Campus Safety Repairs - Custom Fence Phase 2 & 3. Fence Installation - Construction of brick pillars… and 2 more items

State & local contract award Virginia Awarded

Contract number
PO05103824-V3
Awardee
Centennial Contractors Enterprises Inc
Contracting organization
Norfolk State University
Cumulative value
$2,142,258

About this award

Centennial Contractors Enterprises Inc was awarded a contract by Norfolk State University in Virginia for campus safety repairs consisting of custom fence construction in phases 2 and 3. The primary scope of work includes construction of brick pillars and fence panels along Corprew Avenue extending from the east side of the William P. Robinson Sr. Technology Center to the west side of the New Resident Building, as well as fence construction along Middle Towne Crescent from an existing brick pillar in front of Spartan Suites Residence Hall to Gate 9. The contract was awarded on August 17, 2026, with an initial line item value of $1,916,710.00, with deliverables to be directed to Kenny Kyle.

The cumulative contract value, inclusive of the base scope and two change orders, totals $2,142,258.41. Change Order 1, valued at $80,164.80, addresses additional tree and brush removal, fence installation and removal, and signage. Change Order 2, valued at $145,383.61, covers additional security system services resulting from a location change necessitated by unforeseen utility locations. These contract modifications reflect scope adjustments typical of construction projects involving site-specific conditions that require field modifications during execution.

Line items

Item Total
Campus Safety Repairs - Custom Fence Phase 2 & 3. Fence Installation - Construction of brick pillars and fence panels for Phase 2, which includes construction along Corprew Avenue from the east side of William P. Robinson Sr. Technology Center to the west side of the New Resident Building. The… 1 Lump Sum × $1,916,710.00 $1,916,710.00
Change Order 1 - A change order is needed to increase the PO amount by $80,164.80 to cover additional tree and brush removal, fence installation and removal, and additional signage. 1 Lump Sum × $80,164.80 $80,164.80
Change Order 2 - A change order is needed to increase the PO amount by $145,383.61 to cover additional services. Security System location change due to unforeseen utility locations. 1 Lump Sum × $145,383.61 $145,383.61

Award details come from logi.cgieva.com. Updated .

Quick answers

Who was awarded contract PO05103824-V3?

Contract PO05103824-V3 was awarded to Centennial Contractors Enterprises Inc by Norfolk State University in Virginia on August 17, 2026.

How much is contract PO05103824-V3 worth?

Its cumulative value is $2,142,258.

On GovTribe

See this award's full record

  • Every line item and file
  • The contract it was ordered under and its other orders
  • Similar state and local awards and opportunities
  • Ask GovTribe AI about this award