation, mobility, and connectivity.
• Developed a design concept report, an environmental overview, traffic modeling and analysis, and a PEL document.
• Included public involvement and agency coordination to build consensus among agencies and stakeholders.
• Troy Sieglitz – Project Manager
• Shanthi Krishnan – QA/QC
• Alexandra Quintero – Planner
• Sabra Bushey - Planner
• Zachary Allard – GIS Analyst
• Allen Barakovic – Traffic Engineer
3. Georgia DOT, Design Treatments Framework Plan, Atlanta, GA
Jacobs provided professional services to develop cohesive, consistent corridor-wide aesthetic guidance to Georgia Department of Transportation (Georgia DOT) to proactively define the design schematics using an organized/well managed process, while defining the framework and opportunities for adjoining communities to promote their identity. The aim of this document was developed as a tool for Georgia DOT to use when coordinating with the adjacent cities, counties, and Community Improvement Districts (CID) stakeholders to identify Complete Streets and CSS to mitigate impacts and address opportunities for local partnerships to help fund these measures.
• Conducted a Visual Impact Assessment (VIA) to identify and assess potential visual impacts along the I-285 corridor as part of the Environmental Impact Statement (EIS) process
• Developed a Design Treatments Framework Plan document
Project Team and Roles on the project:
• Tom Hester – QA/QC Manager
• Ximena Atterbury – Senior Urban Planner
• Madeline Soultz – Graphics (3D)
4. Diriya Gate Development Authority (DGDA), Diriyah Gate II Master Plan Design Guidelines, Kingdom of Saudi Arabia Jacobs provided professional services to develop the Diriyah Gate II (DGII) Master Plan, which provides a framework for Smart Growth, TOD, and mixed-use development laid out in a grid pattern anchored by a Grand Boulevard, crisscrossed by pedestrianized diagonal streets, and embracing the banks of Wadi Hanifah. It also provides both a transition and a connection between DGI and the rest of the capital, while offering a clear structure and identity to this part of the city. DGII aims to establish a new urban identity for the Kingdom. It is a direct expression of the Saudi Vision 2030, offering a multi-functional environment of global status, with a firm commitment to sustainability, pioneering cultural and entertainment facilities, enhanced by extensive use of Smart City technology. DGII is envisaged to be a Parisian-scale, pedestrian-focused mixed-use development in proximity to the historic Diriyah Gate development. Our team:
• Developed a Master Plan Framework focused on the objectives of creating a mixed-use, well connected, and sustainably innovative development
• Developed Master Plan Design Guidelines that included multimodal/sustainable transportation elements, such as walking, bicycling, micro-mobility, and electric vehicle infrastructure.
• The Transportation Strategy included combination of a rich mix of uses with the dense mobility network , an inviting public realm that is safe, shaded and well designed. And underpinning the strategy smart mobility solutions will be offered to residents and visitors, combining parking, public transport, and e-mobility.
• The core environment and sustainability principles embedded in the design of DG II are the optimization of resources through the management and circular reuse of waste; the promotion of active mobility and a healthy lifestyle; and the use of smart city technology for asset management and operational efficiency.
• Tom Hester – QA/QC
• Ximena Atterbury – Senior Urban Planner
• Neerja Dave – Urban Designer / Graphics (3D)
II. ORG CHART
• Org Chart - Missing job titles, interrelationship unclear, would you like to improve upon this?
The organizational chart for Discipline 3 has been revised as attached. It now reflects each individual’s corporate titles in addition to their contract role(s) per Exhibit 7 of ADOT’s solicitation requirements.
III. PRICING
• Pricing - Can you improve upon this?
