Armstrong Complex Generator Load Bank 3-Year Test (4 hours) and 19 more items

State & local contract award Virginia Awarded

Contract number
PO05382180
Awardee
Fidelity Engineering Corp
Contracting organization
Radford University
Cumulative value
$14,525

About this award

Fidelity Engineering Corp has been awarded a contract by Radford University in Virginia with a cumulative value of $14,525.00. The award was issued on June 15, 2026, and encompasses generator load bank testing services across multiple campus facilities. The contract deliverables are directed to Daniel Smith and include both three-year and annual testing protocols of varying durations performed at campus buildings including Armstrong Complex, Boiler House, Dedmon Center, Allen Building, Kyle Hall, Student Recreation & Wellness Center, 915 Tyler Avenue, Peters/Pocahontas/Bolling Halls, Whitt Hall, McConnell Library, Hemphill Hall, Martin Hall, CFTS Building, Moffett Hall, Reed/Curie Halls, Draper/Ingles Halls, Washington Hall, Jefferson/Madison Halls, Muse Hall, and Artis Center.

The contract comprises twenty line items representing load bank testing services. Three-year tests are four-hour duration tests with unit prices ranging from $800 to $1,250, while annual tests are two-hour duration tests with unit prices ranging from $450 to $750. The services ensure operational readiness and compliance testing of backup generator systems across the Radford University campus infrastructure. All work is to be performed at the respective campus locations in Radford, Virginia.

Line items

Item Total
Armstrong Complex Generator Load Bank 3-Year Test (4 hours). 1 Lot × $1,050.00 $1,050.00
Boiler House Generator Load Bank Annual Test (2 hour). 1 Lot × $700.00 $700.00
Dedmon Center Generator Load Bank Annual Test (2 hours). 1 Lot × $450.00 $450.00
Allen Building Generator Load Bank 3-Year Test (4 hour). 1 Lot × $800.00 $800.00
Kyle Hall Generator Load Bank 3-Year Test (4 hour). 1 Lot × $800.00 $800.00
Student Recreation & Wellness Center Generator Load Bank 3-Year Test (4 hour). 1 Lot × $800.00 $800.00
915 Tyler Ave Generator Load Bank 3-Year Test (4 hour). 1 Lot × $800.00 $800.00
Peters/Pocahontas/Bolling Halls Generator Load Bank Annual Test (2 hour). 1 Lot × $450.00 $450.00
Whitt Hall Generator Load Bank 3-Year Test (4 hour). 1 Lot × $800.00 $800.00
McConnell Library Generator Load Bank 3-Year Test (4 hour). 1 Lot × $1,050.00 $1,050.00
Hemphill Hall Generator Load Bank Annual Test (2 hour). 1 Lot × $700.00 $700.00
Martin Hall Generator Load Bank 3-Year Test (4 hour). 1 Lot × $800.00 $800.00
CFTS Building Generator Load Bank 3-Year Test (4 hour). 1 Lot × $1,250.00 $1,250.00
Moffett Hall Generator Load Bank Annual Test (2 hour). 1 Lot × $450.00 $450.00
Reed/Curie Halls Generator Load Bank Annual Test (2 hour). 1 Lot × $700.00 $700.00
Draper/Ingles Halls Generator Load Bank Annual Test (2 hour). 1 Lot × $450.00 $450.00
Washington Hall Generator Load Bank Annual Test (2 hour). 1 Lot × $450.00 $450.00
Jefferson/Madison Halls Generator Load Bank Annual Test (2 hour). 1 Lot × $575.00 $575.00
Muse Hall Generator Load Bank Annual Test (2 hour). 1 Lot × $750.00 $750.00
Artis Center Generator Load Bank Annual Test (2 hour). 1 Lot × $700.00 $700.00
Show all 20

Award details come from logi.cgieva.com. Updated .

Quick answers

Who was awarded contract PO05382180?

Contract PO05382180 was awarded to Fidelity Engineering Corp by Radford University in Virginia on June 15, 2026.

How much is contract PO05382180 worth?

Its cumulative value is $14,525.

On GovTribe

See this award's full record

  • Every line item and file
  • The contract it was ordered under and its other orders
  • Similar state and local awards and opportunities
  • Ask GovTribe AI about this award