Construction services for various renovations to the 3rd Floor of Merten Hall, which include, new… and 5 more items

State & local contract award Virginia Awarded

Contract number
PO05154333-V5
Awardee
Juniper Construction Co Inc
Contracting organization
George Mason University
Cumulative value
$165,284

About this award

Juniper Construction Co Inc was awarded contract PO05154333-V5 by George Mason University on June 23, 2026, with a cumulative value of $165,283.83. The prime contractor is delivering comprehensive construction services for renovations to the 3rd Floor of Merton Hall in Virginia, encompassing new finishes, furniture installation, mechanical/electrical/plumbing (MEP) modifications, and infrastructure modifications for telecommunications and audiovisual systems. The base contract, valued at $133,265.00, references George Mason University's Project Order No. 011 dated September 24, 2025, with deliverables directed to Caroline Sonner.

The contract includes five change orders totaling $32,018.83, issued between December 2025 and May 2026. These modifications address scope additions including carpet demolition in specified rooms ($1,574.76), electrical connections to variable air volume (VAV) units ($3,004.65), Connectrac modifications ($4,582.14), a second Testing and Balancing mobilization to address ventilation deficiencies ($1,294.63), and sound mitigation measures ($21,562.65). All change orders were processed through formal change request procedures with engineering review and approval documented through WRA, LLP submittals and architectural supplemental instructions.

Line items

Item Total
Construction services for various renovations to the 3rd Floor of Merten Hall, which include, new finishes, new furniture by Mason, MEP modifications and infrastructure modifications for telecommunications and AV. Refer to Mason's Project Order No. 011 dated 9/24/25 1 Each × $133,265.00 $133,265.00
CHANGE ORDER NO. 01 - FCO #001 - Proceed with demoing the carpet in Rooms 3223, 3222, 3139A, 3219, 3202 & 3112 in accordance with WRA, LLP Response to ERFI #002 dated 28 October 2025. Refer to Juniper Construction Company, Inc Change Request dated 04 December 2025 1 Each × $1,574.76 $1,574.76
CHANGE ORDER NO. 02 - FCO #003 - Proceed with providing a electrical connection to the VAV in accordance with WRA, LLP Approved Submittal SA-2 dated 20 October 2025. Refer to Juniper Construction Company, Inc Change Request dated 24 March 2026 1 Each × $3,004.65 $3,004.65
CHANGE ORDER NO. 03 - FCO #002 - Proceed with revising Connectrac to expose the top cover plate in accordance with WRA, LLP email direction dated 14 January 2026. Refer to Juniper Construction Company, Inc Change Request dated 24 March 2026. 1 Each × $4,582.14 $4,582.14
CHANGE ORDER NO. 04 - FCO #004 - Proceed with providing a 2nd TAB mobilization to address inadequate ventilation at existing Terminal Unit #57 as directed by WRA, LLP Submittal Review dated 01 April 2026 for Submittal SA-17 – Testing & Balancing Report. Refer to Juniper Construction Company, Inc… 1 Each × $1,294.63 $1,294.63
CHANGE ORDER NO. 05 - FCO #005 - Proceed with adding sound mitigation in accordance with WRA LLP ASI #02 dated 13 May 2026. Refer to Juniper Construction Company, Inc Change Request dated 14 December 2025 1 Each × $21,562.65 $21,562.65

Award details come from logi.cgieva.com. Updated .

Quick answers

Who was awarded contract PO05154333-V5?

Contract PO05154333-V5 was awarded to Juniper Construction Co Inc by George Mason University in Virginia on June 23, 2026.

How much is contract PO05154333-V5 worth?

Its cumulative value is $165,284.

On GovTribe

See this award's full record

  • Every line item and file
  • The contract it was ordered under and its other orders
  • Similar state and local awards and opportunities
  • Ask GovTribe AI about this award