MPD Project Managers Discipline 3: Transportation Sustainability
DISCIPLINE THREE
Transportation Sustainability Team Organization*
Project Manager Tom Hester
(Role: Project Manager / Title:
Principal Urban Designer & Integrated
Mobility Solutions Regional Leader )
Additional Project Manager Ximena Atterbury
(Role: Graphic Designer / Title: Senior Urban Designer/Planner)
Subconsultant Resources
Task Lead Alexandra Quintero
(Role: Planner / Title: Trans. Planner)
Transportation Sustainability
Transportation Engineer/ Traffic Engineering, Safety Allen Barakovic, PE, PTOE
(Role: Engineer / Title: Trans./Traffic Engineer)
Transportation Planner/Environmental Sabra Bushey
(Role: Planner / Title: Env. Planner)
Urban Designer & Planner - TOD and Neighborhood Scale Planning and Design Travel Needs
Neerja Dave (Role: Graphic Designer / Title: Architect, Urban Designer )
Urban Designer: Zoning Codes, Performance Based Codes
Maren Moegel, LEED AP PMP (Role: Technical Expert / Title: Urban Designer, Master Planner)
Graphics 3D Madeline Soultz
(Role: Graphic Designer / Title: Urban Planner)
DOT Experience:
Smart Growth & Smart Transportation
Patrick McGrath, AICP (Role: Consultant / Title: Sr. Trans. Planner)
*All staff identified by name in the organization chart are Jacobs staff. The accompanying discipline three evaluation questionnaire goes into further detail on each person shown above.
Principal-in-Charge Troy Sieglitz, PE
(Role: Principal / Title: Sr. Project Manager)
GIS Analyst Data Analysis, Mapping
Zachary Allard (Role: GIS / Title: GIS Analyst/Trans. Planner)
Administrative Support Brian Toloczko
(Role: Admin/Financial Support / Title: Project Controls)
Jaqueline Brown (Role: Admin/Financial Support /
Title: Admin. Support Prof.)
Amiee Sanchez (Role: Admin/Financial Support /
Title: Project Controls)
Role: Refers to the individual’s contract role per ADOT’s solicitation document.
DISCIPLINE 5. INTELLIGENT TRANSPORTATION SYSTEMS
I. PROJECT MANAGER
Project Manager- Can you provide an example of the PM’s experience if any in TSMO Planning and in ITS Architecture Development?
ANIL MUDIGONDA, PE, PTOE, RSP1: Anil Mudigonda brings more than 18 years of multi-state professional experience as a project manager/task lead in a range of traffic and transportation engineering projects.
Anil is a hands-on project manager that has broad range of technical experience in planning, development and management of Intelligent Transportation Systems (ITS), traffic signals, connected/automated (CV/AV) technology implementation, transportation planning, wayfinding signage, signing & striping, traffic corridor and safety studies. Anil has successfully managed and led several multi-discipline projects for ADOT and several local agencies.
Below is a recent project example of Anil’s experience in the area of TSMO Planning and ITS Architecture Development:
• MAG, Northern Parkway ITS Infrastructure Needs Assessment Study, Peoria/Glendale, AZ The Northern Parkway project corridor extends 9 miles from State Route 303 Loop to State Route 101 Loop and lies within the jurisdictions of: City of Glendale, City of Peoria, City of El Mirage, ADOT and Maricopa County. The study developed a high-level framework of the Intelligent Transportation Systems (ITS) infrastructure equipment and related recommendations for the Northern Parkway corridor. As part of the study, Jacobs conducted the kick-off meeting and the stakeholder’s meeting with the Northern Parkway Program and an inventory of the existing ITS/Traffic signal infrastructure. Jacobs also identified the existing traffic concept of operations (ConOps) and conducted stakeholder interviews to determine the proposed corridor traffic management concept. A preliminary implementation plan for the proposed ITS infrastructure and a high-level opinion of costs for the project was developed. The proposed ITS infrastructure considered several emerging technologies such as traveler information including ARID detectors, connected and automated vehicles technologies, real-time traffic monitoring and adaptive signal control technologies.
