LOWBOY TRUCK and TRAILER CAPACITY LARGE W/OPERATOR and 23 more items
State & local contract award Virginia Awarded
- Contract number
- PO05260589-V3
- Awardee
- C H White Construction Co Inc
- Contracting organization
- Virginia Department of Transportation
- Cumulative value
- $248,325
About this award
The Virginia Department of Transportation (VDOT) awarded contract PO05260589-V3 to C H White Construction Co Inc on September 1, 2026, with a cumulative value of $248,324.65. Services are to be delivered to Fielder, Jaime Cook. The contract encompasses the provision of heavy equipment and specialized labor resources, including equipment with operators such as lowboy trucks and trailers, track loaders, excavators (both standard and with hydraulic breakers), long-reach excavators, dump trucks, and multiple crane capacities ranging from 135 to 225 tons. Ancillary equipment without operators includes air compressors, concrete saws, generators, water pumps, scaffolding, and ladders.
The contract also encompasses labor services across multiple skill classifications, including foremen (954 hours at $68.56 per hour) and skilled laborers (1,880 hours at $42.19 per hour), as well as specialized equipment rental and mobilization services. Additional line items include grout pumps, pile drivers, concrete buckets, hammer drills, and chain saws. Pricing is structured across hourly, daily, weekly, and per-occurrence rate categories, reflecting the varied nature of the equipment and labor services required for the project scope under this VDOT contract.
Line items
| Item | Total |
|---|---|
| LOWBOY TRUCK and TRAILER CAPACITY LARGE W/OPERATOR | $6,328.32 |
| Track loader min 2 CY bucket w/operator | — |
| Excavator track backhoe model 200 komotsu or equal w/operator | $23,921.52 |
| Concrete bucket min 1 CY WO/operator | $21.09 |
| Air compressor min 250 CFM WO/operator | $395.55 |
| Concrete saw, water cooled diamond edge blades WO/operator | $659.25 |
| Generator, min 3500 watts WO/operator | $580.14 |
| HAMMER DRILL, 2 inch DIA HOLE WO/OPERATOR | $36.92 |
| WATER PUMP 3 inch INTAKE WO/OPERATOR | $8,754.01 |
| Scaffold, platform type 8 FT | — |
| Ladder, extension 24 FT | $553.77 |
| Foreman | $65,406.24 |
| Skilled laborer | $79,317.20 |
| CHAIN SAW, MIN 16 inch TO 20 inch BLADE WO/OPERATOR | — |
| Temporary sheet piling | — |
| Grout pump | $4,973.06 |
| Pile driver powered hammer 40,000 FT/LB WO/operator, per week rate | $11,812.96 |
| Mobilization for 135 ton crane exclusively, cost to include setup and dismantling of crane at job site. Price per each occurance | $6,328.38 |
| Crane min 225 ton capacity with operator, 8 HR minimum per day | — |
| Mobilization for 225 ton crane exclusively, cost to include setup and dismantling of crane at job site. Price per each occurance | — |
| Excavator track backhoe w/hydraulic breaker, model 200 komotsu or equal w/operator | — |
| Excavator, long reach min 60 feet, model link belt 250 or equal w/operator | $23,995.40 |
| Dump truck quad axle w/operator | — |
| Crane min 135 ton capacity with operator, 8 HR minimum per day | $15,240.84 |
Show all 24
Award details come from logi.cgieva.com. Updated .
Quick answers
Who was awarded contract PO05260589-V3?
Contract PO05260589-V3 was awarded to C H White Construction Co Inc by Virginia Department of Transportation on September 1, 2026.
How much is contract PO05260589-V3 worth?
Its cumulative value is $248,325.
On GovTribe
See this award's full record
- Every line item and file
- The contract it was ordered under and its other orders
- Similar state and local awards and opportunities
- Ask GovTribe AI about this award