About this award

Equipment Resource LLC has been awarded a contract by the Virginia Department of Energy with a cumulative value of $175,464.35, effective October 5, 2026. All deliverables are directed to Jennifer Dillemuth. The contract encompasses site preparation and erosion control services, including mobilization, clearing and grubbing (1 acre), surveying, excavation (approximately 250 cubic yards plus 150 additional cubic yards), and demolition services. Additionally, the contractor will remove and reinstall a porch structure and manage landfill fees (60 tons).

The contract also includes the delivery and installation of materials and infrastructure components essential to site stabilization and stormwater management. These items comprise Virginia Department of Transportation–specified stone aggregates (VDOT No. 1 Stone, VDOT No. 57 Stone, and VDOT Crusher Run totaling 625 tons), drainage systems (425 linear feet of 6-inch high-density polyethylene underdrain pipe and 36 linear feet of 15-inch HDPE culvert pipe with associated endwalls), sediment control products (silt fence, filter fabric, and erosion control matting), and landscape features (segmental retaining wall, rock check dams, grass-lined ditch, chain link fence, and revegetation services). Equipment rental services for an excavator with rock hammer (15 hours) are also included. The contract does not specify a defined performance period or annual value.

Line items

Item Total
Mobilization (10% limit) 1 Each × $11,087.00 $11,087.00
Clearing and Grubbing 1 Acre × $5,700.00 $5,700.00
VDOT NO 1 Stone 50 Ton × $39.18 $1,959.00
Surveying… 1 Each × $5,100.00 $5,100.00
VDOT No. 57 Stone 475 Ton × $39.16 $18,601.00
Rock Check Dam 3 Each × $350.00 $1,050.00
VDOT Crusher Run 100 Ton × $39.12 $3,912.00
Segmental Retaining Wall 507 × $103.00 $52,221.00
Silt Fence 168 linear feet × $6.18 $1,038.24
Filter Fabric 395 Square Yard × $3.12 $1,232.40
Excavation (approx. 250 yd) 1 Each × $7,750.00 $7,750.00
Underdrain - 6 Inch HDPE 425 linear feet × $38.75 $16,468.75
6 Inch Endwall 2 Each × $671.00 $1,342.00
Grass Lined Ditch 625 linear feet × $5.12 $3,200.00
Access Road 1 Each × $4,500.00 $4,500.00
Demolition 1 Each × $7,484.50 $7,484.50
Porch Removal 1 Each × $2,200.00 $2,200.00
Porch Re-installation 1 Each × $2,900.00 $2,900.00
Chain Link Fence 110 linear feet × $37.85 $4,163.50
Landfill Fee 60 Ton × $65.00 $3,900.00
Revegetation 1 Acre × $2,510.00 $2,510.00
Mobilization 1 Each × $1,682.00 $1,682.00
Excavator with Rock Hammer 15 Hour × $121.20 $1,818.00
HDPE 15" Culvert Pipe 36 linear feet × $54.86 $1,974.96
Additional Excavation 150 Cubic Yard × $33.00 $4,950.00
Erosion Control Matting 8,400 × $0.80 $6,720.00
Show all 26

Award details come from logi.cgieva.com. Updated .

Quick answers

Who was awarded contract PO05403161-V3?

Contract PO05403161-V3 was awarded to Equipment Resource LLC by Virginia Department of Energy on October 5, 2026.

How much is contract PO05403161-V3 worth?

Its cumulative value is $175,464.

On GovTribe

See this award's full record

  • Every line item and file
  • The contract it was ordered under and its other orders
  • Similar state and local awards and opportunities
  • Ask GovTribe AI about this award