We have carefully crafted our team to include experts in the area of TSMO Planning and ITS Architecture Development, as demonstrated by the following project example:
• Statewide Transportation System Management and Operations (TSMO Master Plan and Program Support), Maryland State Highway Administration, Maryland Jacobs assisted the Coordinated Highway Action Response Team (CHART) in the development and implementation of the Transportation System Management & Operations (TSMO) Program, including the development and maintenance of the Statewide TSMO Master Plan. Jacobs assisted in TSMO Program development and implementation activities, including the development and maintenance of the State-wide TSMO Master Plan and Strategic Deployment Plan. The effort included coordinating agency-wide efforts related to TSMO
Relevant Project Elements
• Statewide TSMO Masterplan Development and Support
• TSMO Life Cycle Planning
• Preliminary Planning and
ConOps for Tier 1 Deployment
Relevant Project Elements
• TSMO Planning
• MAG ITS Architecture
• Stakeholder coordination with multiple jurisdictions
• ITS inventory
• ConOps development
• Framework for ITS infrastructure improvements
• Planning-level cost estimates projects, preparing and presenting TSMO projects’ transportation needs, costs, user benefits, risks/opportunities, and tracks their progress in the project development process. Jacobs collaborated with multiple agency offices and consultants to develop and update of the ArcGIS web application that presents the information captured in the TSMO Master Plan and Strategic Deployment Plan. As part of this task, we also assisted CHART to prioritize projects, apply for design and construction funding, preparation of briefing documents for Senior Management, and collaboration in preliminary planning and system engineering development processes. Results from this effort led to the Concept of Operations for TSMO System 1 (I-70/US 40/ US 29) and funding for the Tier 1 deployment (I-70). Anil was a senior engineer on this project.
II. TEAM
Team – Can you provide an example of planning experience as it relates to this discipline?
• Intelligent Transportation Systems and Technology (ITST) Master Plan, ACTC, Oakland, CA
Jacobs is leading the effort to create an Intelligent Transportation Systems and Technology (ITST) Master Plan and final design for the Port of Oakland. The master plan will be a guiding document for the Port that will define and prioritize infrastructure investments of technology at the Port to optimize goods movement, improve traffic information and surveillance, create a traffic management center and improve center-to-center communication. Deliverables will also include a Systems Engineering Management Plan (SEMP), Concept of Operations (ConOps), and Technology Scan Report. The ITST Master Plan will guide the implementation of ITS system elements including supporting infrastructure for the future implementation of a Freight Advanced Travelers Information System (FRATIS) in a connected vehicle environment. Now in design, the team of engineers and technologists are designing a complex ecosystem of 14 sub-systems that touch across fiber network expansion, center-to-center communication, camera and RFID deployments enhancing incident detection and transportation security and planning. It also includes developing frameworks for mobile and web applications that enhance existing parking use efficiencies and information to ultimately streamline terminal-drayage operations to reduce arterial queuing and truck emissions.
Project Team and Roles on the project:
• Brian Burkhard – Project Manager
• Anil Mudigonda – Senior Traffic/ITS Engineer
• Shanthi Krishnan– Senior Traffic/ITS Engineer – QA/QC
Team – Can you provide an example of public outreach We typically partner with a Public Involvement and Outreach specialty firms on our Transportation Planning, Scoping and Design studies. Our project managers and key staff will be available as needed at these meetings. Recent projects where public and stakeholder involvement were key to projects success are:
• ADOT, I-10 and SR 210 DCR and COAR, Pima County, AZ Jacobs supported ADOT in conducting a formal public hearing and open house to provide information about the Draft EA and Initial DCR, and to give the community an opportunity to learn more about the project and provide their feedback. Information about the ITS infrastructure were provided to the public.
