Spring PM Inspection and 16 more items
State & local contract award Virginia Awarded
- Contract number
- PO05368531-V2
- Awardee
- Fidelity Engineering Corp
- Contracting organization
- Virginia Department of Transportation
- Cumulative value
- $117,895
About this award
Fidelity Engineering Corp has been awarded contract PO05368531-V2 by the Virginia Department of Transportation on July 28, 2026, with a cumulative value of $117,895.00. The contract encompasses preventive maintenance and testing services for power generation equipment, with all deliverables directed to Wanda Lee Elmore Romeo. Services include spring preventive maintenance inspections (42 units at $170 each), fall preventive maintenance oil and filter changes for equipment ranging from 20-60 kilowatts to 100-400 kilowatts (42 total units), and full load bank testing across multiple equipment capacity ranges from 20 kilowatts to 400 kilowatts (62 total tests).
The contract also provides for technician labor at $95 per hour (500 hours budgeted), technician services during nights, weekends, and holidays at the overtime rate of $142.50 per unit (20 units), supplies, materials, parts, and specialized equipment at the contractor's actual cost (budgeted at $25,000), and mileage reimbursement at state rates totaling 10,000 miles across two separate line items at $0.73 and $0.76 per mile. The contract terms and pricing structure indicate these are recurring maintenance services supporting the operation and reliability of the Virginia Department of Transportation's backup or emergency power generation assets.
Line items
| Item | Total |
|---|---|
| Spring PM Inspection | $7,140.00 |
| Fall PM Oil & Filter Change 20-60KW | $10,530.00 |
| Fall PM Oil & Filter Change 100-400KW | $6,000.00 |
| Full Load Bank Test 20KW | $250.00 |
| Full Load Bank Test 22-25KW | $1,500.00 |
| Full Load Bank Test 40KW | $250.00 |
| Full Load Bank Test 50KW | $1,250.00 |
| Full Load Bank Test 60KW | $3,500.00 |
| Full Load Bank Test 100KW | $750.00 |
| Full Load Bank Test 150KW | $2,250.00 |
| Full Load Bank Test 175-200KW | $900.00 |
| Full Load Bank Test 400KW | $800.00 |
| Technician | $47,500.00 |
| Supplies, Materials, Parts and Specialized Equipment at the Contractors Actual Cost | $25,000.00 |
| Mileage at State Rate | $3,650.00 |
| Technician - Nights Weekends Holidays as approved. (1 1/2 times the technician regular rate). | $2,850.00 |
| Mileage at State Rate | $3,800.00 |
Show all 17
Award details come from logi.cgieva.com. Updated .
Quick answers
Who was awarded contract PO05368531-V2?
Contract PO05368531-V2 was awarded to Fidelity Engineering Corp by Virginia Department of Transportation on July 28, 2026.
How much is contract PO05368531-V2 worth?
Its cumulative value is $117,895.
On GovTribe
See this award's full record
- Every line item and file
- The contract it was ordered under and its other orders
- Similar state and local awards and opportunities
- Ask GovTribe AI about this award