Contractor to provide all labor, materials & equipment to complete Lot 318 Stormwater Pipe… and 2 more items
State & local contract award Virginia Awarded
- Contract number
- PO05486063
- Awardee
- Harlan Construction Co., Inc.
- Contracting organization
- Department of Military Affairs
- Cumulative value
- $429,658
About this award
The Virginia Department of Military Affairs awarded contract PO05486063 to Harlan Construction Co., Inc. on September 30, 2026, with a cumulative value of $429,658.16. The prime contractor is performing a Stormwater Pipe Replacement project at Lot 318, Fort Pickett, located in Blackstone, Virginia. The base work scope includes sawcutting asphalt, fence removal and resetting, loading ramp removal, excavation of failed stormwater piping, installation of new 42-inch lined corrugated metal pipe, connection tie-ins at structures 105 and 103, replacement of existing structures, and asphalt repaving of affected areas. The contract is classified as non-capital construction.
Two change orders were issued during contract performance. Change Order #1, valued at $71,024.21, authorized three weeks of hauling operations using a Caterpillar 320 excavator and two dump trucks with operators to import suitable borrow material and remove unsuitable materials, with proof-rolling but no additional compaction testing or load restrictions. Change Order #2, valued at $5,125.95, addressed unforeseen subsurface conditions whereby the graded area exhibited pumping during proof-rolling activities, requiring the general contractor to establish additional foundation stabilization. The base contract line item was valued at $353,508.
Line items
| Item | Total |
|---|---|
| Contractor to provide all labor, materials & equipment to complete Lot 318 Stormwater Pipe Replacement project. Work can generally be described as sawcutting asphalt, fence removal/resetting, loading ramp removal, excavating old failed stormwater piping, resetting new 42" lined CMP, tieing in… | $353,508.00 |
| CHANGE ORDER #1 - Furnish all labor, fuel, and equipment to provide the following work items: Three weeks of hauling operations, CAT320, Dump truck x2, three operators to import suitable material from borrow pit and haul out unsuitable materials to quarry. All materials and labor included, equipment… | $71,024.21 |
| CHANGE ORDER #2 -Unforeseen activity. Area of grad was found to be "pumping" during proof rolling activity after final grade was established. GC had to establish a more stable foundation in this area. | $5,125.95 |
Award details come from logi.cgieva.com. Updated .
Quick answers
Who was awarded contract PO05486063?
Contract PO05486063 was awarded to Harlan Construction Co., Inc. by Department of Military Affairs in Virginia on September 30, 2026.
How much is contract PO05486063 worth?
Its cumulative value is $429,658.
On GovTribe
See this award's full record
- Every line item and file
- The contract it was ordered under and its other orders
- Similar state and local awards and opportunities
- Ask GovTribe AI about this award