• ITS master plan
• Systems Engineering
Management Plan
• ConOps development
• RFID Mobile Technology
Deployment
III. FIRM
Firm – Please provide examples of Firm experience in Broadband, and in fiber management, if any Jacobs has extensive experience in Broadband and Fiber management. We have a dedicated team of senior personnel with expertise in communications, fiber management, telecom, electrical and transportation systems management experience working on several “Middle Mile” projects throughout the country. Some examples are included below:
1. North FL Broadband Authority, Middle Mile Microwave Network Development, Tallahassee, FL Jacobs staff provided Program Management and Construction Management services to the North Florida Broadband Authority for the deployment of a $30 million middle mile microwave network that is being funded through a federal BTOP grant. The program is intended to support broadband connectivity in the rural areas of northern Florida. Working closely with the NFBA leadership team, including NFBA’s General Manager and Jacobs staff led all procurement activities associated with this assignment, from development of procurement documents through proposal evaluation, vendor selection, and contract negotiations. Specifically, we coordinated the successful procurement of (1) Fiber Access Points to provide backhaul to NFBA data centers, (2) Network Operator services, including network operations, monitoring, and trouble-ticket management, and (3) Field Services contractors to provide preventive and reactive maintenance services for NFBA.
2. MassDOT, Massachusetts Emergency Transportation Fiber Optic Network (METFON), Boston, MA The METFON project was a Statewide Emergency Allocated Fiber Optic Network connecting all emergency response and critical incident agencies, in the state of Massachusetts, over a proposed 40GigE Enterprise Network. Two of these agencies, the Massachusetts Department of Transportation (MassDOT), and the Registry of Motor Vehicles in Quincy, MA were separated by over five miles of heavily urbanized terrain, which made a new fiber optic installation problematic. Jacobs designed a licensed digital microwave communications system to close the gap between these two agencies but still provide the maximum throughput of 1Gps. The wireless design incorporated sophisticated radio equipment utilizing dual-polarized transmission paths to minimize equipment complexity and cost while maximizing available bandwidth.
3. Delaware River Port Authority, Broadband Communications Options, Camden, NJ Jacobs evaluated the feasibility of broadband communications options to address DRPA requirements associated with the Central Operations Center. Jacobs evaluated the following options to address DRPA’s needs:
• Lease dark fiber connecting all DRPA bridges.
• Lease broadband service from local service provider.
• Build/operate broadband microwave utilizing existing DRPA licenses.
Our staff coordinated (1) the compilation of network maps for dark fiber providers in the region, (2) interviews with broadband service providers regarding service availability and lease rates, and (3) research regarding microwave feasibility, including preliminary pricing for a digital microwave system.
We then developed a feasibility report detailing the capacity, availability, reliability, and pricing of the alternative solutions.
ADOT Transportation Planning On-Call | 4
IV. PRICING
• Can you improve upon this?
DISCIPLINE 6. FREIGHT AND GOODS MOVEMENT PLANNING
I. PROJECT MANAGER
• Project Manager - Does the PM have Air, Rail, or state freight experience? If so please provide an example.
DAN SEEDAH, PHD, PE – PROJECT MANAGER:
Massachusetts Department of Transportation (MassDOT), State of Massachusetts Freight Network and Freight Planning - Understanding the Impacts of COVID-19 Study, Statewide, MA. Role: Project Manager.
Dan serves as the project manager for the State of Massachusetts’ statewide study for MassDOT to analyze the impacts on COVID-19 on their freight network (including rail, highway, and air-related freight). The work plan that Dan developed, and is working on with his team, includes: conducting a detailed quantitative and qualitative assessment of COVID-19’s impacts on Massachusetts’s freight network and developing an impact-certainty about the future matrix (scenario analysis). The quantitative analysis includes truck origin-destination analysis, freight movement and parking, freight monitoring technologies, commercial vehicle crash analysis, air cargo trends, and marine cargo trends. The impact-certainty about the future matrix will be used in examining and prioritizing strategies pertaining to the state’s infrastructure, workforce, operations, and policies that need further attention in the next Massachusetts Freight Plan update.
WILL HOLIK, PHD, PE – PROJECT MANAGER:
Minnesota Department of Transportation (MnDOT), State of Minnesota Freight/Truck Station Location Optimization Plan, Statewide, MN. Role: Project Manager/Principal Investigator.
Will managed and led the development of MnDOT’s plan to optimize the location of maintenance garages and develop and implementation plan for facility replacement based on facility age, condition, and cost savings from the optimization models. The location models optimized maintenance vehicle routes to reduce operational expenses to MnDOT. A benefit-cost analysis was conducted to compare the operational improvements against costs to build new facilities, including land acquisition, site preparation and utility installation, building construction, wages, and fuel costs. The final result was a phased and prioritized implementation plan that indicated whether facilities should be relocated, rebuilt on-site, or combined.
II. FIRM
• Firm - Can you provide an example of the Firm’s experience in state freight if any?
NEW JERSEY DEPARTMENT OF TRANSPORTATION (NJDOT), STATE FREIGHT STRATEGIC PLAN,
STATEWIDE, NJ
Jacobs led a multidisciplinary team in preparing the State of New Jersey’s statewide Freight-Rail Strategic Plan for NJDOT focused on maximizing the economic, environmental, and quality of life benefits of robust highway and rail freight systems. Building upon extensive coordination and input from multiple state agencies, Class I railroads, and shortline/terminal railroads, the study identified issues representing varying degrees of impediment to creating and operating a flexible and efficient freight rail system. These issues range from critical infrastructure improvement needs affecting operational capacity and integrating freight rail operations into local communities. Recommendations include: 1) facilitating the efficient and cost-effective movement of goods to businesses, industries, and consumers; 2) encouraging business and industry retention and growth; 3) improving public safety; 4) creating jobs; 5) reducing greenhouse gases to enhance the quality of life within New Jersey.
DISCIPLINE 6. FREIGHT AND GOODS MOVEMENT PLANNING
III. PRICING
• Pricing - Can you improve upon this?
DISCIPLINE 8. TRANSPORTATION AND SAFETY PLANNING
I. PROJECT MANAGER
• Project Manager - Does the PM have experience in a PM role on an environmental project?
Our proposed Project Managers - Shanthi and Anil have both led and managed Transportation Planning and Safety Planning projects, on which Environmental aspects were important considerations, but not as a project manager on an environmental project. Below, please find supplemental information on Shanthi and Anil’s qualifications regarding projects on which Environmental was KEY:
SHANTHI KRISHNAN, PE, PTOE, RSP1: With over 29 years of experience as a Project Manager and Senior Traffic Engineer, Shanthi has managed, led, and worked on several Transportation Planning and Safety Planning studies and projects where the environmental elements/technical resources played a significant role, including CATEXs, EAs, EISs and PELs. Below are a few of her studies/projects where she served as the project manager or discipline lead and where the scope of work included significant environmental elements:
• ADOT; Statewide Rest Area study (2011 and Current 2022) - Environmental Review; Shanthi is the Project Manager (currently ongoing) for this Study.
• ADOT; I-10 (I-19 to SR 83) and SR 210 (Barraza-Aviation Parkway to I-10) DCR and COAR; ADOT;
AZ – Environmental Assessment (EA) and Finding of No Significant Impact (FONSI). Shanthi was the Discipline Lead for Traffic/ITS/Lighting
• ADOT; State Route 303L (SR-303L) Freeway Management Systems (FMS) Improvements from Northern Avenue to US60, Project Assessment and Final Design; ADOT, AZ – Categorical Exclusion (CE). Shanthi was the Project Manager for this project.
ANIL MUDIGONDA, PE, PTOE, RSP1: Similar to Shanthi, Anil brings over 18 years of experience as a Project Manager and Senior Traffic Engineer. He has led and managed Transportation and Safety Planning projects, but not any that were environmentally driven (such as a standalone CE, EA, or EIS). A few of the projects he has managed with collaboration/interaction with environmental professionals include:
• NDOT; Pyramid Highway/US 395 Connection (Calle De Plata to Queen Way; and new freeway from US-395 to Pyramid Hwy.); Environmental Impact Statement (EIS) – Anil worked on Traffic Analysis and Design for this project.
• ADOT; I-10 (I-19 to SR 83) and SR 210 (Barraza-Aviation Parkway to I-10) DCR and COAR; ADOT;
AZ – Environmental Assessment (EA) and Finding of No Significant Impact (FONSI). Anil led the Change of Access Report Study (COAR) for this project.
• Project Manager - Can you provide an example of the PM’s experience if any with Strategic Transportation Safety Plan (STSP)?
While our proposed Project Managers - Shanthi and Anil have not directly worked on the development of a Strategic Transportation Safety Plan (STSP) they have worked on several projects focused on the ADOT’s 2019 STSP Emphasis Areas – Highway Safety (behavior-related), Intersections, Lane Departure, Pedestrians, and Safety related data. Our team members (Ravi Ambadipudi) have direct experience with developing Regional Strategic Safety Plans for MPO’s and COG’s in Arizona. Below please find supplemental information illustrating Shanthi and Anil’s safety-related experience on STSP projects:
SHANTHI KRISHNAN, PE, PTOE, RSP1: Shanthi brings more than 29 years of safety experience to ADOT.
She brings multi-state experience working on safety projects, including safety studies, safety evaluations, corridor studies and RSAs, and intersection/corridor improvements to mitigate crashes through the identification and implementation of numerous safety countermeasures. Shanthi serves as our local ‘safety’ champion on all design projects and brings a proactive perspective of blending safety into design, and has completed formal training on RSAs through the National Transit Institute (NTI).
She has conducted over 22 RSAs for various local and state agencies and developed safety countermeasures for mitigating crashes using HSM and NCHRP 600 guidelines. In addition to her strong technical and communication skills, Shanthi is a great problem solver and has successfully led and managed several design projects, operational and safety studies for valley agencies. The following projects demonstrate Shanthi’s experience in the area of STSP and its emphasis areas:
• Strategic Highway Safety Program Experience o New Mexico Department of Transportation (NMDOT); Strategic Highway Safety Plan (SHSP) Statewide On-call; NM – Shanthi is the Quality Control (QC) Manager for this contract and supports the team in reviewing their project deliverables. We recently completed the update of the SHSP Data Analysis and Preliminary Designation of Emphasis Areas.
• ADOT STSP Emphasis Area Experience o Highway Safety (behavior-related) – ADOT; Bottleneck Removal Safety Studies/RSAs
(Groups C & D); AZ – Shanthi was the Project Manager.
o Intersections – Shanthi was the Project Manager on all these listed projects
ADOT’s RSA Program: Jacobs conducted the SR87/SR260 RSA, SR347 Corridor RSA MAG’s RSA Program: Jacobs led and conducted 15 multidisciplinary RSAs MCDOT’s Road Safety Evaluation Program: Jacobs led and conducted RSAs & developed
PAs at 6 intersections City of Phoenix T2050 Program: Jacobs has conducted (3) PAs and (1) Safety Assessment o Lane Departure – ADOT; Lane Departure Road Safety Assessment Group B; AZ. Shanthi is the Project Manager o Pedestrians – ADOT; US 60X – Comprehensive Transportation Study; AZ – Shanthi was the Senior Traffic Engineer and QC Manager on this study.
o Safety Data – Crash Analysis on several ADOT projects
ANIL MUDIGONDA, PE, PTOE, RSP1: Anil is a hands-on project manager that brings broad experience in roadway/traffic design and safety implementation projects. From a technical perspective, his experience includes the planning and design of highway/interstate improvements, Safety Planning including Bottleneck Safety Studies; safety enhancements (including centerline/edge line rumble strips and other safety countermeasures), pavement marking and signing, and traffic control/MOT plans. As a project manager, Anil is well known for facilitating stakeholder/team interaction that result in early identification and resolution of safety issues, locally and regionally. However, Anil has not directly worked on a STSP project but worked with Shanthi in the STSP emphasis areas as demonstrated by the following projects:
• ADOT STSP Emphasis Area Experience o Highway Safety (behavior-related) – ADOT; Bottleneck Removal Safety Studies/RSAs
(Groups C & D);…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .